Ca Mau accelerates disbursement of public investment capital

NHẬT HỒ |

The slow progress of many key projects is putting pressure on the disbursement target of public investment capital of Ca Mau province.

Disbursement has not met expectations

On July 1, the Ca Mau Provincial Department of Finance said that as of June 22, the locality had disbursed 2,373 billion VND out of a total of 6,959.8 billion VND of public investment capital in 2026 assigned by the Prime Minister, reaching 34.1% of the plan. This level is higher than the national average (26.9%) but still lower than the target of 46% set by the province.

Including the capital source for 2025 extended to 2026 and the additional capital at the end of May 2026, the province's total capital plan is more than 10,036 billion VND. To date, the disbursed value has reached 2,562.6 billion VND, equivalent to 25.5% of the plan.

Khẩn trương thi công đường Ninh Quới - Ngan Dừa, Cà Mau ngay sau khi có mặt bằng. Ảnh: Nhật Hồ.
Urgently construct Ninh Quoi - Ngan Dua, Ca Mau road immediately after having the site. Photo: Nhat Ho.

Notably, 70 key projects and works have just disbursed nearly 985 billion VND out of a total of more than 5,401 billion VND allocated, reaching about 18.2% of the plan.

According to the Department of Finance, immediately after being assigned the capital plan, the Provincial People's Committee has detailed allocations for projects that meet the conditions for implementation, and at the same time regularly reviews and adjusts the capital plan in accordance with the implementation progress.

The Standing Committee of the Provincial Party Committee also established 5 supervisory groups headed by the Standing Committee of the Provincial Party Committee, directly inspecting the site and removing difficulties for each project. Along with that, the Provincial People's Committee issued a plan to promote disbursement of public investment capital in 2026, clearly assigning the progress and responsibilities of each agency and unit.

Mr. Huynh Cong Quan - Director of the Department of Finance of Ca Mau province - said that the unit regularly advises on adjusting capital plans, monitoring disbursement progress weekly, monthly, quarterly, and urging investors to accelerate implementation.

Focus on removing bottlenecks in key projects

Although many solutions have been implemented, the progress of some large projects is still slow due to site clearance, land price determination, resettlement, technical infrastructure relocation and legal disputes.

Some projects are facing difficulties such as the investment project to build Ca Mau General Hospital with a scale of 1,200 beds; the road from Phuoc Long town to Ba Dinh; Trem Trem - Xeo Quao road; storm shelter anchorage area and Cai Cung fishing port.

Bệnh viên Đa khoa Cà Mau 1.200 giường tiến độ giải ngân rất chậm ảnh hưởng đến tỉ lệ giải ngân vốn đầu tư công của Cà Mau. Ảnh: Nhật Hồ.
Ca Mau General Hospital with 1,200 beds has very slow disbursement progress, affecting the disbursement rate of public investment capital in the province. Photo: Nhat Ho.

In addition, the shortage of construction materials and the fact that the actual material prices are higher than the announced prices have caused many obstacles in contractor selection and construction. Some projects started right in the rainy season also affected the implementation progress.

According to Chairman of Ca Mau Provincial People's Committee Lu Quang Ngoi, investors must closely follow monthly disbursement plans, accelerate contractor selection, closely coordinate with localities in site clearance and promptly report difficulties beyond their authority.

The Department of Construction is assigned to closely monitor market developments, proactively ensure the supply of construction materials and guide the handling of cases of material price fluctuations.

For the Department of Finance, the Provincial People's Committee requests to closely monitor the disbursement progress of each project, advise on capital transfer from slow-progress projects to projects with good disbursement capacity, ensuring the effective use of public investment capital and completing the disbursement target for 2026.

NHẬT HỒ
RELATED NEWS

A series of Ca Mau wind power projects face difficulties

|

Ca Mau is planned for 48 wind power projects with more than 3,000 MW, but many projects are still behind schedule, not fully exploiting their potential due to obstacles in mechanisms, transmission infrastructure and investor capacity.

Ca Mau: GRDP growth in the first 6 months of the year only reached 6.6%

|

Ca Mau - In the first six months of 2026, the province's GRDP is estimated to increase by about 6.4 - 6.6%, lower than the 8% level according to the province's growth scenario.

Golden land of more than 6.2ha in Ca Mau abandoned after 6 years of recovery

|

The land area of more than 6.2ha right in the center of Ca Mau recovered from the Exhibition and Fair Center Project has not been exploited to date, many works are degraded, causing waste.

Ca Mau sets a target for marine economy to contribute 40-45% of total budget revenue

|

Ca Mau - In 2026, the province strives for a GRDP increase of 10%, of which the marine and pure marine economy contributes about 40-45% of the province's total budget revenue.

Ca Mau still has 238 redundant headquarters and land that have not been exploited

|

Although there have been many solutions to handle public assets after arranging administrative units, Ca Mau still has 238 redundant houses and land facilities that have not been exploited.

Billion-dollar LNG gas power project in Ca Mau is messy with procedures

|

After more than 5 years of being approved for investment policy, the Bac Lieu LNG gas power project, Ca Mau province, is still at the investment preparation stage.

A series of violations at the Bac Lieu Trade Center Project in Ca Mau

|

Ca Mau - Many violations in land, investment, and bidding at the Bac Lieu Trade Center Project.

People provide information when discovering many memorabilia in martyrs' graves in Dong Nai

|

Dong Nai - During the excavation of graves and taking samples of martyrs' remains for DNA testing, functional forces discovered many memorabilia and photos.

A series of Ca Mau wind power projects face difficulties

Nhật Hồ |

Ca Mau is planned for 48 wind power projects with more than 3,000 MW, but many projects are still behind schedule, not fully exploiting their potential due to obstacles in mechanisms, transmission infrastructure and investor capacity.

Ca Mau: GRDP growth in the first 6 months of the year only reached 6.6%

NHẬT HỒ |

Ca Mau - In the first six months of 2026, the province's GRDP is estimated to increase by about 6.4 - 6.6%, lower than the 8% level according to the province's growth scenario.

Golden land of more than 6.2ha in Ca Mau abandoned after 6 years of recovery

NHẬT HỒ |

The land area of more than 6.2ha right in the center of Ca Mau recovered from the Exhibition and Fair Center Project has not been exploited to date, many works are degraded, causing waste.

Ca Mau sets a target for marine economy to contribute 40-45% of total budget revenue

NHẬT HỒ |

Ca Mau - In 2026, the province strives for a GRDP increase of 10%, of which the marine and pure marine economy contributes about 40-45% of the province's total budget revenue.

Ca Mau still has 238 redundant headquarters and land that have not been exploited

NHẬT HỒ |

Although there have been many solutions to handle public assets after arranging administrative units, Ca Mau still has 238 redundant houses and land facilities that have not been exploited.

Billion-dollar LNG gas power project in Ca Mau is messy with procedures

NHẬT HỒ |

After more than 5 years of being approved for investment policy, the Bac Lieu LNG gas power project, Ca Mau province, is still at the investment preparation stage.

A series of violations at the Bac Lieu Trade Center Project in Ca Mau

NHẬT HỒ |

Ca Mau - Many violations in land, investment, and bidding at the Bac Lieu Trade Center Project.