Close-up of 6 aircraft fuel tanks of 6,000 m3/tank at Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - Each floating tank of the fuel supply system at Long Thanh airport has a capacity of 6,000 m3.

On May 16, according to information from the Long Thanh Airport Project Management Board, the fuel supply system for aircraft at Long Thanh airport has been basically completed.

Fuel tanks, underground and above-ground pipelines have been installed and are ready for operation.

The underground fuel pipe system in the aircraft parking area in front of the passenger terminal has also been completed, with the task of directly supplying fuel to the aircraft.

According to reporters' records, currently officials, engineers, and workers are continuing to complete the remaining tasks to put the project into synchronous operation with other bidding packages.

Internal traffic road items, technical infrastructure, landscape; house items... have also been basically completed. Officials, engineers, and workers are testing the electrical - control system, technology system (pumps, valves, filters...).

According to Vietnam Airports Corporation (ACV), for package 4.9, Long Thanh airport fuel supply system, to ensure synchronization in operation and exploitation with the passenger terminal project and other packages, the contractor consortium strives to complete the construction milestones of key items to ensure readiness to put the project into operation in June 2026.

The contractor consortium has mobilized hundreds of personnel and machinery and equipment to deploy construction.

Bidding package 4.9 - Long Thanh airport fuel supply system with a contract value of more than 2,880 billion VND started in October 2024.

In which, the construction item of 6 floating fuel tanks is one of the most important items. Each floating tank of the fuel supply system at Long Thanh Airport has a capacity of 6,000 m3.

Image of 6 fuel tanks for aircraft of 6,000 m3/tank at Long Thanh airport:

Mỗi bồn chứa nổi của hệ thống cung cấp nhiên liệu tại Sân bay Long Thành có dung tích 6.000 m3. Ảnh: HAC
Each floating tank of the fuel supply system at Long Thanh Airport has a capacity of 6,000 m3. Photo: HAC
Từ các bồn chứa nổi, nguồn nhiên liệu thông qua hệ thống ống dẫn sẽ được cung cấp cho tàu bay khi sân bay Long Thành đưa vào khai thác. Ảnh: HAC
From floating tanks, fuel through a pipeline system will be supplied to the aircraft when Long Thanh airport is put into operation. Photo: HAC
Đến nay, việc thi công gói thầu đã cơ bản hoàn thành các hạng mục chính, liên danh nhà thầu đang tiếp tục hoàn thiện các hạng mục phụ trợ còn lại của gói thầu. Ảnh: HAC
To date, the construction of the bidding package has basically completed the main items, and the contractor consortium is continuing to complete the remaining auxiliary items of the bidding package. Photo: HAC
Hệ thống ống dẫn được thi công lắp đặt tại khu vực các bồn chứa nổi của hệ thống cung cấp nhiên liệu tàu bay sân bay Long Thành. Ảnh: HAC
The pipeline system is constructed and installed in the area of the floating tanks of the fuel supply system for Long Thanh airport aircraft. Photo: HAC
Hàng trăm nhân sự, thiết bị đã được liên danh nhà thầu huy động để thi công gói thầu này. Ảnh: HAC
Hundreds of personnel and equipment have been mobilized by the contractor consortium to construct this package. Photo: HAC
Đây là gói thầu trọng điểm tại dự án sân bay Long Thành. Ảnh: HAC
This is a key bidding package at the Long Thanh airport project. Photo: HAC
Người lao động được bảo hộ kỹ càng khi thi công trong thời tiết nắng nóng ở miền Nam. Ảnh: HAC
Workers are carefully protected when constructing in hot weather in the South. Photo: HAC
Người lao động thi công tại gói thầu 4.9 dự án sân bay Long Thành. Ảnh: HAC
Workers constructing at package 4. 9 Long Thanh airport project. Photo: HAC
Các thiết bị phục vụ việc bơm, vận chuyển nhiên liệu đến tàu bay hiện cũng đã được thi công lắp đặt hoàn thiện. Ảnh: HAC
Equipment serving the pumping and transportation of fuel to aircraft has also been completed and installed. Photo: HAC
Gói thầu 4.9 đang tiếp tục được hoàn thiện các phần việc còn lại. Ảnh: HAC
Package 4.9 is continuing to complete the remaining tasks. Photo: HAC
Toàn cảnh 6 bồn chứa nổi hệ thống cung cấp nhiên liệu tại sân bay Long Thành. Ảnh: HAC
Overview of 6 floating fuel supply tanks at Long Thanh airport. Photo: HAC
HÀ ANH CHIẾN
RELATED NEWS

National Assembly Vice Chairman Nguyen Hong Dien inspects Long Thanh airport project

|

Dong Nai - National Assembly Vice Chairman Nguyen Hong Dien and the working delegation inspected the progress of the Long Thanh airport project and connecting traffic routes.

Many projects connecting Long Thanh airport are completed and started in June

|

Long Thanh airport is expected to be put into commercial operation in the fourth quarter of 2026, Dong Nai city is accelerating the progress of completing and starting new connecting transportation projects.

Dong Nai and Ho Chi Minh City agree on directions for 2 metro lines to Long Thanh airport

|

Dong Nai City and Ho Chi Minh City basically agreed on the direction of line 2 of the metro project for the section from National Highway 51 to the station area located in Long Thanh airport.

Dong Nai plans urban area at the western gateway of Long Thanh airport

|

Dong Nai - The population forecast for the new urban area at the western gateway of Long Thanh airport is about 400,000 - 450,000 people.

Hanoi becomes more open from the campaign to reclaim sidewalks

|

After the campaigns to restore urban order, many streets in Hanoi are more open, contributing to ensuring traffic safety.

Green living, green walking, green development

|

From industrial parks, transportation to daily life, green transformation is clearly present, opening up new momentum for sustainable growth.

Instructions on switching from old gasoline cars to electric cars at Green Transit Day 2026

|

On Green Transformation Day 2026, people can bring old gasoline cars to participate in the "gasoline to electricity exchange" program and directly experience new electric vehicle lines.

Draft Report of the Executive Committee of the Vietnam General Confederation of Labor (XIII term) at the XIV Congress of the Vietnam Trade Union, term 2026 - 2031

|

Building a comprehensively strong Vietnam Trade Union; focusing on representing, caring for, and protecting union members and workers; promoting the pioneering role, spirit of innovation and creativity, contributing to realizing the aspiration to build a rich, prosperous, civilized, and happy country.

National Assembly Vice Chairman Nguyen Hong Dien inspects Long Thanh airport project

HÀ ANH CHIẾN |

Dong Nai - National Assembly Vice Chairman Nguyen Hong Dien and the working delegation inspected the progress of the Long Thanh airport project and connecting traffic routes.

Many projects connecting Long Thanh airport are completed and started in June

HÀ ANH CHIẾN |

Long Thanh airport is expected to be put into commercial operation in the fourth quarter of 2026, Dong Nai city is accelerating the progress of completing and starting new connecting transportation projects.

Dong Nai and Ho Chi Minh City agree on directions for 2 metro lines to Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai City and Ho Chi Minh City basically agreed on the direction of line 2 of the metro project for the section from National Highway 51 to the station area located in Long Thanh airport.

Dong Nai plans urban area at the western gateway of Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - The population forecast for the new urban area at the western gateway of Long Thanh airport is about 400,000 - 450,000 people.