Need to approve land price for 3,500 billion VND project in Quang Ngai

VIÊN NGUYỄN |

The Hoang Sa - Doc Soi road project in Quang Ngai has been under construction for a year, but the three localities where the project passes have not yet completed land price approval, causing difficulties for the project.

The Hoang Sa - Doc Soi road project has a route length of 26.88km, starting at the intersection with Tri Binh - Dung Quat road, ending at the Hoang Sa road. The project passes through Binh Son district for 17.62km, Son Tinh district for 1.9km and Quang Ngai city for 7.36km. The total investment is 3,500 billion VND, of which the central budget is 1,300 billion VND, the provincial budget is 2,200 billion VND (capital collected from land use fees). The implementation period is from 2022 to 2027, with the Quang Ngai Provincial Traffic Project Management Board as the investor, and construction started in December 2023.

Qua tinh toan, du an duong Hoang Sa - Doc Soi can gan 644.000m³ cat. Tuy nhien, hien chi co 3/9 mo cat chi dinh duoc cap phep khai thac. Anh: Vien Nguyen
According to calculations, the Hoang Sa - Doc Soi road project needs nearly 644,000m³ of sand. However, currently only 3/9 designated sand mines are licensed for exploitation. Photo: Vien Nguyen

The project will invest in the construction of 10 resettlement areas, 655 plots of land (equivalent to an area of ​​27.09 hectares) and 1 burial area in Quang Ngai City. According to Mr. Ngo Van Dung - Director of the Quang Ngai Provincial Traffic Project Management Board, the total capital plan allocated for the project to date is nearly 1,579 billion VND. Of which, the central budget is over 979 billion VND, the provincial budget is over 599 billion VND. The capital plan for 2024 is over 762.5 billion VND from the central budget.

According to the investor, although the project has been implemented for about a year, the three localities where the project passes through, Binh Son district, Son Tinh district and Quang Ngai city, have not yet completed the approval of specific land prices according to the provisions of the 2024 Land Law. The approval of compensation plans has not progressed, to date, compensation plans have been approved for 15.88/164.51 hectares, reaching 9.7% of the total area.

According to Mr. Ngo Van Dung, the project construction value to date has reached about 135/2,322 billion VND, reaching 6% of the contract value. Over 77.9/162.5 billion VND has been disbursed, reaching 47.9% of the capital plan. For the additional capital of 600 billion VND from the central budget newly allocated on June 14, 2024, it has not been disbursed.

To facilitate this key project, the People's Committee of Quang Ngai province has identified 9 sand mining locations to grant to the Hoang Sa - Doc Soi project. Up to now, the People's Committee of the province has granted mineral exploration licenses to 3/9 sand mines, including the sand mine on Xi Phong, Binh Chuong commune; the sand mine in Binh My commune (Eastern area) and the sand mine in Binh Minh commune. The project implementation process still faces many difficulties, the investor

The Ministry of Planning and Investment has reported to the Steering Committee for the implementation of key projects in Quang Ngai province in the period of 2024-2025 to monitor and direct the Department of Natural Resources and Environment to continue to pay attention to and support construction units to promptly complete the procedures for granting licenses to exploit sand mines for the project. For the People's Committees of Binh Son, Son Tinh districts and Quang Ngai city, it is necessary to urgently complete the work of approving specific land prices in November 2024. For the People's Committee of Binh Son district, it is necessary to urgently complete the work of issuing land recovery notices to implement the project.

VIÊN NGUYỄN
TIN LIÊN QUAN

The first steel arch bridge in Quang Ngai is under construction

|

Tra Khuc 3 Bridge with the first steel arch design in Quang Ngai is accelerating construction, ready for technical traffic opening by the end of this year.

A household blocked an 850 billion VND project in Quang Ngai

|

The Tra Khuc 3 bridge project in Quang Ngai province, with a total investment of VND850 billion, is currently facing major obstacles because a household has not agreed to hand over the land.

Quang Ngai resolves problems for 20,400 billion VND expressway

|

Quang Ngai actively supports the investor of the Quang Ngai - Hoai Nhon expressway, speeds up construction progress, site clearance, and ensures completion on schedule.

Sa Pa Airport construction schedule delayed by another year

|

Lao Cai - Since breaking ground in 2022, the 7,000 billion VND Sa Pa airport construction project has continued to miss its scheduled start date.

Gold price update morning 11.12: Breakout, should you buy?

|

Update on the morning of December 11, gold price increased dramatically. The difference between buying and selling gold in the country is still quite high, posing a risk of loss when "surfing".

The precarious fate of the dialysis village about to be cleared in the mountain town

|

In the middle of Dien Bien mountain town, a "dialysis" village with many people carrying a deadly disease is still holding out hope...

Thuy Hien tells behind the scenes of Sister and her relationship with Thu Phuong

|

"Sister" Thuy Hien shared about her close relationship with singer Thu Phuong in "Sister Who Makes Wave 2024".

Enforced recovery of nearly 35 hectares of encroached industrial park land

|

Dak Nong - Authorities have carried out enforcement and recovered nearly 35 hectares of land in the Quang Tam Industrial - Handicraft Cluster that was illegally encroached upon by people.

The first steel arch bridge in Quang Ngai is under construction

VIÊN NGUYỄN |

Tra Khuc 3 Bridge with the first steel arch design in Quang Ngai is accelerating construction, ready for technical traffic opening by the end of this year.

A household blocked an 850 billion VND project in Quang Ngai

VIÊN NGUYỄN |

The Tra Khuc 3 bridge project in Quang Ngai province, with a total investment of VND850 billion, is currently facing major obstacles because a household has not agreed to hand over the land.

Quang Ngai resolves problems for 20,400 billion VND expressway

VIÊN NGUYỄN |

Quang Ngai actively supports the investor of the Quang Ngai - Hoai Nhon expressway, speeds up construction progress, site clearance, and ensures completion on schedule.