On January 1, speaking with a reporter from Lao Dong Newspaper, Mr. Tran Van Huyen - Executive Director of the joint venture contractor for package 21 (Lizen Joint Stock Company) said that on January 1, 2025, at the construction site, the joint venture contractor still maintained machinery and equipment and engineers and workers working throughout the holiday to ensure project progress.
According to Mr. Huyen, the contractor is currently mobilizing all motorbikes, equipment and workers to work in 3 shifts, 4 shifts continuously day and night to speed up progress.
It is expected that in early January 2025, the contractor will begin paving the first kilometers of the Bien Hoa - Vung Tau expressway and strive to basically complete the work volume by April 30, 2025, the section deployed by Lizen Joint Stock Company.
Package No. 21 of component project 1 of Bien Hoa - Vung Tau expressway passes through 5 communes and towns of Long Thanh district including An Phuoc commune, Long Duc commune, Long Thanh town, Loc An commune, Long An commune.
According to the Dong Nai Province Traffic Construction Project Management Board, the Bien Hoa - Vung Tau Expressway component project 1 is 16km long through Dong Nai province, starting from National Highway 1 (Bien Hoa City) and ending at Long An Commune (Long Thanh District).
The project has two construction packages, including package No. 18 (Km0+000 - Km6+200) through Bien Hoa City, which is implementing 6 construction phases, including Buong River bridge, roadbed, horizontal drainage culvert, residential underpass, Super T girder casting and precast components, with current output reaching about 3.2%.
Package No. 21 (Km6+200 - Km16+000) through Long Thanh district is organizing 15 construction teams, including Nuoc Trong bridge, overpass, main line bridge, roadbed, weak soil treatment, and girder casting, with output reaching about 18.1%.
Package No. 21 worth more than 1,400 billion VND, the section from Km6+200 to Km16+000 of Bien Hoa - Vung Tau expressway is constructed by a consortium (Lizen Joint Stock Company, Hai Dang Joint Stock Company, Construction Joint Stock Company 368 and Construction Corporation No. 1), the contract implementation time is 915 days.
Bien Hoa - Vung Tau Expressway, passing through Dong Nai and Ba Ria - Vung Tau provinces, is nearly 54km long and will start construction in June 2023.
In Dong Nai province, component project 1 and component project 2 will be constructed, and in Ba Ria - Vung Tau province, component project 3 will be constructed.
In phase 1, the project will have a scale of 4-6 lanes (depending on each section). The total investment is over 17,800 billion VND.