On January 29, component project 3 of the Bien Hoa - Vung Tau expressway (section passing through Ho Chi Minh City) is completing the final items to be ready for operation and exploitation.
According to the project investor, currently the construction output on the 19.5 km long road - with the starting point connecting to component project 2 (Dong Nai), the ending point intersecting with National Highway 56 - has reached about 98% progress, most items have been completed.
Along the route, the asphalt road surface, road markings, medians,... are mostly completed. Only the lighting system and signs at some intersections are in the final stages of construction.
Currently, the investor is coordinating with functional units to organize site clearance to implement additional items such as My Xuan - Ngai Giao intersection; service road... to complete the entire route according to the design.
Previously, component project 3 of the Bien Hoa - Vung Tau expressway was started in June 2023, and technically opened to traffic in April 2025. When completed and put into synchronous operation, the entire Bien Hoa - Vung Tau expressway phase 1 will contribute to strengthening regional connectivity, reducing pressure on National Highway 51, creating motivation for socio-economic development for the Southeast region.