Dau Giay - Tan Phu expressway completed site clearance in the first quarter

HÀ ANH CHIẾN |

Dong Nai - Dau Giay - Tan Phu expressway project recovers nearly 312ha of land from many communes and wards, completing compensation recovery work in the first quarter of 2026.

On January 28, the Provincial Land Fund Development Center just reported on the progress of the Dau Giay - Tan Phu expressway construction investment project (phase 1) according to the PPP method and proposed assigning the People's Committees of Dau Giay, Binh Loc, Gia Kiem, Xuan Bac, Dinh Quan, Phu Hoa, Tan Phu, Phu Lam communes and wards to urgently coordinate with the Land Fund Development Center of Thong Nhat, Xuan Loc, Dinh Quan branches, Project Management Board of Area 11 to complete the recovery and compensation work in the first quarter of 2026.

To implement the project, Dong Nai province had to recover nearly 312ha of land.

In August 2025, the Dau Giay - Tan Phu expressway project was started construction.

The project has a total length of more than 60km, the starting point of the project intersects with National Highway 1 and coincides with the ending point of the Ho Chi Minh City - Long Thanh - Dau Giay expressway in Dau Giay commune, Dong Nai province; the ending point crosses the intersection with National Highway 20 in Phu Lam commune, Dong Nai province.

The project is the first section of the Dau Giay - Lien Khuong expressway, belonging to the group of key national transport infrastructure projects, invested in PPP (public-private partnership) - BOT contract (build - operate - transfer) method with a total investment of about 8,496 billion VND.

The project is designed according to expressway standards, with a design speed of 100 km/h, scale of 4 lanes.

The expected construction time is 24 months, completed on August 19, 2027.

When put into operation, the expressway will contribute to completing the road and expressway network according to the plan, creating a breakthrough in traffic connection between Dong Nai, Ho Chi Minh City, and the Southeast and Central Highlands provinces.

The project helps shorten transportation time, reduce load on National Highway 20, and at the same time promote the efficiency of expressways, ring roads, ports and railways.

This is also a prerequisite for completing the Dau Giay - Lien Khuong expressway (CT.27), promoting socio-economic development, tourism and ensuring security and defense.

HÀ ANH CHIẾN
RELATED NEWS

Bao Loc - Lien Khuong expressway is behind schedule

|

Lam Dong - Leaders of Lam Dong Provincial People's Committee criticized the investor of the Bao Loc - Lien Khuong Expressway Project for delays in project preparation and implementation.

Starting construction of 60km of Dau Giay - Tan Phu expressway with a total investment of nearly VND 8,500 billion

|

Dong Nai - The Dau Giay - Tan Phu Expressway construction investment project is the first section of the Dau Giay - Lien Khuong Expressway, which will be completed after 2 years of construction.

Important notes when trading between strong fluctuations in gold and silver prices

|

At a time when gold prices are high, silver is becoming an investment channel chosen by many people. People need to pay attention to avoid risks to the market and trading places.

Gold confiscation without invoices" is misunderstood, people who spread false information may be fined

|

The confiscation is only set for gold bars that are exhibits of illegal trading and business. People who intentionally distort and spread false information may be penalized.

Son La requests dismantling of 6-year land lease expired registration center

|

Son La - Local authorities have just issued a document requesting the dismantling of the registration center that has expired land lease for nearly 6 years, as reflected by Lao Dong Newspaper.

Provinces and cities are forecast to have rain and severe cold due to a new cold air wave

|

It is forecasted that provinces and cities in the Northern region will turn cold, with mountainous areas experiencing severe cold from February 1 due to the impact of cold air.

Following the trend of dirty food from online markets to wholesale markets in the Capital during Tet

|

The closer to Tet, the more frozen food of unknown origin has the opportunity to creep into the market, from closed online markets to open wholesale markets.

Bao Loc - Lien Khuong expressway is behind schedule

Phúc Khánh |

Lam Dong - Leaders of Lam Dong Provincial People's Committee criticized the investor of the Bao Loc - Lien Khuong Expressway Project for delays in project preparation and implementation.

Starting construction of 60km of Dau Giay - Tan Phu expressway with a total investment of nearly VND 8,500 billion

HÀ ANH CHIẾN |

Dong Nai - The Dau Giay - Tan Phu Expressway construction investment project is the first section of the Dau Giay - Lien Khuong Expressway, which will be completed after 2 years of construction.

Cần chuẩn xác số liệu, sớm hoàn thiện hồ sơ cao tốc Dầu Giây - Tân Phú

Đức Mạnh |

Đường cao tốc Dầu Giây – Tân Phú là đoạn đầu của cao tốc Dầu Giây – Liên Khương với tổng chiều dài hơn 60km, đi qua địa bàn các huyện Thống Nhất, Xuân Lộc, Định Quán, Tân Phú của tỉnh Đồng Nai. Giai đoạn 1 cao tốc được xây dựng với quy mô 4 làn xe, bề rộng nền đường 17m, có tổng mức đầu tư 8.776 tỉ đồng.