The Hoa Lien - Tuy Loan Expressway project has a total length of about 11.5km, including 6 lanes in the completion phase and 4 lanes in the investment phase.
The total investment of the Hoa Lien - Tuy Loan Expressway project is more than VND 2,112 billion, of which the cost of compensation and site clearance including provisions is VND 951 billion.
Up to now, the final items of the Hoa Lien - Tuy Loan expressway project are being urgently completed, workers are arranged to work in 3 consecutive shifts to open the technical traffic on August 19.

According to the most updated data of the Ho Chi Minh Road Project Management Board, the output of the Hoa Lien - Tuy Loan expressway project has reached nearly 81.83% of the contract value, equivalent to 703.41 billion VND/859.58 billion VND. Of which, the main section of the Hoa Lien - Tuy Loan Expressway is 98% complete.
Contractors are focusing on completing auxiliary items, traffic safety systems, site organization and environmental sanitation to meet the technical requirements for opening the Hoa Lien - Tuy Loan expressway on schedule.

The Hoa Lien - Tuy Loan Expressway project has a total investment of more than VND 2,100 billion, of which the cost of site clearance alone accounts for more than VND 951 billion. The project started in September 2023, and the main route is expected to be completed on August 19, 2025 and the entire project in November 2025.
The investor is the Ho Chi Minh Road Project Management Board; the supervision consultant is the Road Technical Center 3; the construction contractor includes a joint venture of Truong Son Construction Corporation, Traffic Construction Corporation 5 - JSC and Company Limited 17.
Some images at the Hoa Lien - Tuy Loan Expressway Project: