The large bridge on Ring Road 4 has been closed, the final items are under construction

SÓNG HỮU |

Hanoi - The railway overpass under the Ring Road 4 parallel road project has been closed, the contractor is implementing the final items.

Component project 2.1 invests in the construction of a parallel road system (urban road) of Ring Road 4 through Hanoi with a total length of about 58.2km.

The route passes through the wards and communes: Kim Anh, Noi Bai, Me Linh, Quang Minh, Tien Thang, O Dien, Dan Phuong, Hoai Duc, Duong Hoa, Son Dong, An Khanh, Yen Nghia, Phu Luong, Binh Minh, Tam Hung, Thuong Tin, Hong Van.

Package No. 8 to build a parallel road of Ring Road 4 is about 23km long, passing through the communes of Kim Anh, Noi Bai, Me Linh, Quang Minh, Tien Thang. The consortium of Truong Son Construction Corporation - Thinh Vuong TVT Joint Stock Company - Thai Yen Investment and Construction Joint Stock Company is in charge of the construction of this package.

Speaking to Lao Dong Newspaper reporter, Mr. Do Ngoc Sam - Commander of package 8, Truong Son Construction Corporation - said that after more than 2 years of construction, package 8 has now reached about 83% of the volume, meeting the set progress.

Package 8 also undertakes the construction of 3 bridges on the route, including: Ca Lo River overpass, Hanoi - Lao Cai railway overpass and Hau village bridge.

Of these, the railway overpass is the largest project with a length of nearly 590m, including 27 spans; the width of the bridge deck is 15m on each side.

"Up to now, the bridge has been closed. Next week, the contractor will install the bridge railing, deploy asphalt paving on the bridge deck and complete the expansion joints on the bridge" - Mr. Sam said.

For the road item, the sections of the route under package No. 8 have basically been paved with asphalt. With some new sections receiving site handover, the contractor is speeding up construction, and it is expected that the asphalt layer will be completed in about a month.

Regarding site clearance, Commander Do Ngoc Sam said that there is still a part of the area related to 2 farms on the left dike of the Red River (Tien Thang commune) that has not been handed over to the contractor. In addition, there are some points where underground and above-ground infrastructure is still stuck that have not been relocated by the units.

"We request that the locality promptly hand over the remaining site so that the contractor can construct synchronously throughout the project, ensuring the completion progress in 2025 according to the city's direction" - Mr. Sam said.

ss
The parallel road of Ring Road 4 through Noi Bai Commune (Hanoi), afternoon of October 18. Photo: Song Huu
ss
Vehicles can now move back and forth in the completed sections of package No. 8. Photo: Song Huu
ss
The Hanoi - Lao Cai railway overpass with 27 spans under package 8 has basically completed the main items. Photo: Song Huu
ss
ss
The cross-section of each bridge unit is about 15m. Photo: Song Huu
ss
ss
ss
Next week, the contractor will mobilize workers to install the bridge railing system, asphalt and complete the expansion joints. Photo: Song Huu
ss
The bridge over the Ca Lo River has also basically completed the main items. Photo: Song Huu
ss
Machinery and materials are gathered to construct the bridge through Hau village. Photo: Song Huu
ss
A residential area in Quang Minh commune was cleared not long ago. Photo: Song Huu
ss
Construction machinery rolls down the roadbed at the intersection of the Ring Road 4 parallel road with Road 100 Me Linh. Photo: Song Huu
SÓNG HỮU
RELATED NEWS

Information on the progress and completion time of the Hanoi Ring Road 4 parallel road

|

According to the set target, the Ring Road 4 parallel road section through Hanoi will be basically completed by the end of 2025, after about 2.5 years of construction.

Information on the construction of 2 bridges across the Red River on Ring Road 4

|

Hanoi - Hong Ha and Me So bridges across the Red River on Ring Road 4 will be built from now until 2027, helping to connect inter-regional areas, reducing traffic congestion.

Hanoi wants to be the managing agency of the project connecting Ring Road 4 and Ring Road 5

|

Hanoi proposed to be the managing agency of the project connecting Hanoi Ring Road 4 with Ring Road 5 through Ninh Binh province.

Tien Linh continues to be silent, Ho Chi Minh City Police loses minimally to Becamex Ho Chi Minh City

|

On the evening of March 1st, Ho Chi Minh City Police Club suffered a 0-1 defeat to Becamex TPHCM in round 13 of LPBank V.League 2025-2026 on Tien Linh's lackluster day.

Metro connecting the two banks of the Saigon River is expected by people

|

Ho Chi Minh City - With a capital of 33,000 billion VND, Ben Thanh - Thu Thiem Metro is expected to be completed soon, meeting the people's expectations for a connected transportation system.

Live football Nam Dinh vs Ninh Binh in round 14 of V.League

|

Live match between Nam Dinh and Ninh Binh in round 14 of LPBank V.League 2025-2026, taking place at 6:00 PM today (March 1).

Iran declares the US suffered heavy casualties in retaliatory attack

|

Iran retaliated against US and Israeli attacks by targeting Washington's military bases throughout the region.

Information on the progress and completion time of the Hanoi Ring Road 4 parallel road

SÓNG HỮU |

According to the set target, the Ring Road 4 parallel road section through Hanoi will be basically completed by the end of 2025, after about 2.5 years of construction.

Information on the construction of 2 bridges across the Red River on Ring Road 4

Sóng Hữu |

Hanoi - Hong Ha and Me So bridges across the Red River on Ring Road 4 will be built from now until 2027, helping to connect inter-regional areas, reducing traffic congestion.

Hanoi wants to be the managing agency of the project connecting Ring Road 4 and Ring Road 5

SÓNG HỮU |

Hanoi proposed to be the managing agency of the project connecting Hanoi Ring Road 4 with Ring Road 5 through Ninh Binh province.