Nhat Le 3 bridge removes site bottleneck after last households agree

NGUYỄN LUÂN |

Quang Tri - After a period of mobilization, the household finally agreed to receive compensation and agreed to hand over the site, removing obstacles for the Nhat Le 3 bridge project.

On July 3, in an exchange with a reporter from Lao Dong Newspaper, Mr. Hoang Ngoc Dan - Chairman of Dong Hoi Ward People's Committee (Quang Tri province) said that the last household still facing problems in site clearance work under component project 2 - Nhat Le 3 Bridge and roads at both ends of the bridge has agreed to the compensation plan, received compensation money and committed to handing over the site for construction deployment.

According to Mr. Dan, this is the result after a long time of local authorities and functional forces persistently meeting, dialoguing, propagating, and mobilizing the remaining households to comply with the policy of land acquisition to serve the key transportation project.

We have been to each household since morning to mobilize the remaining households to hand over the land. By tonight (July 2), the households have finally agreed to the compensation plan and agreed to hand over the land," Chairman of Dong Hoi Ward People's Committee informed.

Lãnh đạo phường Đồng Hới cùng lực lượng chức năng đến từng nhà để tuyên truyền, vận động người dân bàn giao mặt bằng cho dự án. Ảnh: Ngọc Đan
Leaders of Dong Hoi ward and functional forces go to each house to propagate and mobilize people to hand over land for the project. Photo: Ngoc Dan

According to Dong Hoi Ward People's Committee, as of July 1, the project still has 7 households and individuals who have not complied with Land Recovery Decision No. 1975/QD-UBND dated June 22, 2026 of the Chairman of Dong Hoi Ward People's Committee.

Before the request to accelerate the project progress, leaders of the Ward People's Committee and representatives of specialized departments, the Provincial Police force and related units directly went to each household to dialogue, listen to their thoughts and aspirations; and at the same time explain the provisions of the law on land, compensation, support, and resettlement policies as well as the meaning of the project for local socio-economic development.

Through the mobilization process, people's recommendations were received and answered based on the provisions of law and the actual project implementation. Previously, 4 households agreed to receive compensation and support money and committed to handing over the land. By the evening of July 2, the household finally agreed on a compensation plan.

Sau quá trình đối thoại, vận động, hộ dân cuối cùng đã đồng ý nhận bồi thường và bàn giao mặt bằng cho dự án cầu Nhật Lệ 3. Ảnh: Ngọc Đan
After a process of dialogue and mobilization, by the evening of July 2, the household finally agreed to receive compensation and hand over the site for the Nhat Le 3 bridge project. Photo: Ngoc Dan

Currently, Nhat Le 3 bridge has completed about 95% of the construction volume. The main bridge part is basically completed, only waiting for the clean ground in the East to construct the access road and complete the entire project.

Nhat Le 3 bridge spans the Nhat Le River, belongs to the Coastal Road and Nhat Le 3 Bridge Project, has a total length of more than 2.8km, a total investment of about 1,300 billion VND, implemented in the 2022-2026 period. When put into use, the project will contribute to connecting the two banks of the Nhat Le River, reducing the load on the existing transportation system, completing urban infrastructure and creating motivation for the development of urban space and coastal tourism of Quang Tri province.

NGUYỄN LUÂN
RELATED NEWS

Nhat Le 3 bridge is about to be completed but the access road is still blocked

|

Quang Tri - Nhat Le 3 bridge is about to reach the finish line, but so far 13 households have not handed over land, affecting the construction progress of the project.

Nhat Le 3 Bridge is about to be completed, the approach road is still stuck with land clearance

|

Quang Tri - The Nhat Le 3 bridge project and the road at both ends of the bridge are facing many difficulties in site clearance, risking affecting construction progress.

Quang Ninh announces decision to appoint 2 department directors

|

Quang Ninh - July 3rd, Quang Ninh Provincial People's Committee held a conference to announce the decisions of the Chairman of the Provincial People's Committee on personnel work.

Bad news

|

Mr. Do Minh Khang, born in 1938 (father of comrade Do Thu Trang - Deputy Head in charge of the Secretariat of the Lao Dong Newspaper) passed away at 12:20 pm on July 2, 2026 (ie May 18, Binh Ngo year), at the age of 89.

Cau Bay River before the opportunity to "change its coat" after many years of pollution

|

Hanoi - Living next to a polluted river for many years, people expect the Cau Bay river renovation project to soon bring a healthier living environment.

Hesco project changes wastewater treatment plant into clean water tank, functional agencies request review

|

The investor of the Hesco project continues to be required to review and complete the dossier fully according to regulations.

Cầu Nhật Lệ 3 không thể phơi mưa nắng kéo dài thêm nữa

Lê Thanh Phong |

Cầu Nhật Lệ 3 đã hoàn thành đến 95% khối lượng vẫn mắc kẹt vì 17 hộ dân.

Nhat Le 3 bridge is about to be completed but the access road is still blocked

CÔNG SÁNG - THANH TRUNG |

Quang Tri - Nhat Le 3 bridge is about to reach the finish line, but so far 13 households have not handed over land, affecting the construction progress of the project.

Nhat Le 3 Bridge is about to be completed, the approach road is still stuck with land clearance

CÔNG SÁNG |

Quang Tri - The Nhat Le 3 bridge project and the road at both ends of the bridge are facing many difficulties in site clearance, risking affecting construction progress.