site clearance for Nhat Le 3 bridge still has many problems

CÔNG SÁNG |

Quang Binh - The site clearance of Nhat Le 3 bridge is facing difficulties due to many households not agreeing and problems in land records.

Acceleration on the entire route

On June 18, speaking with a reporter from Lao Dong Newspaper, Mr. Le Minh Tri - Technical Officer of Nhat Le 3 Bridge said that the project had completed about 85% of the total output. The project management board is focusing resources on the construction of key items such as installation, tightening of steel arch cables, complex construction phases and deciding on the technical quality of the entire route.

Mr. Tri informed that at the 120m long S2 span, all arch sections have been installed. The remaining 2 spans (S1 and S3, each 80m long) have completed the installation of the main arch and are constructing the horizontal suspension. It is expected that in June 2025, 3 arch spans will be completed, creating conditions for the implementation of arch cable car systems, high-precision technical items, requiring specialized equipment such as 5,000-ton barges and 800-ton axle cranes, nearly 93m high.

Along with the main progress in the main bridge section, the approach bridge items have completed 6/7 spans. The remaining span will be deployed immediately after completing the installation of the PI beam system.

Hien tai van con vuong giai phong mat bang tai day. Anh: Minh Tri
Currently, there are still problems with site clearance here. Photo: Minh Tri

According to the new plan approved by the investor, the entire project will be completed on September 2, 2025, a 12-month shortening compared to the original plan. To meet this progress, the construction force of more than 120 engineers and workers is organizing 3 consecutive shifts, while strictly controlling technical requirements, quality and labor safety.

Site clearance still faces many problems

However, despite the strong acceleration of the project, the biggest problem at present is still the site clearance and resettlement stages, especially at Component Project 2 and the Nhat Le 3 bridge resettlement area in Bao Ninh commune.

A representative of the Department of Agriculture and Environment of Dong Hoi City said that the area requiring site clearance for Component Project 2 is 12.3 hectares, of which only 4.98 hectares (40%) have been completed. The remaining area (7.32ha) is undergoing compensation, including many cases of disagreement or legal difficulties in confirming the origin of land use.

The Nhat Le 3 bridge resettlement area alone needs 3.24ha of site clearance, but is currently only able to implement 0.93ha (28.7%). Of the remaining area, 1.64ha has difficulty in re-establishing compensation records according to the new regulations of the 2024 Land Law. Some households with garden land and production forest land have not agreed on the price, or requested to be compensated for the entire area outside the GPMB scope.

In particular, the relocation of graves in the resettlement area still has no replacement site, causing serious progress. Although the Provincial People's Committee and the People's Committee of Dong Hoi City have issued specific instructions, it still takes time for units to review and agree with the people on compensation plans.

In addition, many households in the new land acquisition phases are still in the stage of publicizing plans, mobilizing persuasiveness or waiting for the measurement to be completed, leading to the risk of delays if not completely handled in June and July.

Accelerating construction while site clearance is still slow is putting great pressure on the Project Management Board and related parties. According to the assessment, if problems with land records, compensation prices and resettlement arrangements are not resolved promptly, the progress of Nhat Le 3 bridge may be affected.

CÔNG SÁNG
TIN LIÊN QUAN

Clearing land, expanding Ba Dinh Square area for parade and march

|

The Deputy Prime Minister requested Hanoi to focus on directing site clearance and expanding the Ba Dinh Square area to organize commemorative ceremonies, parades and parades.

Nghe An urges payment of compensation for site clearance on National Highway 1A

|

Nghe An - The Provincial People's Committee requested districts and towns to review, dialogue, and fully pay compensation for site clearance on National Highway 1A.

Removing the site, speeding up the construction of Nhat Le 3 bridge

|

The Nhat Le 3 Bridge project is accelerating construction but is still stuck with site clearance in Bao Ninh commune, affecting the progress of key projects in Quang Binh.

16 Vietnamese citizens return home from Iran

|

On June 18, 2025, 16 Vietnamese citizens in Iran returned home, the remaining 11 citizens were still kept in touch regularly.

TMV Aurora has not been licensed, but the clinic still provides weight loss consultation with RF waves and enzyme culture

|

Although not licensed by the authorities as a medical examination and treatment facility, TMV Aurora still advises on weight loss with RF waves and enzyme culture.

Concerns about investors building railways but actually to develop TOD projects

|

National Assembly delegate Hoang Van Cuong is concerned about the situation where investors propose to build a railway but in fact, to develop the TOD project is the main goal.

Tuoi Tre Thu Do Newspaper receives Third Class Labor Medal

|

Hanoi - On June 18, the Capital Youth Newspaper held a ceremony to celebrate the 100th anniversary of the Vietnam Revolutionary Press Day and received the Third Class Labor Medal.

Decoding deposit record levels at credit institutions

|

Bank deposits reached nearly VND7.47 trillion in the first quarter of 2025. However, not all of this cash flow is residential savings.

Clearing land, expanding Ba Dinh Square area for parade and march

ANH HUY |

The Deputy Prime Minister requested Hanoi to focus on directing site clearance and expanding the Ba Dinh Square area to organize commemorative ceremonies, parades and parades.

Nghe An urges payment of compensation for site clearance on National Highway 1A

QUANG ĐẠI |

Nghe An - The Provincial People's Committee requested districts and towns to review, dialogue, and fully pay compensation for site clearance on National Highway 1A.

Removing the site, speeding up the construction of Nhat Le 3 bridge

CÔNG SÁNG |

The Nhat Le 3 Bridge project is accelerating construction but is still stuck with site clearance in Bao Ninh commune, affecting the progress of key projects in Quang Binh.