The final stage of the billion-dong connecting road project through Thai Nguyen

Đặng Vũ |

Thai Nguyen - The regional connecting road with a total investment of thousands of billions of VND is entering the final stage, expected to create a breakthrough in the inter-provincial infrastructure of the North.

As one of the key transport projects, the regional connecting route through Thai Nguyen is expected to open a new connection axis between the three northern midland provinces.

This project plays a role in connecting strategic infrastructure, while creating momentum for inter-regional economic development in the context of Thai Nguyen restructuring development space.

Cac hang muc ha tang tuyen duong lien ket vung dang khan truong hoan thien. Anh: Dang Vu.
Infrastructure items of the regional connecting road are being urgently completed. Photo: Dang Vu

The Thai Nguyen - Bac Giang - Vinh Phuc regional connecting road project started construction in mid-2022, with the Thai Nguyen Provincial Traffic and Agricultural Construction Investment Project Management Board as the investor.

The project has a total length of 42.55km, going from Pho Yen city (old) to Dai Tu district (old), with a total investment of VND3,800 billion.

According to Lao Dong Newspaper's reporter in mid-July 2025, after many years of implementation, the regional connecting road has been basically completed.

Cac cong nhan, may moc duoc huy dong trien khai, tien hanh thi cong. Anh: Dang Vu.
Workers and machinery are mobilized to deploy and carry out construction. Photo: Dang Vu

At the construction site, workers and machinery are mobilized and deployed in many teams to spread asphalt layer on the road surface, complete the connecting sections and install auxiliary infrastructure.

According to the contractor, the entire route currently has only about 2km of road surface and the bridge connections have not been completed.

As of the beginning of the third quarter of 2025, site clearance has reached 99.8%, roadbed has been constructed nearly 99%, asphalt concrete road surface has reached 87%, crushed stone foundation has been completed 89%.

Supporting items such as drainage systems, trees, underpasses, sidewalks... reached about 94% of the volume.

Cac cau vuot hien
The railway overpasses, National Highway 3 overpasses and Cong River overpasses have all reached over 83% of the progress. Photo: Dang Vu

There are 11 bridges on the entire route, of which three large bridges play a vital role in connecting, including: the railway overpass, the National Highway 3 overpass and the Cong River overpass.

These items are currently over 83% complete, of which two bridges have exceeded the 90% construction mark.

However, there are still some shortcomings in terms of land in Thanh Cong commune, Phuc Thuan ward and Van Xuan ward (formerly under Pho Yen city).

In total, there are 20 households that have not yet handed over the site, of which some households are obstructing construction, one household has not yet completed handling the affected assets.

A hotel has not relocated the technical system, along with the situation of telecommunication cables running across the road surface that have not been fixed.

Mat duong toan tuyen co ban duoc tham nhua, con 2km
The road surface of the entire route is basically paved with asphalt to facilitate vehicle travel. Photo: Dang Vu

Mr. Tran Trong Cuong - Deputy Director of the Project Management Board - said that he has requested localities to focus on handling all problems related to the site to hand over to the investor.

At the same time, network operators are required to coordinate in burying the cable line in accordance with the design, ensuring aesthetics and safety during operation after exploitation.

Due to the impact of prolonged rain, the technical traffic opening schedule has been adjusted to before August 19 and the entire project will be completed on August 31, 2025.

When completed, the project will contribute to completing the strategic infrastructure network in the Northern midlands, while creating a new development corridor between the three provinces of Thai Nguyen, Bac Giang (old) and Vinh Phuc (old).

Đặng Vũ
TIN LIÊN QUAN

A series of key overpasses on the billion-dong connecting road

|

Thai Nguyen - The Thai Nguyen - Bac Giang - Vinh Phuc connecting road has a total investment of VND3,800 billion, and has gradually been completed after a long period of construction.

The shape of a river-crossing bridge on the regional connecting road

|

Thai Nguyen - The Cong River overpass on the Thai Nguyen - Bac Giang - Vinh Phuc connecting route is speeding up the progress, constructing the installation of girders.

Another body of a victim of a tourist boat capsize in Ha Long Bay was found

|

Quang Ninh - This morning (September 21), the authorities of Quang Ninh province found the body of a victim in the QN-7105 tourist boat capsized in Ha Long Bay.

Forecast of the area most affected by storm No. 3 Wipha in the next 24 hours

|

Coastal waters and mainland areas from Quang Ninh to Nghe An will be strongly affected by storm No. 3 Wipha in the next 24 hours.

Vietnam ranked 6/40 countries on the World AI Index

|

Vietnam made its mark when it ranked 6th out of 40 countries, reaching 59.2 points on the scale of 100 of the World AI Index.

Vietnam and China organize joint military training for the first time

|

The relationship between the Vietnamese and Chinese military has achieved a stable development at a high level.

Thanh Hoa fishermen rush to pull their boats out to avoid storm No. 3

|

Thanh Hoa - Faced with the complicated developments of storm No. 3, fishermen in Sam Son sea urgently pulled their boats out to ensure safety.

Russia - Ukraine conduct fierce airstrikes as leaders open up peace negotiations

|

On July 20, both Russia and Ukraine carried out UAV airstrikes on each other's territories in the context of the leaders of the two countries opening up to negotiate peace.

A series of key overpasses on the billion-dong connecting road

Lam Thanh |

Thai Nguyen - The Thai Nguyen - Bac Giang - Vinh Phuc connecting road has a total investment of VND3,800 billion, and has gradually been completed after a long period of construction.

The shape of a river-crossing bridge on the regional connecting road

Lam Thanh |

Thai Nguyen - The Cong River overpass on the Thai Nguyen - Bac Giang - Vinh Phuc connecting route is speeding up the progress, constructing the installation of girders.

Hình hài tuyến đường liên kết vùng sau hơn 1 năm thi công

Nguyễn Tùng |

Dự án đường liên kết vùng Thái Nguyên - Bắc Giang - Vĩnh Phúc tổng mức đầu tư gần 3.800 tỉ đồng được kỳ vọng sẽ tạo ra không gian, động lực phát triển mới cho các địa phương nơi tuyến đường đi qua.