The government requests to stop, the investor of the Hesco project is still vigorously constructing

NHÓM PV |

Construction activities are still taking place rampantly at the Hesco project after the stop order from the Ha Dong ward authorities.

Still massively constructed after request to stop

Lao Dong Newspaper has an article reflecting the incident on June 2nd, Ha Dong ward functional agencies requested the investor of the Hesco Trade Center, Office, and High-rise Apartment Project (Hesco project) to stop the construction of the wastewater treatment plant.

However, after the government requested to stop, construction activities in the area near the residential block of alley 131 Tran Phu still took place.

Hình ảnh thi công tại khu vực dải đất sát các nhà dân ngõ 131 Trần Phú vào sáng ngày 9.6. Ảnh: Người dân cung cấp
Construction images at the land strip adjacent to houses in alley 131 Tran Phu on the morning of June 9. Photo: People provided

Continuously on September 8-9, PV of Lao Dong Newspaper continued to receive information that the investor of the Hesco project mobilized manpower and machinery to construct on the land strip adjacent to people's houses.

Households are worried that the construction process may affect the housing structure, living environment and safety of the area.

Người dân phản ánh tới PV nhiều băn khoăn về việc sau chỉ đạo của phường, chủ đầu tư dự án Hesco vẫn tiếp tục thi công. Ảnh: Nhóm PV
People reflected to reporters many concerns about the fact that after the ward's direction, the investor of the Hesco project still continued construction. Photo: PV Group

Notably, according to PV's investigation, in fact, before Ha Dong ward requested to stop construction, the Hanoi Department of Planning and Architecture had clearly pointed out that the wastewater treatment station arrangement plan did not meet regulations on environmentally safe distance.

In document No. 165/QHKT-HTKT sent to the Hanoi Department of Construction, the Hanoi Department of Planning and Architecture said: "The proposal to build an underground wastewater treatment plant, with a capacity of 900m3/day and night and arranged in a parking strip does not ensure a safe environmental distance to the existing residential buildings in the East and the planned villas in the West according to QCVN 01:2021/BXD (minimum 15m).

The project belongs to the basin of the Yen Xa centralized wastewater treatment plant (the plant has been completed, is undergoing trial operation, and is currently implementing the completion of the collection culvert network). Therefore, it is proposed that Thang Long Company contact the Project Management Board for Investment and Construction of Technical and Agricultural Infrastructure of Hanoi City (the investor of the Yen Xa wastewater treatment system construction project) to be provided with information and agreement to serve as a basis for proposing a design solution to connect the project's wastewater to the Yen Xa plant for treatment".

However, after that, the investor of the Hesco project still started construction of an underground wastewater treatment plant, located close to individual housing projects, causing public questioning about the reception of opinions from specialized agencies and the responsibility of the investor.

Investor admits mistake, switches to building clean water tank

On June 17, a reporter from Lao Dong Newspaper had a working session with Thang Long Vietnam Housing and Urban Development Group Joint Stock Company (in the Investor Consortium) regarding the wastewater treatment plant of the Hesco project.

At the working session, the representative of the investor, Mr. Le Van Vi - Head of the project management board, said that the planning project from 2008 of the project "does not show the location of the wastewater treatment plant". By 2019, the Environmental Impact Assessment Report of the project also did not have a drawing showing the location of the wastewater treatment plant.

Then, at the end of 2023, the Investor Consortium including Thuy Loi Equipment Joint Stock Company and Thang Long Vietnam Housing and Urban Development Group Joint Stock Company conducted a review of dossiers and adjusted the plan. The Consortium repeatedly requested to adjust the plan, but was not approved by the City People's Committee.

Previously, the project no longer had land, to be honest, I had the idea to build under the parking lot a wastewater treatment plant with the most modern technology, the best cost, and the most optimal construction method. But through the review process, staying there, although I chose the solution, it was still wrong" - Mr. Le Van Vi said.

Chủ đầu tư dự án Hesco thừa nhận sai, chuyển sang xây bể nước sạch ở dải đất giáp các nhà dân ngõ 131 Trần Phú. Ảnh: Nhóm PV
The investor of the Hesco project admitted his mistake, switching to building a clean water tank in the strip of land adjacent to houses in alley 131 Tran Phu. Photo: PV Group

Speaking about the handling direction, this person said: "The joint venture of investors realized they had to change, we no longer use that location as a wastewater treatment station, but become a clean water tank.

According to PV's records, construction activities at the land strip adjacent to houses in alley 131 Tran Phu still take place after receiving the stop order from Ha Dong ward until now. The investor affirmed that the construction of a clean water tank is under the authority of the investor.

At the same time, Mr. Vi also said: "During the functional conversion period, we can move the wastewater treatment plant to the office, because the office is preparing a feasibility study report. The final approval decision is not yet available.

Answering PV's question about concerns that the construction process affects the house structure of households next to the project, Mr. Le Van Vi said: "We are a real estate company, so every company loses a lot of money on insurance. The previous insurance contract at the time of building this high-rise building was valid until August 20, 2026. Throughout that process, up to this point, only one house in alley 131 has cracked in the balcony, I have taken insurance to make an assessment and pay the money. Based on the contract my side signed for insurance, no matter what time, if anyone's house complains about something, we still have the responsibility to remedy, compensate, and repair it".

NHÓM PV
RELATED NEWS

Hesco project builds unsafe wastewater treatment plant, requested to stop construction

|

The Hesco high-rise commercial - office - apartment center project built a wastewater treatment plant that does not ensure safety, and was requested by functional agencies to stop construction.

Building a project on public land, authorities intervene to enforce

|

Hanoi - Tran Phu Commune People's Committee has organized the forced dismantling of illegal construction works on public land of 4 households.

Overcoming a broken wastewater pipe causing a foul odor in North Nha Trang

|

Khanh Hoa - The wastewater pipe burst incident in the Ru Ri pass overpass area has been overcome by functional agencies, after wastewater spilled out onto the road.

Lao Cai invests 185 billion VND in industrial park wastewater treatment system

|

Lao Cai - Three centralized wastewater treatment system projects are being accelerated, creating an important foundation for green industry development.

People provide information when discovering many memorabilia in martyrs' graves in Dong Nai

|

Dong Nai - During the excavation of graves and taking samples of martyrs' remains for DNA testing, functional forces discovered many memorabilia and photos.

Stocks increase in the first trading session of Q3/2026

|

Cash flow pouring into large-cap groups helped the stock market maintain its green color.

The case of incorrectly determining the route in Hue: Correct errors but don't let people suffer losses

|

Thuy Xuan ward government, Hue city admitted mistakes when incorrectly determining the route in the process of preparing a compensation plan for site clearance.

Integrating administrative procedures through public service portals, saving about 5,640 billion VND

|

The National Public Service Portal integrates and provides online public services for 3,745 administrative procedures, estimated to save about 5,640 billion VND in 2025.

Hesco project builds unsafe wastewater treatment plant, requested to stop construction

NHÓM PV |

The Hesco high-rise commercial - office - apartment center project built a wastewater treatment plant that does not ensure safety, and was requested by functional agencies to stop construction.

Building a project on public land, authorities intervene to enforce

SÓNG HỮU |

Hanoi - Tran Phu Commune People's Committee has organized the forced dismantling of illegal construction works on public land of 4 households.

Overcoming a broken wastewater pipe causing a foul odor in North Nha Trang

Hữu Long |

Khanh Hoa - The wastewater pipe burst incident in the Ru Ri pass overpass area has been overcome by functional agencies, after wastewater spilled out onto the road.

Lao Cai invests 185 billion VND in industrial park wastewater treatment system

Bảo Nguyên |

Lao Cai - Three centralized wastewater treatment system projects are being accelerated, creating an important foundation for green industry development.