Complete the first resettlement area of the high-speed railway project through Ha Tinh

TRẦN TUẤN |

Ha Tinh - After nearly a year of construction, the resettlement area of the first high-speed North-South railway project in Ha Tinh has been completed.

On June 27, according to reporters of Lao Dong Newspaper, the resettlement area in Lien Vinh residential group, Ha Huy Tap ward has completed construction. Drainage system, lighting, transformer station have been installed, traffic roads have been paved with asphalt and painted lines.

Machinery has been removed from the construction site, workers have also left temporary shelters after nearly a year of sticking to the construction of the first resettlement area of the North-South high-speed railway project through Ha Tinh province.

This is a resettlement area with an area of 3.8 hectares including 57 residential land plots, with a total investment of 37 billion VND, which started construction on August 19, 2025, invested by Ha Huy Tap Ward People's Committee.

Trạm biến áp, hệ thống chiếu sáng đã được lắp đặt đầy đủ. Ảnh: Trần Tuấn
Transformer stations and lighting systems have been fully installed. Photo: Tran Tuan

Mr. Nguyen Nhat Linh - Vice Chairman of Ha Huy Tap Ward People's Committee said that up to this point, the resettlement area in Lien Vinh residential group has completed construction.

Infrastructure including roads, lighting systems, domestic electricity, and clean water have ensured the housing construction of people when implementing site clearance for the North-South high-speed railway project through the area.

Also according to Mr. Linh, for the remaining 2 resettlement areas, the locality has planned and completed the preparation of preliminary design documents, submitting them to departments and branches for appraisal.

The North-South high-speed railway project is expected to pass through Ha Huy Tap ward, about 9 km long, affecting more than 1,000 land plots of all kinds with a total area of 71 ha. Among the households whose land is recovered, there are 207 households under resettlement.

To serve site clearance work, Ha Huy Tap ward proactively plans to build 3 resettlement areas.

According to information from the Ha Tinh Department of Construction, based on the approved pre-feasibility study report dossier, the high-speed railway project on the North-South axis section passing through Ha Tinh has a length of about 103.42 km, passing through 23 communes and wards.

Through preliminary review, Ha Tinh is expected to recover about 764 hectares of land, including 84 hectares of residential land; affecting about 1,800 households, nearly 1,300 households must be relocated and resettled; relocating over 4,000 graves... The cost of site clearance for the project is estimated at over 8,400 billion VND.

Based on the preliminary boundary of site clearance, localities plan to build 35 resettlement areas with a total area of nearly 80 hectares.

Up to now, resettlement areas have been approved for planning, especially the resettlement area in Lien Vinh residential group, Ha Huy Tap ward has completed construction. The remaining resettlement areas have basically completed preliminary design documents, submitted to competent authorities for appraisal and approval.

Khu tái định cư Liên Vinh, phường Hà Huy Tập là khu tái định cư đầu tiên của dự án đường sắt Bắc - Nam tốc độ cao qua Hà Tĩnh được triển khai xây dựng và hoàn thành thi công. Ảnh: Trần Tuấn
Lien Vinh resettlement area, Ha Huy Tap ward is the first resettlement area of the North-South high-speed railway project through Ha Tinh to be implemented and completed. Photo: Tran Tuan

According to the Ha Tinh Department of Construction, because the site clearance milestones have not been handed over by the investor; the route direction and works on the route at some locations are not consistent, so the measurement, inventory, pricing, and approval of compensation plans for the North-South high-speed railway project passing through the province are not sufficient for implementation.

TRẦN TUẤN
RELATED NEWS

Complete construction of voting feature elsewhere on VneID

|

The Ministry of Public Security has issued guidelines for voters to participate in voting elsewhere electronically and complete the development of voting features elsewhere on VNeID.

Complete the construction of 100 schools in the border commune before August 30, 2026

|

The Prime Minister requested determination to complete the groundbreaking of the construction of 100 schools in 2025 and complete before August 30, 2026.

Nguyen Canh Di Street, Hanoi can be completed in 2-3 months

|

Hanoi - The investor said that the construction of Nguyen Canh Di Street (Dinh Cong Ward) will be completed within 2-3 months if the site is fully received.

Saturday afternoon coffee: From live sessions to finalize billion-VND bills to responsibilities in cyberspace

|

Billion-VND livestream sessions are opening up great opportunities, but also posing increasingly high requirements for responsibility.

Hot weather continues to spread and burn Europe, many temperature records broken

|

Healthcare, transportation and firefighting systems across Europe are struggling as the heat surges and the risk of forest fires increases.

Forecast of the number of storms and tropical depressions this year and peak times

|

Due to the impact of the El Nino phenomenon that has formed, the 2026 storm season is identified as challenging with complexity and unpredictableness.

List of collectives and individuals expected to be honored in the 2026 Glory of Vietnam Program

|

On the afternoon of June 25, 2026, the Selection Council for the 2026 Glory of Vietnam Program met to consider nominees from Central Committees, Ministries, sectors and Provincial and City Labor Federations, Central Industry Trade Unions and equivalents. Below are the expected selection of collectives and individuals to be considered and honored in the 2026 Glory of Vietnam Program.

Complete construction of voting feature elsewhere on VneID

ANH HUY |

The Ministry of Public Security has issued guidelines for voters to participate in voting elsewhere electronically and complete the development of voting features elsewhere on VNeID.

Complete the construction of 100 schools in the border commune before August 30, 2026

PHẠM ĐÔNG |

The Prime Minister requested determination to complete the groundbreaking of the construction of 100 schools in 2025 and complete before August 30, 2026.

Nguyen Canh Di Street, Hanoi can be completed in 2-3 months

HỮU CHÁNH |

Hanoi - The investor said that the construction of Nguyen Canh Di Street (Dinh Cong Ward) will be completed within 2-3 months if the site is fully received.