Hanoi Chairman requests special attention to the progress of 7 bridges

HOÀI ANH |

Hanoi - Chairman of the City People's Committee Vu Dai Thang requested the Department of Construction to continue to pay special attention and closely monitor the progress of 7 bridges and housing projects...

In the afternoon of September 16, Member of the Party Central Committee, Deputy Secretary of the City Party Committee, Chairman of Hanoi People's Committee Vu Dai Thang chaired a meeting, listening to a report on the performance of functions and tasks of the Department of Construction in the first 9 months of 2026; directions and tasks for the last 3 months of 2026.

42/51 traffic congestion points have been handled

Reporting at the meeting, Director of Hanoi Department of Construction Vo Nguyen Phong said that in the first 9 months of 2026, the Department was assigned a total of 2,268 tasks, completed 1,751 tasks, reaching 77.2%; and is currently implementing 517 tasks, accounting for 22.8%.

According to the Director of the Department of Construction, the transportation sector has handled 42/51 bottlenecks. The city has put into operation 10/10 flood prevention emergency works; supplemented 83ha of regulating lakes, about 15.89km of culverts and 26 pumping stations.

Regarding key projects, Director of the Department of Construction Vo Nguyen Phong said that Hong Ha bridge, Tu Lien bridge, and Tran Hung Dao bridge projects are being implemented. Some urban railway projects have also been started.

However, the Department of Construction determined that the progress of some key targets and tasks has not met the requirements; the volume of work in the fourth quarter is still very large.

Among the key tasks in the last months of the year, the Department will accelerate the progress of key projects, routes and urban railways; continue to handle traffic bottlenecks and flooding; develop housing, renovate old apartment buildings, renovate and develop urban areas, and manage technical infrastructure.

To complete the tasks for 2026, the Department of Construction proposed that the City People's Committee direct departments, branches, and localities to coordinate in removing difficulties in planning, site clearance, technical infrastructure relocation, and procedures for social housing development.

Converting mechanisms and policies into specific products

Concluding the meeting, Chairman of Hanoi People's Committee Vu Dai Thang emphasized that planning work is a particularly important task, because planning must go one step ahead to lay the foundation for implementing the next tasks, from project preparation, investment policy decisions to construction investment.

After the 100-year vision of the Capital's master plan is approved, the entire sub-level planning system needs to be urgently implemented to concretize the master plan. According to Plan No. 331, some plans must be completed in September, and the remaining plans must be completed in 2026.

Chairman Vu Dai Thang requested the Department of Construction to focus highly on this task, and at the same time proactively remove difficulties related to the number of consulting units, human resources with expertise in planning and planning capacity in communes and wards.

According to the Chairman of the City People's Committee, the effective implementation of the 100-year vision of the Capital's master plan requires the lower-level planning system to be synchronously completed. Otherwise, the master plan will be difficult to promote its effectiveness in practice.

Therefore, the Chairman of the City People's Committee requested the Department of Construction to focus highly, strengthen coordination with localities, provide guidance on expertise, procedures and data, thereby ensuring the completion of planning tasks on schedule.

We have introduced many models and new mechanisms to have special projects, creating momentum for development. Therefore, it is necessary to quickly implement and immediately transform mechanisms and policies into specific products and specific projects to serve growth," Chairman Vu Dai Thang emphasized.

Chairman Vu Dai Thang also requested the Department of Construction to pay special attention to groups of traffic projects and other important urban projects.

Among them are 7 bridges that the Project Management Boards are organizing to implement, along with housing projects and many other important works. These are all projects with very urgent progress requirements.

The Chairman of the City People's Committee cited an example, there are projects that have only implemented some initial tasks but require completion in July 2027.

This is an extremely drastic roadmap. If there is no supervision, no urging, it cannot be run" - Chairman Vu Dai Thang said and requested the Department of Construction to continue to pay special attention and closely monitor the progress of projects.

HOÀI ANH
RELATED NEWS

Hanoi Chairman: The construction of new works at Hoan Kiem Lake must be carefully calculated

|

Hanoi - Chairman of Hanoi People's Committee Vu Dai Thang said that the construction of new works at Hoan Kiem Lake will have to be carefully calculated.

Hanoi Chairman requests to strengthen control and limit dust spread during construction

|

Hanoi - Chairman of the City People's Committee Vu Dai Thang requested to strengthen control and take measures to limit the spread of dust during construction, transportation and dismantling.

Bui River flood exceeds alarm level III, many people in Quang Bi must evacuate

|

Hanoi - Bui River flood exceeds alarm level III, water continues to rise, causing many areas in Quang Bi to be deeply flooded. People are evacuated, many temporary bridges are prohibited from crossing.

Excavating ancient tombs in Nghe An, discovering golden leaves and iron swords

|

Nghe An - Two ancient tombs at the Buddha's hut were excavated, inside there are swords, iron swords, gold chains, gold leaves and many burial items.

Can Tho Department of Health rectifies health check-up activities after Lao Dong's reflection

|

Can Tho - After the reflection of Lao Dong Newspaper, the City Department of Health (TP) has issued an official dispatch on rectifying health check-up activities in the city.

Hanoi Chairman: The construction of new works at Hoan Kiem Lake must be carefully calculated

HOÀI ANH |

Hanoi - Chairman of Hanoi People's Committee Vu Dai Thang said that the construction of new works at Hoan Kiem Lake will have to be carefully calculated.

Chủ tịch Hà Nội chỉ đạo khẩn trương xác minh thông tin nam tài xế bị đá nhiều lần vào đầu

HOÀI ANH |

Hà Nội - Chủ tịch UBND TP chỉ đạo các đơn vị liên quan khẩn trương kiểm tra, xác minh thông tin nam tài xế kể bị người mặc áo bảo vệ đá nhiều lần vào đầu.

Hanoi Chairman requests to strengthen control and limit dust spread during construction

HOÀI ANH |

Hanoi - Chairman of the City People's Committee Vu Dai Thang requested to strengthen control and take measures to limit the spread of dust during construction, transportation and dismantling.