HCMC Chairman tightens progress for 3 metro lines connecting Long Thanh airport

MINH QUÂN |

HCMC - Metro lines Ben Thanh - Tham Luong, Ben Thanh - Thu Thiem and Thu Thiem - Long Thanh are required to speed up progress to be completed by 2030.

Ho Chi Minh City People's Committee has just directed departments, branches and related units to urgently accelerate the progress of implementing a series of projects connecting with Long Thanh International Airport, including urban railway projects.

For Metro Line No. 2 (Ben Thanh - Tham Luong section), the Chairman of Ho Chi Minh City People's Committee assigned the Ho Chi Minh City Urban Railway Management Board to accelerate the construction progress, ensuring completion and commissioning in 2030.

This metro line was started on January 15, 2026, with a total length of nearly 11.3 km, of which more than 9 km is underground, the rest is the elevated section and access road to the depot.

Phối cảnh tuyến Metro số 2 (Bến Thành - Tham Lương) đoạn trên cao. Ảnh: MAUR
Perspective of Metro Ben Thanh - Tham Luong elevated section. Photo: MAUR

When operating, the Ben Thanh - Tham Luong Metro line uses a 3-carriage train, with a maximum speed of 80 - 110 km/h, with a transport capacity of about 14,400 passengers/hour/direction.

For Metro Line No. 2 (Ben Thanh - Thu Thiem section), the Chairman of Ho Chi Minh City People's Committee requested relevant units to urgently complete the slow procedures such as: establishing an appraisal council; appraisal team to select contractors; selecting consultants to appraise feasibility study reports; determining the route plan and land fund for BT contract payment.

The city emphasized that if delays continue, the heads of units will be held responsible before the Chairman of the Ho Chi Minh City People's Committee.

Ben Thanh - Thu Thiem Metro has been assigned by the Ho Chi Minh City People's Committee to Dai Quang Minh Real Estate Investment Joint Stock Company (a member of Truong Hai Group) to organize the preparation of a feasibility study report in the form of public-private partnership (PPP), construction - transfer (BT) contract.

Khu vực ga Thủ Thiêm của tuyến Metro Bến Thành - Thủ Thiêm và đường sắt Thủ Thiêm - Long Thành. Ảnh: Anh Tú
Thu Thiem station area of the Ben Thanh - Thu Thiem Metro line and Thu Thiem - Long Thanh railway. Photo: Anh Tu

This project has a length of about 5.58 km, including 6 underground stations, with a preliminary total investment of about 33,000 billion VND.

The route starts from the Ben Thanh area, follows Ham Nghi road, crosses the Saigon River to Thu Thiem, then runs along the Mai Chi Tho axis and ends at Thu Thiem station.

Ho Chi Minh City is speeding up procedures to start the project in April 2026, completing it before 2030.

The Thu Thiem - Long Thanh railway line is identified as a strategic connecting axis between the center of Ho Chi Minh City and Long Thanh airport. The line is about 42 km long, designed with a double track of 1,435 mm gauge, with a maximum speed of 120 km/h.

The entire route is expected to have 20 stations, including 16 elevated stations and 4 underground stations, with a preliminary total investment of about 84,753 billion VND.

The Thu Thiem - Long Thanh route has also been assigned to Dai Quang Minh Real Estate Investment JSC to study and prepare a feasibility study report.

The Chairman of the Ho Chi Minh City People's Committee requested departments and branches such as the Department of Finance, Department of Construction, Department of Agriculture and Environment, Department of Planning and Architecture... to closely coordinate to ensure synchronization in planning, technology, technical standards and the ability to connect the entire metro network.

Phối cảnh đường sắt Thủ Thiêm - Long Thành đi qua nút giao An Phú (TPHCM). Ảnh: Sở Xây dựng TPHCM
Perspective of the Thu Thiem - Long Thanh railway passing through An Phu intersection (HCMC). Photo: HCMC Department of Construction

The planned route runs along the corridor of the Ho Chi Minh City - Long Thanh - Dau Giay expressway and Ring Road 3, mainly through vacant land, convenient for site clearance.

Ho Chi Minh City sets a target to start construction of the Thu Thiem - Long Thanh route before June 30, 2026 and complete it in 2030.

When Metro Line 2 is extended from Tham Luong to Thu Thiem and connected to the Thu Thiem - Long Thanh urban railway line, Ho Chi Minh City will form a modern transport corridor, directly connecting Tan Son Nhat airport - Ho Chi Minh City center - Long Thanh airport.

Passengers from Tan Son Nhat airport can move to Ba Queo station to take Metro Line 2 to Ben Thanh station, continue to Thu Thiem station and connect the Thu Thiem - Long Thanh railway line to Long Thanh airport.

MINH QUÂN
RELATED NEWS

Ho Chi Minh City accelerates the extension of Metro Line No. 1 to Long Thanh airport

|

Ho Chi Minh City urgently implements preparation steps to extend Metro Line No. 1 (Ben Thanh - Suoi Tien) directly connecting to Long Thanh International Airport.

Ben Thanh - Thu Thiem Metro 33 trillion VND started construction before April 20

|

Ho Chi Minh City - Ben Thanh - Thu Thiem Metro is nearly 6 km long, with a total estimated investment of about 33,000 billion VND, expected to start construction before April 20.

Long Thanh airport is about to open, Ho Chi Minh City urgently completes connectivity

|

Ho Chi Minh City - Long Thanh Airport will be operational from mid-2026. Ho Chi Minh City directs acceleration of connecting transport projects to avoid congestion when the airport comes into operation.

Hai Phong Trade Union intervenes after workers' reflections on overtime

|

Hai Phong - In the afternoon of March 24, Hai Phong City Labor Federation worked with businesses after workers' reflections on working overtime on Sundays.

Vietnamese men's football and new hopes

|

A series of titles and promotion in the rankings once again bring many hopes for Vietnamese men's football in the near future.

The Vietnam Register speaks out about the proposal to abolish the exhaust gas test method

|

On March 24, the Vietnam Register spoke out about the proposal to abolish the method of pedaling the entire accelerator when checking emissions of some cars.

Fire burns down many properties inside a pub in Da Lat

|

Lam Dong - The fire that occurred at noon burned down many properties at a pub in Lam Vien ward - Da Lat, fortunately there were no casualties.

Hanoi is about to open for sale 254 social housing units in phase 1, priced from 14.9 million VND/m2

|

Hanoi - The Department of Construction has just announced a plan to receive applications to buy 254 social housing units (rented units for sale) at buildings N04, N05 of the Ecohome 3 project (phase 1).

Ho Chi Minh City accelerates the extension of Metro Line No. 1 to Long Thanh airport

MINH QUÂN |

Ho Chi Minh City urgently implements preparation steps to extend Metro Line No. 1 (Ben Thanh - Suoi Tien) directly connecting to Long Thanh International Airport.

Ben Thanh - Thu Thiem Metro 33 trillion VND started construction before April 20

MINH QUÂN |

Ho Chi Minh City - Ben Thanh - Thu Thiem Metro is nearly 6 km long, with a total estimated investment of about 33,000 billion VND, expected to start construction before April 20.

Long Thanh airport is about to open, Ho Chi Minh City urgently completes connectivity

MINH QUÂN |

Ho Chi Minh City - Long Thanh Airport will be operational from mid-2026. Ho Chi Minh City directs acceleration of connecting transport projects to avoid congestion when the airport comes into operation.