Preparing to complete 58km of expressway connecting the Mekong Delta to Long Thanh airport

Tâm Tú |

The 58km long Ben Luc - Long Thanh expressway is expected to be fully opened in September, connecting the Mekong Delta provinces with Long Thanh airport, reducing traffic congestion for Ho Chi Minh City.

After 12 years of construction with many delays, the Ben Luc - Long Thanh expressway project, 58km long, with a total investment of 31,300 billion VND, is expected to open the entire route in September. The project plays a strategic role in connecting the East and Southwest regions, helping to connect the Mekong Delta with Long Thanh airport and reduce traffic pressure for the inner city of Ho Chi Minh City.

Cao tốc Bến Lức - Long Thành đã hoàn thành khoảng 55/58 km, trong đó gần 26 km được khai thác tạm.
The Ben Luc - Long Thanh expressway has completed about 55/58 km, of which nearly 26 km is temporarily exploited. Photo: Anh Tu

Started in 2014 with the goal of completion after 5 years, the project was once temporarily suspended when it reached 80% of the volume due to problems with investment policy and capital sources. Up to now, according to Mr. Dang Huu Vi, Deputy Director of the Southern Expressway Project Management Board (SEPMU) under Vietnam Expressway Corporation (VEC), the construction output of construction packages has reached about 99% of the contract value. Nearly 55km of the total length of the route has been completed.

At My Yen intersection (Tay Ninh), the starting point of the Ben Luc - Long Thanh expressway connects to the Ho Chi Minh City - Trung Luong expressway and Ring Road 3. Currently, some branches in this area have been put into operation since the beginning of the year. The expressway is designed with 4 lanes, 2 emergency stop lanes, and a maximum speed of 100 km/h.

Cao tốc Bến Lức - Long Thành kết nối Quốc lộ 50 qua xã Đa Phước, TPHCM, mở thêm hướng đi từ khu vực phía Nam, phía Tây thành phố đến các tỉnh miền Tây.
The starting point of the Ben Luc - Long Thanh expressway is at My Yen intersection (Tay Ninh), connecting to the Ho Chi Minh City - Trung Luong expressway and Ring Road 3. Currently, the expressway section passing through here has allowed vehicles to circulate on some branches since the beginning of the year. Photo: Anh Tu.
Tuyến đường được thiết kế gồm 4 làn xe chạy, 2 làn dừng khẩn cấp, tốc độ tối đa 100 km/h.
The road is designed with 4 lanes for driving, 2 lanes for emergency stopping, maximum speed of 100 km/h. Photo: Anh Tu
Cao tốc Bến Lức - Long Thành, đoạn phía Tây từ Quốc lộ 1A đến Nguyễn Văn Tạo, đã hoàn thành và đưa vào khai thác, giúp phương tiện kết nối nút giao Mỹ Yên với Khu công nghiệp - cảng Hiệp Phước.
Ben Luc - Long Thanh expressway, the western section from National Highway 1A to Nguyen Van Tao, has been completed and put into operation, helping vehicles connect My Yen intersection with Hiep Phuoc Industrial Park - port. Anh: Anh Tu

Currently, the project only has two packages being focused on completion, including package J3-1 (Phuoc Khanh bridge) and package XL-NG51 (National Highway 51 intersection). In which, Phuoc Khanh bridge, 3.1km long across the Long Tau River, has just been joined and is being urgently completed to be put into operation in September 2026. Previously, Binh Khanh cable-stayed bridge, 2.76km long across the Soai Rap River, was completed but could not be put into use due to waiting for synchronous connection.

Cao tốc Bến Lức - Long Thành qua cầu Bình Khánh, cây cầu dây văng vượt sông Soài Rạp, kết nối Nhà Bè với Cần Giờ.
The Ben Luc - Long Thanh expressway through Binh Khanh bridge was completed in December 2025, the cable-stayed bridge across the Soai Rap river, connecting Nha Be with Can Gio. Although completed, it has not been exploited because Phuoc Khanh bridge has not been completed, and the entire route cannot be connected.
Cao tốc Bến Lức - Long Thành qua cầu Phước Khánh vượt sông Lòng Tàu, nút thắt cuối cùng của dự án, đang được hoàn thiện, dự kiến xong cuối tháng 9. Ảnh: Anh Tú
The Ben Luc - Long Thanh expressway through Phuoc Khanh bridge crossing the Long Tau River, the final bottleneck of the project, is being completed, expected to be completed by the end of September. Photo: Anh Tu

Regarding the operation situation, there are currently nearly 30km of expressway that have allowed temporary traffic, including the section from the Ho Chi Minh City - Trung Luong expressway intersection to Nguyen Van Tao intersection, about 22km long (through Tay Ninh province, Ho Chi Minh City) and the section from Phuoc An intersection to National Highway 51, about 7 km long (belonging to Dong Nai City). The remaining about 25 km, although basically completed, cannot be opened to traffic due to the lack of important connections at both ends of the route as well as the unfinished section between Binh Khanh and Phuoc Khanh bridges.

Chủ đầu tư cùng các nhà thầu đang khẩn trương triển khai các hạng mục còn lại để thông xe toàn tuyến vào tháng 9. Ảnh: Anh Tú
The investor and contractors are urgently deploying the remaining items to open the entire route to traffic in September. Photo: Anh Tu
Trong ảnh là điểm cuối dự án thuộc gói thầu XL-NG51 kết nối cao tốc Biên Hòa - Vũng Tàu và Quốc lộ 51, dự kiến hoàn thành cuối tháng 8.
In the photo is the end point of the project belonging to package XL-NG51 connecting the Bien Hoa - Vung Tau expressway and National Highway 51 being urgently constructed. Photo: Anh Tu

When officially put into operation, the Ben Luc - Long Thanh expressway through the My Yen intersection, National Highway 50, Nguyen Van Tao, Phuoc An and National Highway 51 will connect with the Ho Chi Minh City - Trung Luong expressway, Ring Road 3, Bien Hoa - Vung Tau expressway and major port clusters. The route forms a new traffic direction directly to Long Thanh airport, shortening travel time from the Mekong Delta provinces to Dong Nai City and significantly relieving traffic flow into the center of Ho Chi Minh City.

Tâm Tú
RELATED NEWS

Carefully study mechanisms and policies applied generally to expressways

|

Government leaders requested a careful study of mechanisms and policies applied generally to expressways in the 2026-2030 period, especially regulations on public investment and PPP.

Cat Lai ferry congestion nearly 2km, Ho Chi Minh City - Long Thanh expressway clear in the afternoon of September 2nd

|

Ho Chi Minh City - In the afternoon of September 2nd, the eastern gateway of the city was basically clear, especially Cat Lai ferry was crowded, cars lined up waiting to cross the ferry.

Current traffic situation on 2 expressways from Dong Nai to Ho Chi Minh City

|

Dong Nai - Phan Thiet - Dau Giay expressway and Ho Chi Minh City - Long Thanh - Dau Giay expressway in the direction from Phan Thiet to Ho Chi Minh City are clear on the morning of September 2.

Live Miss World 2026 Final

|

The Miss World 2026 final takes place at 7 pm on September 5th at 2/4 Square (Nha Trang, Khanh Hoa), gathering 111 beauties from countries and territories.

Live Cong An TPHCM vs Hanoi in round 1 of V.League 2026-2027

|

Live Cong An TPHCM vs Hanoi FC in round 1 of V.League 2026-2027, taking place at 6:00 PM today (September 5th).

Ho Chi Minh City to open a new 40m wide road to reduce traffic congestion at the Northwest gateway

|

Ho Chi Minh City - The Phan Van Hon parallel road, 9 km long, 40m wide, with a capital of more than 6,800 billion VND, is expected to reduce congestion at the Northwest gateway of Ho Chi Minh City.

Tasco's toll revenue decreased by more than 30%, VETC reports profit increase of nearly 9%

|

Tasco deploys non-stop toll collection activities through VETC. In the first half of 2026, Tasco's toll collection revenue decreased by more than 30% compared to the same period.

My Anh talks about the similarities and differences between her father Anh Quan and mother My Linh

|

My Anh shared about her journey of maturity in music with the companionship of diva My Linh and musician Anh Quan.

Carefully study mechanisms and policies applied generally to expressways

PHẠM ĐÔNG |

Government leaders requested a careful study of mechanisms and policies applied generally to expressways in the 2026-2030 period, especially regulations on public investment and PPP.

Cat Lai ferry congestion nearly 2km, Ho Chi Minh City - Long Thanh expressway clear in the afternoon of September 2nd

Anh Tú |

Ho Chi Minh City - In the afternoon of September 2nd, the eastern gateway of the city was basically clear, especially Cat Lai ferry was crowded, cars lined up waiting to cross the ferry.

Current traffic situation on 2 expressways from Dong Nai to Ho Chi Minh City

HÀ ANH CHIẾN |

Dong Nai - Phan Thiet - Dau Giay expressway and Ho Chi Minh City - Long Thanh - Dau Giay expressway in the direction from Phan Thiet to Ho Chi Minh City are clear on the morning of September 2.