On May 11, Khuong Dinh Ward People's Committee (Hanoi) issued a notice on receiving, handing over the site, and demolishing the project to implement the Ring Road 2.5 construction investment project from Nguyen Trai (National Highway 6) - Dam Hong.
Accordingly, Khuong Dinh Ward People's Committee is carrying out site clearance and deploying construction of the Ring Road 2.5 construction investment project, the section from Nguyen Trai - Dam Hong.
On May 14, Khuong Dinh Ward People's Committee will organize the receipt and handover of the site, and organize demolition to implement the project.
To ensure safety for the people, Khuong Dinh Ward People's Committee temporarily barricades the area of alley 345 Khuong Trung street (from the project implementation boundary to house number 47 alley 345 Khuong Trung street).
Time from 7 am on May 14 until further notice.
Khuong Dinh Ward People's Committee requests the political system of residential areas and residential groups in the ward to widely inform households and individuals to know and implement.

The Ring Road 2.5 project, Nguyen Trai - Dam Hong section, has a length of 1,520m, with a cross-section scale of 40m of roadbed.
This is a group A project, with a total investment of more than 2,432 billion VND; of which, site clearance costs account for more than 2,001 billion VND.
The total land area to be recovered is 60,902.1 m2, involving 736 cases, including 16 organizations and 720 households and individuals.
According to the People's Committee of Khuong Dinh ward, the site clearance for the Ring Road 2.5 project has been identified by the Party Committee and government of Khuong Dinh ward as a key task, with the strong involvement of the entire political system and functional forces in the area with a drastic, synchronous and highly responsible spirit.
As of May 3, the recovered land area reached 41,308.2 m2 out of a total of 60,902.1 m2, equivalent to 67.83%.