Workers on the "sleepless construction site" of the Chau Doc - Can Tho - Soc Trang expressway

Thành Nhân |

An Giang - Hundreds of engineers and workers are working "3 shifts, 4 crews", overnight on the Chau Doc - Can Tho - Soc Trang expressway, determined to bring the project to completion.

At about 7 pm on March 1st, the wind from the field blew strongly. Convoys of dump trucks lined up to carry materials to the construction site. The sound of engines, rollers, and bulldozers harmonized into the characteristic rhythm of a "sleepless mega-construction site". On the section passing through An Giang province, many construction teams were arranged to work overnight to keep up with the progress.

Công nhân thi công vào ban đêm trên công trường cao tốc đoạn qua tỉnh An Giang. Ảnh: Thành Nhân
Workers constructing at night on the expressway construction site section passing through An Giang province. Photo: Thanh Nhan

Mr. Duong Van Huy - Construction Technical Team of package 42 of the Chau Doc - Can Tho - Soc Trang expressway project - said that he has been attached to the project for more than 1 year. "During the day, the sun is harsh, the temperature is high, the road surface is both compacted and steaming hot. Working at night is less stuffy, and it avoids heavy traffic on temporary routes. It's hard, but the brothers are used to it," Mr. Huy shared.

Not far away, a group of workers is spreading a layer of crushed stone. Some are shoveling, some are scratching, some are checking the height. Under the construction site lights, sweat sparkles on the sunken faces. "The night is quiet, so work is more focused. However, absolute safety must be ensured, from the lighting system, traffic signs to traffic diversion," said Mr. Nguyen The Anh - technical officer of package 42 of the Chau Doc - Can Tho - Soc Trang expressway project (section through An Giang province).

Captain Tran Minh Thanh - Deputy Director of the Truong Son 11 Steering Committee (12th Corps) - informed that there are currently about 150 officials, engineers, and workers on the construction site along with nearly 100 vehicles, machinery, and equipment mobilized. Taking advantage of favorable weather conditions, the unit organizes continuous construction according to the motto "3 shifts, 4 crews", working day and night.

According to Captain Tran Minh Thanh, the unit determined that if working during the day is not on schedule, it is necessary to increase work at night. "However, do not neglect quality because of chasing the schedule. Each layer of material, each batch of concrete is strictly inspected according to technical standards," Captain Tran Minh Thanh emphasized.

Công nhân tranh thủ làm việc khi thời tiết thuận lợi. Ảnh: Thành Nhân
Workers take advantage of working when the weather is favorable. Photo: Thanh Nhan

Up to now, package 42 of the Chau Doc - Can Tho - Soc Trang expressway project has reached a construction volume of 73.8%. To ensure completion and traffic opening of the entire route on June 30, 2026 according to the direction of the Prime Minister, many construction teams are arranged to work in flexible shifts. At night, under the lights of the construction site, vehicles carrying materials still line up to enter and exit. Construction teams are continuously deployed, ensuring technical quality and labor safety," said Captain Tran Minh Thanh.

Thành Nhân
RELATED NEWS

200 workers construct the Chau Doc - Can Tho - Soc Trang expressway during the New Year holiday

|

An Giang - 200 officials, engineers, and workers constructing the Chau Doc - Can Tho - Soc Trang expressway, determined to stick to the construction site throughout the New Year.

Prime Minister requests technical opening of Chau Doc-Can Tho-Soc Trang expressway on June 30

|

Can Tho - Inspecting the component project of the Chau Doc-Can Tho-Soc Trang expressway, the Prime Minister requested that the project be technically opened to traffic by June 30.

Mobilizing machinery and human resources to construct the Chau Doc - Can Tho - Soc Trang expressway

|

An Giang - At the Chau Doc - Can Tho - Soc Trang expressway construction site (through An Giang), the contractor mobilized all resources to aim for the end of June 2026.

Chain collision between 4 cars in Ho Chi Minh City, driver trapped in cabin

|

Ho Chi Minh City - On National Highway 13, a chain accident occurred between 4 cars, a driver trapped inside the cabin was rescued.

Hanoi requests private schools not to collect reservation fees and deposits for grade 10 classes

|

The Hanoi Department of Education and Training requires high-quality private high schools not to collect reservation fees or deposits for the 2026 - 2027 school year.

Chairman of Dong Nai province urgently directs the case of lowering the roadbed level causing precarious houses

|

Dong Nai - Chairman of the Provincial People's Committee directs urgent verification and inspection of information about lowering the ground level of DT. 753 road, causing many houses to be precarious on the edge of the abyss.

Emission testing for diesel engines, many vehicle registration facilities worry about risks of damage

|

On some forums, there is a buzzing document committing to voluntarily conduct emission tests for diesel engines.

Ho Chi Minh City adds 50 points to install battery exchange cabinets, accelerating electric motorbike infrastructure

|

Ho Chi Minh City has 50 more locations eligible to install electric motorbike battery exchange cabinets on sidewalks, raising the total number of points allowed to be deployed throughout the area to 102 locations.

200 workers construct the Chau Doc - Can Tho - Soc Trang expressway during the New Year holiday

Thành Nhân |

An Giang - 200 officials, engineers, and workers constructing the Chau Doc - Can Tho - Soc Trang expressway, determined to stick to the construction site throughout the New Year.

Prime Minister requests technical opening of Chau Doc-Can Tho-Soc Trang expressway on June 30

TẠ QUANG |

Can Tho - Inspecting the component project of the Chau Doc-Can Tho-Soc Trang expressway, the Prime Minister requested that the project be technically opened to traffic by June 30.

Mobilizing machinery and human resources to construct the Chau Doc - Can Tho - Soc Trang expressway

Thành Nhân |

An Giang - At the Chau Doc - Can Tho - Soc Trang expressway construction site (through An Giang), the contractor mobilized all resources to aim for the end of June 2026.