The first hundred billion industrial cluster in poor district Thai Nguyen

Nguyễn Hoàn |

Thai Nguyen - After 2 years of construction, the Tan Duong Industrial Cluster project deployed in the poor district of Dinh Hoa with a total investment of more than 450 billion VND is about to be completed.

Tan Duong Industrial Cluster project has a total investment of more than 450 billion VND, invested by Thagaco International Investment Joint Stock Company, and started construction in November 2022.

The project is deployed on an area of ​​13 hectares in Tan Duong commune (Dinh Hoa, Thai Nguyen), with a prime traffic location, next to provincial road 254, Ho Chi Minh road and surrounded by densely populated areas.

On January 7, according to PV, after more than 2 years of implementation, the Tan Duong industrial cluster project has gradually taken shape and completed basic infrastructure items.

Inside the project, the ground, embankment, and fence of the industrial park have been completed. At the construction site, workers and machines are constructing internal roads, water supply and drainage systems, wastewater treatment, and auxiliary items.

To implement the industrial cluster, more than 200 households had their land confiscated, mainly rice fields and production forests. Mr. Nguyen Cong Hieu (Tan Duong commune) said that when the information about the project being implemented in the area was received, the people were very sympathetic and supportive.

Toan canh du an cum cong nghiep Tan Duong sau 2 nam khoi cong. Anh: Nguyen Hoan.
Overview of Tan Duong Industrial Park project after 2 years of construction. Photo: Nguyen Hoan.

"Many children of these families currently have to work in companies and industrial parks far from home. When the project was brought back, the people were very happy and excited because this was the first large project to be implemented in the poor district of Dinh Hoa. When the project is completed and put into operation, it will certainly create many jobs, people will have jobs right in the locality, no need to go far to find work anymore", Mr. Hieu shared.

According to the investor, Tan Duong Industrial Park project is the first industrial park with the largest scale in Dinh Hoa district, expected to be completed in the first quarter of 2025.

After completing the infrastructure, the investor will build a factory and install a production line with a capacity of 2.2 million garment products/year. It is expected to create regular jobs for nearly 4,500 workers.

The industrial cluster will also attract projects for processing agricultural, forestry and food products and other industrial and handicraft sectors in accordance with local planning.

Speaking to reporters, a leader of Tan Duong Commune People's Committee said that the construction process at the project was very favorable, and the people agreed and supported it.

"The district sent 32 people to the commune to learn sewing so that they can later work in the industrial park. This is one of the key and meaningful projects for the locality. When completed, it will create many jobs for workers and thereby help develop the local economy," the commune leader informed.

Some images recorded at the project:

Mat bang du an cum cong nghiep Tan Duong da hoan thanh.
Tan Duong industrial park project site has been completed.
Bo ke, tuong bao va he thong dien co ban hoan thien.
Embankment, surrounding wall and basic electrical system completed.
Duong dan vao cum cong nghiep dang khan truong thi cong nhung hang muc cuoi cung.
The road leading to the industrial park is urgently under construction of the final items.
Ben trong du an, may moc gap rut trien khai thi cong.
Inside the project, machinery is rushing to deploy construction.
Khu vuc duong noi bo trong cum cong nghiep da thi cong dan hinh thanh.
Internal road area in the industrial park has been formed.

According to information from the State Treasury of Thai Nguyen province, the province's budget revenue in 2023 will reach over 20,000 billion VND. Of which, the lowest is Dinh Hoa district with a revenue of 63.7 billion VND, accounting for only over 0.31% of the total budget in the province; the highest belongs to Pho Yen city with 2,855 billion VND, accounting for over 14.2%.

Nguyễn Hoàn
TIN LIÊN QUAN

A border province has an additional 280 billion VND industrial cluster

|

Lang Son - Bac Son 2 Industrial Park with a scale of nearly 25 hectares and a total investment of over 280 billion VND has just started construction.

Strong cold air is coming near Lunar New Year 2025

|

According to a representative of the meteorological agency, cold air close to Lunar New Year 2025 will cause the weather in the North to turn cold with light rain.

RHYDER: I used to be bored and had nothing before I came to Say Hi Brother

|

In "Saturday Afternoon Coffee" with Lao Dong, singer RHYDER shared about the changes after coming out of the show "Anh trai say hi".

Solution to punish using phone at gas station

|

The proposal to fine 5-7 million VND for using cell phones at gas stations has received much attention and agreement, with the goal of ensuring fire safety.

Vietnamese rice rises to the world's Top 3 and challenges in 2025

|

In 2024, the Vietnamese rice industry will set an export record, rising to the world's Top 3. However, in 2025, the industry will face many challenges from global competition and price fluctuations. Quality and brand will be the decisive factors in helping Vietnamese rice maintain sustainable development.

A border province has an additional 280 billion VND industrial cluster

Khánh Linh |

Lang Son - Bac Son 2 Industrial Park with a scale of nearly 25 hectares and a total investment of over 280 billion VND has just started construction.

Cụm công nghiệp gần 30ha tại TP Thái Nguyên vướng mặt bằng

Lam Thanh |

Việc chậm giải phóng mặt bằng, bố trí tái định cư khiến dự án cụm công nghiệp Sơn Cẩm 3 (TP Thái Nguyên) triển khai chậm trễ.

Cụm công nghiệp trăm tỉ ở Thái Nguyên lâm cảnh hoang tàn

Việt Bắc |

Thái Nguyên - Sau hơn 5 năm triển khai, dự án Cụm công nghiệp Bá Xuyên (TP Sông Công) tổng mức đầu tư trên 431 tỉ đồng vẫn dang dở, lâm vào cảnh hoang tàn.