Long Thanh airport control tower 2 months ahead of schedule

HÀ ANH CHIẾN |

Dong Nai - The air traffic control tower project of Long Thanh airport component 2 is about 2 months ahead of schedule.

On December 10, Minister of Transport Tran Hong Minh and his delegation worked on the progress of the Long Thanh airport project in Dong Nai province.

Reporting at the meeting, a representative of the Department of Construction Investment Management - Ministry of Transport said that the Long Thanh airport project has 4 component projects.

In which, with component project 1 - the headquarters of agencies and units, currently 3 headquarters including the Airport Authority, the Immigration Department and the local police are planned to be completed before December 31, 2025. The Customs headquarters is planned to be completed in June 2026. The Animal and Plant Quarantine Station is being deployed.

Component project 2 - air traffic control works, has one completed construction package, 2 construction and installation packages are being implemented, meeting the schedule, expected to be completed in September 2025; 5 specialized equipment packages are selecting contractors, expected to be completed by December 31, 2025.

The investor representative also said that the Long Thanh airport air traffic control tower has completed the rough construction, about 2 months ahead of schedule.

Component project 3 - construction of taxiways and runways is scheduled to be completed by April 30, 2025.

Bo truong Bo Giao thong van tai Tran Hong Minh cung doan cong tac lam viec ve tien do du an san bay Long Thanh ngay 10.12. Anh: HAC
Minister of Transport Tran Hong Minh and his delegation worked on the progress of the Long Thanh airport project on December 10. Photo: HAC

Minister of Transport Tran Hong Minh requested the Vietnam Airports Corporation (ACV) and contractors to focus maximum human and material resources to speed up progress; negotiate with contractors to purchase equipment to bring it in as soon as possible, completing the Long Thanh airport passenger terminal before December 31, 2025.

Regarding the second runway, the National Assembly has just approved the investment policy, the Minister requested the investor and relevant units to promptly implement the procedures, if necessary, appoint contractors with experience in constructing the first runway to shorten the progress and must complete before December 31, 2025.

The Minister also requested the leaders of Dong Nai province to support the licensing of material mines to construct roads to the airport. At the same time, carry out site clearance work to construct a fuel pipeline from Go Dau port to Long Thanh airport.

HÀ ANH CHIẾN
TIN LIÊN QUAN

Dong Nai auctions 282-hectare land plot next to Long Thanh airport

|

Dong Nai Province Land Fund Development Center proposed to auction a 282-hectare land plot in Binh Son Commune, Long Thanh District, near Long Thanh Airport, worth VND7,400 billion.

Strictly handle officials who obstruct and delay the implementation of Long Thanh airport

|

On the morning of December 3, during his working program in the South, Politburo member and Prime Minister Pham Minh Chinh inspected the construction of Long Thanh International Airport project and the traffic system connecting to Long Thanh International Airport.

Prime Minister Pham Minh Chinh inspects Long Thanh airport project

|

Dong Nai - On December 3, Prime Minister Pham Minh Chinh and the Central working delegation inspected the progress of the Long Thanh airport project.

Will Nguyen Xuan Son start in the match between Vietnam and Myanmar?

|

Vietnam team will meet Myanmar at ASEAN Cup on the evening of December 21 at Viet Tri Stadium. Sports Viewpoint No. 194 and commentator Hoang Hai predict Nguyen Xuan Son's position.

Putin reveals regrets about the campaign in Ukraine

|

Russian President Vladimir Putin said that the decision to launch a military operation in Ukraine should probably be made earlier than 2022.

Hanoi investors look to the provinces to "hunt" for cheap land

|

Real estate investors in Hanoi are tending to look to neighboring provinces such as Bac Ninh, Bac Giang, Ha Nam, and Hung Yen to "hunt" for cheap land.

Forecast of affected areas in Vietnam when low pressure enters the East Sea

|

The low pressure system in the Philippines is likely to strengthen as it moves east of the Truong Sa archipelago in the South China Sea.

Deadline for completing the arrangement of departments and branches under the Provincial People's Committee

|

Before February 20, 2025 is the expected time for localities to complete the organization of specialized agencies under the People's Committees at the provincial and district levels.

Dong Nai auctions 282-hectare land plot next to Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai Province Land Fund Development Center proposed to auction a 282-hectare land plot in Binh Son Commune, Long Thanh District, near Long Thanh Airport, worth VND7,400 billion.

Strictly handle officials who obstruct and delay the implementation of Long Thanh airport

HÀ ANH CHIẾN |

On the morning of December 3, during his working program in the South, Politburo member and Prime Minister Pham Minh Chinh inspected the construction of Long Thanh International Airport project and the traffic system connecting to Long Thanh International Airport.

Prime Minister Pham Minh Chinh inspects Long Thanh airport project

HÀ ANH CHIẾN |

Dong Nai - On December 3, Prime Minister Pham Minh Chinh and the Central working delegation inspected the progress of the Long Thanh airport project.