Long Thanh airport control tower 2 months ahead of schedule

HÀ ANH CHIẾN |

Dong Nai - The air traffic control tower project of Long Thanh airport component 2 is about 2 months ahead of schedule.

On December 10, Minister of Transport Tran Hong Minh and his delegation worked on the progress of the Long Thanh airport project in Dong Nai province.

Reporting at the meeting, a representative of the Department of Construction Investment Management - Ministry of Transport said that the Long Thanh airport project has 4 component projects.

In which, with component project 1 - the headquarters of agencies and units, currently 3 headquarters including the Airport Authority, the Immigration Department and the local police are planned to be completed before December 31, 2025. The Customs headquarters is planned to be completed in June 2026. The Animal and Plant Quarantine Station is being deployed.

Component project 2 - air traffic control works, has one completed construction package, 2 construction and installation packages are being implemented, meeting the schedule, expected to be completed in September 2025; 5 specialized equipment packages are selecting contractors, expected to be completed by December 31, 2025.

The investor representative also said that the Long Thanh airport air traffic control tower has completed the rough construction, about 2 months ahead of schedule.

Component project 3 - construction of taxiways and runways is scheduled to be completed by April 30, 2025.

Bo truong Bo Giao thong van tai Tran Hong Minh cung doan cong tac lam viec ve tien do du an san bay Long Thanh ngay 10.12. Anh: HAC
Minister of Transport Tran Hong Minh and his delegation worked on the progress of the Long Thanh airport project on December 10. Photo: HAC

Minister of Transport Tran Hong Minh requested the Vietnam Airports Corporation (ACV) and contractors to focus maximum human and material resources to speed up progress; negotiate with contractors to purchase equipment to bring it in as soon as possible, completing the Long Thanh airport passenger terminal before December 31, 2025.

Regarding the second runway, the National Assembly has just approved the investment policy, the Minister requested the investor and relevant units to promptly implement the procedures, if necessary, appoint contractors with experience in constructing the first runway to shorten the progress and must complete before December 31, 2025.

The Minister also requested the leaders of Dong Nai province to support the licensing of material mines to construct roads to the airport. At the same time, carry out site clearance work to construct a fuel pipeline from Go Dau port to Long Thanh airport.

HÀ ANH CHIẾN
RELATED NEWS

Dong Nai auctions 282-hectare land plot next to Long Thanh airport

|

Dong Nai Province Land Fund Development Center proposed to auction a 282-hectare land plot in Binh Son Commune, Long Thanh District, near Long Thanh Airport, worth VND7,400 billion.

Strictly handle officials who obstruct and delay the implementation of Long Thanh airport

|

On the morning of December 3, during his working program in the South, Politburo member and Prime Minister Pham Minh Chinh inspected the construction of Long Thanh International Airport project and the traffic system connecting to Long Thanh International Airport.

Prime Minister Pham Minh Chinh inspects Long Thanh airport project

|

Dong Nai - On December 3, Prime Minister Pham Minh Chinh and the Central working delegation inspected the progress of the Long Thanh airport project.

Vietnam welcomes ceasefire agreement between the US and Iran

|

Vietnam welcomes the ceasefire agreement just reached on April 7, 2026 between the US and Iran.

Live Vietnam futsal team vs Thailand at the 2026 Southeast Asian Championship

|

Live football match between Vietnam futsal team and Thailand futsal team at the 2026 Southeast Asian Futsal Championship at 8:00 PM tonight (April 8th).

Expelled from the Party former Chairman, Deputy General Director in charge of ACV

|

Former Chairman of the Board of Directors of Vietnam Airports Corporation Lai Xuan Thanh and Deputy General Director in charge Nguyen Tien Viet were expelled from the Party.

27,000 tons more LNG arrives at Ho Chi Minh City port

|

HCMC - KOOL BLIZZARD ship carrying 27,000 tons of LNG has safely docked at Cai Mep - Thi Vai port area.

US commits to Israel on Iran's goal of complete denuclearization

|

Israel said the US has agreed with the country on its persistent request for Iran to eliminate all nuclear materials and ballistic missiles during the 14-day ceasefire.

Dong Nai auctions 282-hectare land plot next to Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai Province Land Fund Development Center proposed to auction a 282-hectare land plot in Binh Son Commune, Long Thanh District, near Long Thanh Airport, worth VND7,400 billion.

Strictly handle officials who obstruct and delay the implementation of Long Thanh airport

HÀ ANH CHIẾN |

On the morning of December 3, during his working program in the South, Politburo member and Prime Minister Pham Minh Chinh inspected the construction of Long Thanh International Airport project and the traffic system connecting to Long Thanh International Airport.

Prime Minister Pham Minh Chinh inspects Long Thanh airport project

HÀ ANH CHIẾN |

Dong Nai - On December 3, Prime Minister Pham Minh Chinh and the Central working delegation inspected the progress of the Long Thanh airport project.