The leader of Kien Thuy District Party Committee has just checked the construction progress of investment projects to build roads connecting provincial road 354 through Kien Thuy industrial park to coastal roads in Doan Xa commune. Du an co tong muc dau tu 924,238 ti dong tu nguon ngan sach TP Hai Phong, khoi cong ngay 10.5.2020.
Through the report, until 14.4, the project reached 70% of the progress. Specifically, for the construction progress of the contractor, Vietnam Australia Company (6.28 km long from km 8+500 to km14+780) has completed the loading work; Complete mountain soil on the road floor 4.5 km/6.28 km; Sugar carpet 1 1.6/6.28km. It is expected that the bidding package will complete 100% of the 1st road surface carpet and clear in June 62025.
The construction progress of the contractor is Hoang Loc Company (5.9 km long from km 3+100 to km8+500) has now completed Base A 100%; Class 1 pavement carpet 3.5 km/5.4 km. It is expected that the end of April 2025, the company will complete 100% of the remaining 1st class pavement carpet and clear the bidding package.
The contractor is Phuong Dong Company, which is 1.64 km long from km 1+460 to km3+100 up to now, has completed the loading work, which is implementing the construction of the road floor. Du kien, cac hang muc hoan thanh trong thang 8.2025.
Bidding package Hai Nam Company (length of 1.46km from km 0+00 to km1+460), expected to complete the entire item in June 2025.
Through actual inspection at the project, Mr. Do Duc Hoa - Secretary of Kien Thuy District Party Committee requested the district's specialized agencies, the investor focused on removing difficulties, speeding up the construction progress, ensuring the quality and planning.