Speeding up the transport project of more than 920 billion dong in Hai Phong

Hoàng Khôi |

Hai Phong - The project of investing in construction of provincial road 354 through Kien Thuy industrial park to coastal road has reached 70% of progress.

The leader of Kien Thuy District Party Committee has just checked the construction progress of investment projects to build roads connecting provincial road 354 through Kien Thuy industrial park to coastal roads in Doan Xa commune. Du an co tong muc dau tu 924,238 ti dong tu nguon ngan sach TP Hai Phong, khoi cong ngay 10.5.2020.

Through the report, until 14.4, the project reached 70% of the progress. Specifically, for the construction progress of the contractor, Vietnam Australia Company (6.28 km long from km 8+500 to km14+780) has completed the loading work; Complete mountain soil on the road floor 4.5 km/6.28 km; Sugar carpet 1 1.6/6.28km. It is expected that the bidding package will complete 100% of the 1st road surface carpet and clear in June 62025.

The construction progress of the contractor is Hoang Loc Company (5.9 km long from km 3+100 to km8+500) has now completed Base A 100%; Class 1 pavement carpet 3.5 km/5.4 km. It is expected that the end of April 2025, the company will complete 100% of the remaining 1st class pavement carpet and clear the bidding package.

The contractor is Phuong Dong Company, which is 1.64 km long from km 1+460 to km3+100 up to now, has completed the loading work, which is implementing the construction of the road floor. Du kien, cac hang muc hoan thanh trong thang 8.2025.

Bidding package Hai Nam Company (length of 1.46km from km 0+00 to km1+460), expected to complete the entire item in June 2025.

Through actual inspection at the project, Mr. Do Duc Hoa - Secretary of Kien Thuy District Party Committee requested the district's specialized agencies, the investor focused on removing difficulties, speeding up the construction progress, ensuring the quality and planning.

Hoàng Khôi
TIN LIÊN QUAN

The largest largest freshwater lake in Hai Phong

|

Hai Phong - Since Storm Yagi in 2024, the pearl freshwater reservoir (Hai Phong) has been eroded, degraded, affected by the supply of daily -life water for Cat Ba Island.

Hong Bang District Job Fair, Hai Phong attracts nearly 1,000 workers

|

Hai Phong - On April 12, nearly 1,000 people attended the job fair and career counseling in Hong Bang district, Hai Phong in 2025.

Technical traffic opening of Bien Hoa - Vung Tau Expressway Component 3 Project

|

Ba Ria - Vung Tau has 4 projects that were started and inaugurated on April 19 to celebrate the 50th anniversary of the country's reunification.

Many school officials pay a total of 4.2 billion VND to fix admission violations

|

Thanh Hoa - To overcome the consequences of enrolling the wrong subjects, many cadres and leaders of the school have voluntarily paid a total of 4.2 billion VND.

US changes strategy, Crimea becomes a card despite Ukraine peace negotiations

|

Bloomberg News reported that the US is ready to recognize Crimea as Russia's in the peace deal in Ukraine.

Forecast of thunderstorms in the area before the April 30 - May 1 holiday

|

According to the representative of the meteorological agency, before the April 30 - May 1 holiday, the North is likely to have showers and thunderstorms, and the temperature will decrease.

Former Vice President Nguyen Thi Binh was in tears when signing the Paris Agreement

|

Former Vice President Nguyen Thi Binh is the only woman to sign the historic Paris Agreement on January 27, 1973.

VEC sues many partners, demands land for Noi Bai - Lao Cai expressway rest stop

|

Vietnam Expressway Corporation (VEC) has sued many investors in rest stops on the Noi Bai - Lao Cai Expressway for breach of contract.

Tước giấy phép lái xe của tài xế cố tình vượt đường ngang ở Hải Phòng

Hoàng Khôi |

Hải Phòng - Phòng Cảnh sát giao thông Công an TP vừa xử phạt lái xe ôtô đi vào đường ngang khi cần chắn đã đóng.

The largest largest freshwater lake in Hai Phong

Mai Dung |

Hai Phong - Since Storm Yagi in 2024, the pearl freshwater reservoir (Hai Phong) has been eroded, degraded, affected by the supply of daily -life water for Cat Ba Island.

Hong Bang District Job Fair, Hai Phong attracts nearly 1,000 workers

Mai Dung |

Hai Phong - On April 12, nearly 1,000 people attended the job fair and career counseling in Hong Bang district, Hai Phong in 2025.