Speed up the progress of expressway rest stops after having the site

Duy Tuấn |

Binh Thuan - People have handed over nearly 10 hectares of land in advance to construct the Vinh Hao - Phan Thiet expressway rest stop at Km205.

The Vinh Hao - Phan Thiet Expressway is planned to have 2 rest stops at Km205+092 through Ham Thuan Bac district and at Km144+560 through Tuy Phong district, Binh Thuan province. The area of each station is 10 hectares, including the left and right sides of the route.

Duong gom dan sinh di ngang vi tri thi cong tram dung nghi cao toc Vinh Hao - Phan Thiet o km205. Anh: Duy Tuan
The residential road passes along the construction site of the Vinh Hao - Phan Thiet expressway rest stop at km205. Photo: Duy Tuan

Currently, at Km205, there are rest stops on both sides of the route and on the left side of the route, which will operate from January 20 for cars to stop and rest, eat and go to the toilet. The construction part of the rest stop and the operation part of the temporary rest stop are fenced off to ensure construction safety.

Cac vat lieu thi cong tai cong truong. Anh: Duy Tuan
Construction materials at the construction site. Photo: Duy Tuan
Xe lu tai cong truong. Anh: Duy Tuan
Road rollers at the construction site. Photo: Duy Tuan

Recorded on the afternoon of March 21 at the construction site of the Vinh Hao - Phan Thiet expressway rest stop at Km205, many dump trucks carrying soil and rocks came to level the ground on the right side of the route. The project operator on the left side of the route has also been relocated to a nearby location for construction.

Nha dieu hanh tai cong truong duoc doi ra vi tri khac. Anh: Duy Tuan
The operator at the construction site was moved to another location. Photo: Duy Tuan

According to the Department of Construction of Binh Thuan province, up to now, the People's Committee of Ham Thuan Bac district has mobilized people to hand over 100% (9.97ha) of the rest stop at Km 205 to investors for construction. This locality has also submitted to the Department of Agriculture and Environment for appraisal and adjustment of the District-level Land Use Plan for the period (2021 - 2030), with a vision to 2050. The Department of Agriculture and Environment is collecting comments from relevant departments and branches to synthesize reports for the Provincial People's Committee to consider and approve. After the District Land Use Plan is approved, Ham Thuan Bac District People's Committee will carry out land acquisition procedures according to regulations.

Tram dung nghi tam hoat dong trong khu vuc thi cong va duoc ngan cach bang luoi rao. Anh: Duy Tuan
The temporary rest stop operates in the construction area and is separated by a fence. Photo: Duy Tuan

As for the rest stop at Km 144+560, Tuy Phong District People's Committee is currently actively working with organizations and households in the project area to hand over land to investors to have construction site.

Xe ben cho dat da toi cong truong thi cong chieu 21.3. Anh: Duy Tuan
Dump trucks carrying soil and rocks arrived at the construction site on the afternoon of March 21. Photo: Duy Tuan

The Project Management Board 7 (Ministry of Construction) is the investor of Vinh Hao - Phan Thiet Expressway, hoping that the locality will soon hand over the site to implement the construction.

Cot moc vi tri giai phong mat bang de lam tram dung nghi. Anh: Duy Tuan
Marker of site clearance for rest stops. Photo: Duy Tuan

Director of the Department of Agriculture and Environment of Binh Thuan province, Cao Son Dung, requested the People's Committee of Tuy Phong district to urgently speed up the compensation and site clearance progress of the rest stop at Km 144+560 to ensure the project is implemented according to the required schedule. Tuy Phong District People's Committee urgently speeds up the progress of submitting to competent authorities for appraisal and approval of adjustment of the Land Use Plan for rest stops at Km 144+560 to carry out land acquisition procedures according to regulations. The Department will have a document guiding Tuy Phong District People's Committee to resolve difficulties and problems in compensation and site clearance for organizations and individuals.

Xung quang cong truong duoc rao day. Anh: Duy Tuan
The construction site is fenced with ropes. Photo: Duy Tuan
Doan cao toc Vinh Hao - Phan Thiet gan den tram dung nghi km205. Anh: Duy Tuan
The Vinh Hao - Phan Thiet expressway section is near the rest stop at Km205. Photo: Duy Tuan

The Vinh Hao - Phan Thiet Expressway is 100.8km long, the entire route passes through Binh Thuan province and was put into operation, exploiting the main route from May 19, 2023, inaugurated on June 18, 2023.

Duy Tuấn
TIN LIÊN QUAN

Damage to the residential access road due to the construction of the expressway rest stop

|

Binh Thuan - Many dump trucks carrying materials damaged the residential road near the construction site of the Vinh Hao - Phan Thiet expressway rest stop.

The backup plan is to move the location to make a highway rest stop

|

Binh Thuan - Backup plan to move the Vinh Hao - Phan Thiet expressway rest stop from Km144 to Km147 for more convenience in site clearance and to keep up with progress.

Safety risks along Vinh Hao - Phan Thiet highway

|

Binh Thuan - Many potential safety risks come from people along the Vinh Hao - Phan Thiet highway such as walking along the highway to collect scrap metal, spontaneous shops...

Strong earthquake in Tonga just a few days after Myanmar earthquake

|

A 7.1-magnitude earthquake near Tonga prompted an initial Tsunami warning but was later lifted.

The Cong Viettel beat Hoang Anh Gia Lai to advance to the semi-finals of the National Cup

|

On the evening of March 30, The Cong Viettel defeated Hoang Anh Gia Lai with a score of 2-0 to win a ticket to the semi-finals of the 2024-2025 National Cup.

Updated gold price at the end of session 30.3: Profit despite surfing

|

Updated gold price at the end of the session on March 30: The difference between buying and selling is at a high level, investors still make a profit even if investing in the short term.

The army and police set out to support overcoming the consequences of the earthquake

|

The delegation of officers and soldiers of the Ministry of National Defense and the Ministry of Public Security have set out to support Myanmar in overcoming the consequences of the earthquake.

Waiting for the end of living with wastewater in industrial parks

|

Quang Tri - The lives of people living next to industrial parks have been disrupted by wastewater. Meanwhile, the wastewater treatment plant has not yet come into operation

Damage to the residential access road due to the construction of the expressway rest stop

Duy Tuấn |

Binh Thuan - Many dump trucks carrying materials damaged the residential road near the construction site of the Vinh Hao - Phan Thiet expressway rest stop.

The backup plan is to move the location to make a highway rest stop

Duy Tuấn |

Binh Thuan - Backup plan to move the Vinh Hao - Phan Thiet expressway rest stop from Km144 to Km147 for more convenience in site clearance and to keep up with progress.

Safety risks along Vinh Hao - Phan Thiet highway

Duy Tuấn |

Binh Thuan - Many potential safety risks come from people along the Vinh Hao - Phan Thiet highway such as walking along the highway to collect scrap metal, spontaneous shops...