Sluggish construction of flood dyke, Phu Tho issues ultimatum

Minh Chuyên - Xuyên Đông |

The Pheo - Che flood and flood control dyke project (Phu Tho province) has a total investment of nearly 600 billion VND, initially expected to be completed in 2025. However, the current progress is still slow. Provincial leaders requested to finalize the progress and put the project into operation in 2026.

People yearn

The urgent dike project to prevent floods and flooding in Pheo - Che has a total investment of more than 597 billion VND, invested by the Project Management Board of Agricultural Works of Hoa Binh province (old), now the Project Management Board of Hoa Binh area.

The project has a scale of renovating and upgrading the dike line combined with a 15.8km long traffic road, stretching from Pheo area (Ky Son ward) to Che area (Thinh Minh commune, bordering Hanoi). The goal is to ensure safety for flood prevention and control, flood control in the downstream area of the Da River, and at the same time connect inter-regional traffic between Hoa Binh - Phu Tho - Hanoi.

The project started in March 2024, and is scheduled to be completed by the end of 2025. However, records from early April 2026 show that the construction progress is slower than required. Many items are still unfinished, although some locations have been basically formed.

In Thinh Minh commune, Ms. Bui Thi Lan said that the existing road is narrow and degraded, and transporting agricultural products is difficult. Local people expect the project to be completed soon to facilitate trade, economic development and improve living standards.

Reality shows that, although it is an urgent project to serve flood prevention and control and flooding prevention, the implementation is still not decisive. Some sections are under construction, not synchronized, directly affecting the efficiency of connection and people's lives in the area.

Request to finalize progress and operation in 2026

Faced with the delay situation, Vice Chairman of Phu Tho Provincial People's Committee Dinh Cong Su directly inspected and urged the project progress. The conclusion after inspection shows that the current implementation progress is very slow, not meeting the direction requirements of the province. The investor has not been decisive at locations where land has been cleared. The coordination to remove difficulties is still not proactive.

The contractor has not arranged enough manpower and construction equipment. In particular, site clearance is still slow, becoming the biggest bottleneck affecting project progress.

Faced with this situation, the leaders of Phu Tho province requested the Hoa Binh Regional Project Management Board to urgently build a detailed progress chart, ensuring 100% disbursement of capital in 2026 and putting the project into operation this year. The investor is assigned to direct contractors to increase manpower, equipment, and supplement construction teams. Bridge and culvert items must be prioritized for completion before the rainy season. In which, Ngoi Tom bridge is required to be completed before May 31, 2026.

In parallel with that, the weekly progress reporting regime must be strictly implemented to promptly remove arising problems.

The Provincial People's Committee also requested relevant localities including Hoa Binh ward, Ky Son ward and Thinh Minh commune to identify this as a key task. Propaganda and mobilization of people to hand over land needs to be promoted.

Specific time milestones are given: Complete resettlement arrangement, relocate households before April 2026; review policies for 24 households in the paper factory collective area and 8 households at the beginning of the route; complete all site clearance no later than July 2026.

Leaders of Phu Tho province emphasized the requirement to focus maximum resources and accelerate construction progress so that the project is completed on schedule. When completed, the project will not only contribute to reducing flooding in the downstream area of the Da River but also create motivation for socio-economic development and strengthen inter-regional connectivity.

Minh Chuyên - Xuyên Đông
RELATED NEWS

Urgent progress of the 600 billion VND flood prevention and control dike project along the Da River

|

Phu Tho - The urgent project of flood prevention and control of Pheo - Che flooded area, in Ky Son ward with a total investment of nearly 600 billion VND is at risk of being behind schedule.

Urgent request to handle the damaged flood dike incident in Quang Tri

|

Quang Tri - After being affected by storm No. 6, the Ben Hai left dike was directly affected by flooding, causing many locations on the dike to be severely damaged and eroded.

Mai Thu Huyen: I really hate the phrase "mobile vase

|

In "Samediday Afternoon Coffee", producer, director, actress Mai Thu Huyen shared her perspective on the development of the film industry in 2026.

Cold storage fire in Bui Xuong Trach, 6 motorbikes and cars burned down

|

Hanoi - A cold storage fire on Bui Xuong Trach street (Khuong Dinh ward) caused many properties to be burned down, including 6 motorbikes and 1 truck.

People discover a bullet and explosives in the Ba River area

|

Gia Lai - Police warn people not to move or dig up explosives and remaining bombs and bullets.

Death certificate, marriage registration "how important" without authorization

|

The delegate wondered, a deceased person needs a death certificate for burial, how to handle not authorizing the Chairman of the Commune People's Committee when this person is busy attending a meeting?

Gia Lai discovers redundant teaching to extend holidays to 9 days

|

Gia Lai - Discovering make-up teaching to extend the April 30 - May holiday to 9 days, the Department of Education and Training requests affiliated units to rectify and not arbitrarily adjust the teaching schedule.

Chili prices fall more than ten times compared to last year, Quang Ngai farmers suffer heavy losses

|

Quang Ngai - Chili prices in the province have dropped sharply, only about 5,000 VND/kg, causing chili farmers to suffer heavy losses.

Urgent progress of the 600 billion VND flood prevention and control dike project along the Da River

Minh Nguyễn |

Phu Tho - The urgent project of flood prevention and control of Pheo - Che flooded area, in Ky Son ward with a total investment of nearly 600 billion VND is at risk of being behind schedule.

Urgent request to handle the damaged flood dike incident in Quang Tri

HƯNG THƠ |

Quang Tri - After being affected by storm No. 6, the Ben Hai left dike was directly affected by flooding, causing many locations on the dike to be severely damaged and eroded.

Xuyên đêm đắp đê chống lũ ở Bắc Giang

Trần Tuấn |

Bắc Giang - Đêm 8.9, lực lượng chức năng tích cực phối hợp đắp đê chống tràn, bảo vệ sản xuất của nhân dân xã Vũ Xá (Lục Nam).