According to reporters' records, 16km of component project 1 of the Bien Hoa - Vung Tau expressway is being urgently constructed by contractors to put the project into operation in May 2026. Currently, many sections have been paved with asphalt, and median strips and guardrails are being installed... so far, the construction volume has reached over 75%.
At the starting point of component project 1 of the Bien Hoa - Vung Tau expressway, intersecting with Vo Nguyen Giap street, Phuoc Tan ward, Dong Nai province, asphalt has been paved and construction is being completed.
Component project 1 of the Bien Hoa - Vung Tau expressway, about 16km long, is being increased by contractors, organizing continuous construction to compensate for slow volume, striving to complete the project on schedule and ensure quality.
The Bien Hoa - Vung Tau expressway project is a key project with a length of more than 53km and divided into 3 component projects. In which, the section through Dong Nai province is about 34km long (including component projects 1 and 2) and the section through Ho Chi Minh City (component project 3) is about 19.5km long.
The Dong Nai Provincial Construction Investment Project Management Board said that, according to the direction, component project 1 of the Bien Hoa - Vung Tau expressway will be inaugurated in May 2026.
When completed and put into operation, the project will contribute to completing the transportation network of the Southern region, creating more favorable connection conditions between Dong Nai and Ho Chi Minh City, and also play an important role in effectively supporting the operation of Long Thanh airport in the coming time.
For component projects 2 and 3 of the Bien Hoa - Vung Tau expressway, functional agencies are coordinating to complete procedures to conduct acceptance and put the main route into operation.
Some images of the appearance of component project 1 of the Bien Hoa - Vung Tau expressway being urgently constructed: