Strange appearance when the Bang Giang River rises

Tân Văn |

Cao Bang - The city's dam is in the testing phase, but the changes from the project are being positively welcomed by the people.

According to the reporter's actual records, starting from the afternoon of April 29, all 3 flat valve gates of the Cao Bang city dam system have been closed, causing the water level from Bang Giang bridge to the foot of Hoang Nga bridge to rise significantly.

Raising water levels makes boating activities on the river more convenient, while creating conditions for organizing experimental art programs on the river, bringing people a new space for entertainment and sightseeing.

Dap dang nuoc trong qua trinh dang thu nghiem. Anh: Tan Van
Water dam during the trial offering process. Photo: Tan Van

According to the plan, there will be about 2-3 small boats per day to bring artists to perform Then singing and musical instruments right on the river.

This is the first time this traditional art form has been performed on water in Cao Bang, creating a new and attractive experience for local people as well as tourists.

Mr. Nong Dinh Quang (residing in Trung Khanh district) shared: "Today, I took my wife and children to the city to play during a big holiday, and happened to experience taking a boat to listen to the Then singing on the river, everyone was very excited, especially the children".

Sau khi nuoc duoc dang, hoat dong hat Then - dan Tinh tren song duoc trien khai. Anh: Son Viet
After the water was raised, Then singing - Tinh lute on the river was implemented. Photo: Son Viet

In a conversation with reporters, Mr. Quang expressed his agreement with the policy of building a dam to raise water, saying that this project has contributed to significantly changing the appearance of the central area of Cao Bang city.

Although the project is still in the process of completion, the initial results have shown many positive signals. People hope that in the coming time, the provincial leaders will have further investment steps to help activities on the Bang Giang River become more organized and effective.

Hoat dong hat Then - dan Tinh tren song thu hut dong dao nguoi dan don xem. Anh: Son Viet
Then singing and Tinh lute activities on the river attract a large number of people to watch. Photo: Son Viet

Previously, in May 2023, the People's Council of Cao Bang province passed Resolution No. 20, approving the investment policy for the Cao Bang city dam construction project, with a total investment of 150 billion VND.

The objective of the project is to offer and stabilize the Bang river water level (also known as Bang Giang River), create urban landscapes for the downtown area, while serving the needs of exploiting surface water for daily life and production in riverside areas.

After completion, the dam will create a spacious water surface, contributing to climate regulation, improving the ecological environment, and developing services and tourism on the river and on both banks.

This project also helps reduce the river water level fluctuation range, stabilize river banks, reduce flow rate and limit landslides.

Khan gia o nhieu do tuoi cung hao huc don xem cac tiet muc nghe thuat. Anh: Son Viet
The audience of all ages eagerly welcomed the performance. Photo: Son Viet
The new look of the Bang Giang River.

The flat valve will regulate the water level during the dry season and return the flood drainage aperture to the natural river level, ensuring the ability to drain floodwater during the rainy season.

Along with the construction of the dam system, the Bang Giang riverbed is also being actively dredged and cleared to beautify the landscape, ensuring good traffic flow, ready for water raising when the dam comes into official operation.

Tân Văn
TIN LIÊN QUAN

Installing valve doors, preparing to test Cao Bang dam

|

Cao Bang - The dam project in the border city is about to be completed.

The water recedes at the construction site of the hundred-billion-dong dam in the border area

|

Cao Bang - According to the plan, the dam project in the city only has 7 days to complete.

The hundred-billion-dong dam in the border area will be completed on April 30

|

Cao Bang - The City People's Committee is aiming to complete the dam project in the city by April 30, 2025.

Minister of Public Security explains the Law on transferring people serving prison sentences

|

Minister of Public Security Luong Tam Quang has explained many important regulations on transferring people serving prison sentences.

Ho Chi Minh City Police inform about driving license testing and new points to note

|

HCMC - In the past 3 months, HCMC Police have received more than 300,000 pending driving license applications, applying a set of 600 test questions.

The headquarters of the agency in Phu Quy island district simultaneously changed its name to Phu Quy Special Zone

|

Binh Thuan - Many names at agencies on Phu Quy island have been changed from district to Phu Quy Special Zone and changed the name of the province to Lam Dong.

Installing valve doors, preparing to test Cao Bang dam

Tân Văn |

Cao Bang - The dam project in the border city is about to be completed.

The water recedes at the construction site of the hundred-billion-dong dam in the border area

TÂN VĂN |

Cao Bang - According to the plan, the dam project in the city only has 7 days to complete.

The hundred-billion-dong dam in the border area will be completed on April 30

Tân Văn |

Cao Bang - The City People's Committee is aiming to complete the dam project in the city by April 30, 2025.