New look at 35m wide Hung Vuong street in Phu Tho

Tô Công |

Phu Tho - Hung Vuong road section connecting National Highway 2 in Phong Chau ward, after many months of construction, renovation and upgrading, now has a new look.

As the main road connecting National Highway 2 with the center of Phu Tho town in the past, Hung Vuong road is more than 8km long, passing through Au Co ward, Phu Tho ward and Phong Chau ward.

The Hung Vuong road section from Phu Tho ward through Phu Ha industrial park to the intersection with provincial road 320 (Phong Chau ward) - more than 4km long - has been invested and upgraded by Phu Tho town to be spacious and modern.

Đoạn đường Hùng Vương đoạn qua địa bàn phường Phú Thọ. Ảnh: Tô Công
Hung Vuong street section passing through Phu Tho ward. Photo: To Cong

The roadbed width is 35m (people often call it road 35), in which the above-mentioned section has been asphalted, sidewalks paved, trees planted, and lighting systems installed.

The remaining section of nearly 1km long from National Highway 2 to the intersection with provincial road 320, belonging to Phong Chau ward, with the road surface still being cement concrete, has been old and degraded for many years.

From October 14, 2024, the old Phu Tho Town People's Committee approved the investment policy for the project to upgrade and renovate Hung Vuong road section from provincial road 320B to National Highway 2.

Một bên đường đã được thảm nhựa. Ảnh: Tô Công
One side of the road has been asphalted. Photo: To Cong

After the two-level local government model went into operation, the project was transferred to Phong Chau Ward People's Committee for implementation. The total investment of the project is more than 47 billion VND.

By the end of 2025, Package No. 07: Construction and installation of the project has completed the contractor selection and started construction to date (winning bid price of nearly 41 billion VND).

According to reporters of Lao Dong Newspaper in the last days of July 2026, after more than half a year of construction, the project has completed many items, bringing a new look to this main road.

Những lớp bê tông nhựa sẽ thay thế cho mặt đường bê tông xi măng đã xuống cấp. Ảnh: Tô Công
Asphalt concrete layers will replace the degraded cement concrete road surface. Photo: To Cong

It can be seen that the drainage system has been renovated, the sidewalks have been paved with bricks, trees have been planted, and the lighting system has also been installed... In particular, the section of the route is being asphalted.

Mr. Vu Dinh Thinh - a resident of Phong Chau ward shared: "The road section after being renovated and upgraded with road surface and sidewalk will be as beautiful as the section from Phu Ha industrial park to the town center before, the urban face will become more and more spacious and modern".

Cây xanh đã được trồng, đèn chiếu sáng đã được lắp đặt. Ảnh: Tô Công
Trees have been planted, lights have been installed. Photo: To Cong

According to the design, the project will construct a road length of 997.15m according to the road level, which is the main road of the area, along with a drainage system and other auxiliary works. The road section has a roadbed width of 35m, a road surface of 21m, a median strip of 3m, and a sidewalk width of 3.3m on each side.

Talking to Lao Dong Newspaper reporters on the morning of July 25, Mr. Thieu Quang Cong - Director of Phong Chau Ward Project Management Board said that with the completed volume up to now, the project is being constructed ahead of schedule ( deadline ends in 2026).

Nhà thầu sẽ sớm hoàn thành công tác thảm bê tông nhựa mặt đường. Ảnh: Tô Công
The contractor will soon complete the asphalt concrete pavement work. Photo: To Cong

After completing the sidewalk, green trees, and lighting, the contractor is continuing to complete the asphalt concrete pavement of the road surface, and then will construct the traffic safety system (traffic signs, painted road markings)" - Mr. Cong shared.

Previously, during the process of Phong Chau ward propagating and mobilizing site clearance to implement the project, households proactively dismantled violating works on the sidewalk corridor, handed over the site early to the construction contractor, contributing to accelerating the project progress.

Tô Công
RELATED NEWS

Completion of extended inter-regional road connecting near Phong Chau bridge in Phu Tho

|

Phu Tho - The extended inter-regional road connecting National Highway 32 near Phong Chau bridge, after more than 1 year of construction, has now completed construction items.

Continuously handling the situation of encroachment on traffic corridors in Phu Tho

|

Phu Tho - The inspection and handling of the situation of illegal construction and expansion of works within the traffic corridor in Cam Khe commune is carried out throughout.

13.8ha land along Hung Vuong street in Phu Tho will be auctioned

|

Phu Tho - Urban housing area on both sides of Hung Vuong street in Phu Tho and Phong Chau wards with an area of nearly 13.8ha will be auctioned.

China evacuates more than 20,000 people before Typhoon Noul makes landfall

|

China evacuated more than 20,000 people and temporarily suspended railway operations in the south as Typhoon Noul made landfall.

Vietnam speaks out about being imposed a new 12.5% tariff by the US

|

It is requested that the US fully assess the measures Vietnam has implemented to adjust the tax rates applied to Vietnamese goods.

Temporary domino effect of diamond brands in Ho Chi Minh City

|

Many diamond business brands in Ho Chi Minh City have continuously announced temporary suspension of operations, restructuring or stopping exchange transactions.

Deploying the search and repatriation of martyrs' remains in Minh Duc commune, Dong Nai city

|

Dong Nai - General Phan Van Giang, Member of the Politburo, Deputy Prime Minister, Minister of National Defense attends the ceremony to deploy the search and repatriation of martyrs' remains.

Completion of extended inter-regional road connecting near Phong Chau bridge in Phu Tho

Tô Công |

Phu Tho - The extended inter-regional road connecting National Highway 32 near Phong Chau bridge, after more than 1 year of construction, has now completed construction items.

Continuously handling the situation of encroachment on traffic corridors in Phu Tho

Tô Công |

Phu Tho - The inspection and handling of the situation of illegal construction and expansion of works within the traffic corridor in Cam Khe commune is carried out throughout.

13.8ha land along Hung Vuong street in Phu Tho will be auctioned

Tô Công |

Phu Tho - Urban housing area on both sides of Hung Vuong street in Phu Tho and Phong Chau wards with an area of nearly 13.8ha will be auctioned.