541 billion VND project in Hue entangled with 44 households

PHÚC ĐẠT |

After more than 3 months of construction, the Ba Trieu road upgrade project is still behind schedule because dozens of households have not handed over the site.

The project to upgrade and expand Ba Trieu street - one of the key traffic routes in the center of Hue City - has resumed construction after a period of stagnation. However, the overall progress has not yet met expectations.

According to the latest report of the Project Management Board for Construction Investment Area 1 sent to Hue City People's Committee, the biggest reason for the project delay is that there are still 44 cases that have not completed site handover, disrupting the entire construction line.

The project to upgrade and expand Ba Trieu street has a total investment of more than 541 billion VND, of which compensation, support, and resettlement costs alone account for more than 466 billion VND. The upgraded road is about 923m long, expanded to a cross-section of 26m...

The Project Management Board said that the entire project has 185 affected households, including 92 households in Thuan Hoa ward and 93 households in Vy Da ward. To date, most compensation dossiers have been prepared and approved. However, there are still 44 cases that have not handed over land.

In which, in Thuan Hoa ward, there are still 35 households that have not handed over the site, and in Vy Da ward, there are still 9 households. The fact that the site is not continuous prevents the contractor from deploying it simultaneously on the entire route but must construct in short sections of about 200-300m to both ensure traffic and limit the impact on the business activities of people on both sides of the road.

According to the report, after more than three months of construction since April 7, 2026, the value of the completed volume only reached about 16.73% of the contract value.

The Project Management Board said that for locations with clean ground, the progress basically meets the plan. However, the overall progress of the entire project still depends greatly on site clearance work.

During the construction process, the construction unit also encountered many conflicts with existing technical infrastructure systems such as electricity, water supply, and telecommunications. Some locations experienced cable breaks and pipe bursts, causing the project to be temporarily suspended to coordinate with the management unit for handling, continuing to affect the progress.

The contractor is currently mobilizing 4 excavators and about 20 workers per day, and at the same time simultaneously deploying items of undergrounding electricity, installing communication systems, curbs, paving sidewalks and expanding roadbeds in the handed-over sections.

According to the plan, the sidewalk item will be completed in the third quarter of 2026, and the asphalt concrete pavement will be completed before December 30, 2026. The Project Management Board will coordinate with localities to remove obstacles in site clearance and strengthen the mobilization of households that have not complied. If the site is still not handed over, the unit will advise the Hue City People's Committee to enforce land recovery according to regulations.

PHÚC ĐẠT
RELATED NEWS

Adjusting capital for the Coastal Road and Nhat Le 3 bridge project

|

Quang Tri - Quang Tri Provincial People's Council approves Resolution approving the adjustment of investment policy for the coastal road and Nhat Le 3 bridge project.

Lao Cai awards investment policy for 24 projects, total registered capital of more than 24,160 billion VND

|

Lao Cai - The Investment Promotion Conference marks a new beginning for the province after the merger, with the award of investment policy approval decisions for 24 economic projects.

Quang Ngai Provincial People's Council focuses on removing bottlenecks in public investment and key projects

|

Quang Ngai - The 5th session of the 14th Provincial People's Council spends a lot of time removing difficulties in public investment, key projects...

After organizing the civil servant exam, Cao Bang Department of Education and Training received instructions to reduce 596 staff positions

|

Cao Bang - The Department of Education and Training has a document requesting to temporarily suspend the recruitment of public employees in the Education sector due to a reduction of nearly 600 staff positions.

People's Artist Trung Anh: I used to play extras for a long time, wanting to quit the profession

|

In the program "Saturday Afternoon Coffee", People's Artist Trung Anh shared about his time with the Vietnam Drama Theater.

Verifying information that preschool children in Ho Chi Minh City were allowed to sleep in front of the toilet door

|

Ho Chi Minh City - Tam Binh Ward People's Committee is verifying parents' complaints about children being bedridden by teachers in front of the toilet door.

Forecast of heavy rain in the area from tonight, with very heavy rain in some places over 250mm

|

From the night of July 18 to the night of July 19, it is forecast that the mountainous and midland areas of the Northern region will have moderate rain, heavy rain and thunderstorms, with locally very heavy rain over 250mm.

Adjusting capital for the Coastal Road and Nhat Le 3 bridge project

NGUYỄN LUÂN |

Quang Tri - Quang Tri Provincial People's Council approves Resolution approving the adjustment of investment policy for the coastal road and Nhat Le 3 bridge project.

Lao Cai awards investment policy for 24 projects, total registered capital of more than 24,160 billion VND

Bảo Nguyên |

Lao Cai - The Investment Promotion Conference marks a new beginning for the province after the merger, with the award of investment policy approval decisions for 24 economic projects.

Quang Ngai Provincial People's Council focuses on removing bottlenecks in public investment and key projects

ĐÔNG GIANG |

Quang Ngai - The 5th session of the 14th Provincial People's Council spends a lot of time removing difficulties in public investment, key projects...