The 546 billion VND project in Lao Cai is supplemented with 93 billion VND

Tô Công |

Lao Cai - The Road project connecting National Highway 32 with Noi Bai - Lao Cai Expressway (IC15) continues to be adjusted, adding VND93 billion to the total investment.

Adding 93 billion VND

The project of the road connecting National Highway 32 with Noi Bai - Lao Cai Expressway (IC15) was approved by the People's Committee of Yen Bai province (old) under Decision No. 3447/QD-UBND dated December 31, 2020 with a total investment of 420 billion VND.

On May 29, 2024, after being approved by the People's Committee of Yen Bai province for adjustment and supplementation, the total investment of the project was increased to nearly 547 billion VND (Decision No. 1013/QD-UBND).

By May 26, 2025, the project was further approved by the People's Committee of Yen Bai province to adjust and supplement VND93 billion (Decision No. 1104/QD-UBND), raising the total investment to nearly VND640 billion.

In the adjusted and supplemented value this time (93 billion VND), the cost of compensation, support, and resettlement is 1 billion VND; the construction cost is nearly 88 billion VND; the cost of construction investment consulting is more than 3.1 billion VND; the rest is project management costs, other costs, and contingency costs.

Of the total investment (nearly 640 billion VND), the cost of compensation, support, and resettlement is 64 billion VND; the construction cost is nearly 527 billion VND; the construction investment consulting cost is nearly 22 billion VND; the rest is project management costs, other costs, and contingency costs.

According to the investigation of Lao Dong Newspaper reporters at the National Bidding Network System, the Lao Cai Province No. 1 Construction Investment Project Management Board (currently the project investor) has just announced to invite bids for an additional construction package (including the above adjusted and additional value of VND93 billion).

That is Package No. 27: Construction of the road connecting National Highway 32 with the Noi Bai - Lao Cai Expressway (IC15) - Category: Handling locations affected by landslides on positive and negative slopes, damage to road surfaces, and vertical ditches caused by rain and storms.

Package No. 27 was widely bid online, priced at nearly 79 billion VND (estimated price of more than 83.3 billion VND) from the central budget, local budget and other legal capital sources. The implementation period of this package is 180 days.

Tren tuyen nhieu taluy am, taluy duong. Anh: Tran Bui.
The route has many negative and positive slopes. Photo: Tran Bui.

Adjusted and supplemented construction scale

In the coming time, after the results of the approval of contractor selection approved by the investor, on the basis of the route being invested in construction, the construction unit will carry out additional and handling of locations affected by landslides on positive and negative slopes, locations damaged by road surfaces, vertical ditches, traffic safety systems and other damages on the entire route caused by rain and storms.

According to the project documents, there are up to 19 landslides on the route, the construction unit will take measures to handle the situation, temporarily to ensure traffic in front with a hop-off solution, combined with placing stone baskets to ensure traffic safety.

At the same time, they will continue to monitor landslides during construction and during exploitation and use to have stable and long-term design solutions.

Regarding the project, the project was initiated on January 9, 2022, the construction units include: Yen Bai Traffic Construction Joint Stock Company, Nam Phong Construction and Trading Investment Joint Stock Company; Tay Bac Infrastructure Investment and Development Joint Stock Company; Dong Tien Company Limited and a number of other units.

According to the design, the route is of a grade IV mountainous scale with a total length of 43.5km, connecting from the western districts to the eastern part of Yen Bai (old).

The project has a starting point at the intersection with National Highway 32 in Gia Hoi Commune, Van Chan District (now Gia Hoi Commune, Lao Cai Province) and an end point at the intersection with Provincial Road 166 in Dong An Commune, Van Yen District (now Dong Cuong Commune, Lao Cai Province).

The goal of this project is to upgrade infrastructure, gradually complete the transportation system of the two old districts of Yen Bai province, formerly Van Yen district and Van Chan district, create conditions for people to travel and trade goods, improve the material and spiritual life of people in the project area, promote socio-economic development and ensure security and national defense of the locality and the region.

Tô Công
TIN LIÊN QUAN

The Ministry of Home Affairs proposes to add leadership positions at the commune level, especially the Secretary and Chairman of the People's Committee

|

The Ministry of Home Affairs urgently recommends arranging enough staff at the commune level, adding to the missing leadership positions, especially the Secretary and Chairman of the People's Committee at the commune level.

Da Nang is supplemented with 500 billion VND to upgrade National Highway 14D

|

Da Nang This is an additional capital from the Central Government, helping to accelerate the project to upgrade National Highway 14D, creating effective connections between Da Nang and the Central Highlands.

Liquidity explodes, stocks hit a historic peak after 25 years

|

The VN-Index set the highest score in the trading history of the stock market with a record liquidity of nearly 2 billion USD.

Electric vehicle charging stations flourish in Ho Chi Minh City

|

HCMC - The shortage of legitimate charging infrastructure has caused many households, cafes, and parking lots in HCMC to set up charging stations for electric vehicles.

Mass shooting in the Thai capital, many casualties

|

A mass shooting incident occurred in the capital Bangkok, Thailand, causing many casualties.

Lecturer owed money by school for a decade: Chairman of Quang Ngai Provincial People's Committee directs inspection

|

Quang Ngai - After Lao Dong Newspaper's reflection on lecturers being owed overtime teaching fees, wages... on July 28, the Chairman of the Provincial People's Committee - directed departments to urgently inspect.

96 years of the brilliant mark of the working class and the Vietnam Trade Union

|

After 96 years of construction and development, with 13 National Trade Union Congresses, the Vietnam Trade Union has become an important political and social force, closely associated with workers, accompanying the nation in each historical period.

The Ministry of Home Affairs proposes to add leadership positions at the commune level, especially the Secretary and Chairman of the People's Committee

HƯƠNG NHA |

The Ministry of Home Affairs urgently recommends arranging enough staff at the commune level, adding to the missing leadership positions, especially the Secretary and Chairman of the People's Committee at the commune level.

Da Nang is supplemented with 500 billion VND to upgrade National Highway 14D

Hoàng Bin |

Da Nang This is an additional capital from the Central Government, helping to accelerate the project to upgrade National Highway 14D, creating effective connections between Da Nang and the Central Highlands.

Trả hồ sơ, điều tra bổ sung vụ lừa khách về Đồng Nai mua dự án ma, chiếm đoạt hơn 255 tỉ đồng

MINH CHÂU |

Đồng Nai - Ngày 23.7, TAND tỉnh trả hồ sơ vụ án để điều tra bổ sung đối với vụ lừa khách từ TPHCM về mua dự án ma", chiếm đoạt số tiền hơn 255 tỉ đồng.