The project to renovate the longest canal in Ho Chi Minh City needs an additional 830 billion VND

MINH QUÂN |

The Tham Luong - Ben Cat - Nuoc Len canal renovation project, the longest canal in Ho Chi Minh City, needs an additional VND830 billion in capital due to the addition of some items.

The report on the decision to adjust the investment policy for the project to build infrastructure and improve the environment of Tham Luong - Ben Cat - Nuoc Len canal was submitted by the Ho Chi Minh City People's Committee to the Ho Chi Minh City People's Council at the 19th session this morning (November 14).

The total initial investment capital of the project is 8,200 billion VND, of which 4,000 billion VND comes from the central budget and the rest comes from the Ho Chi Minh City budget.

Ho Chi Minh City People's Committee proposed to adjust the total investment to more than VND9,030 billion (an increase of about VND830 billion).

Explaining this, the HCMC People's Committee said that the project needs an additional VND205 billion for site clearance and technical infrastructure relocation. Most of this cost will be spent on relocating 7 high-voltage power poles, upgrading 2 500kV power lines according to standards and re-establishing construction items in the Go Cat landfill area.

In addition, construction costs also increased by VND 917 billion due to the need to add essential infrastructure works such as: Traffic roads in the area of ​​the Vam Thuat and Nuoc Len tidal control sluice project; construction of a water intake system for fire prevention and fighting; installation of 39 new tidal gates for existing sluices, along with temporary bridges serving people's traffic at Da Han canal, Hong Ky sluice, etc.

In contrast, some other expenses and provisions were adjusted down by more than VND292 billion.

The Ho Chi Minh City People's Committee also proposed extending the project implementation period from 2021 to 2026, instead of ending in 2025 as originally planned.

Doan kenh qua quan Go Vap (TPHCM) da thi cong ke be tong. Anh: Minh Quan
The canal section through Go Vap district (HCMC) has been constructed with concrete embankments. Photo: Minh Quan

With a length of 32.7 km, Tham Luong - Ben Cat - Nuoc Len canal flows through 7 districts, including: District 12, Binh Tan, Tan Phu, Tan Binh, Go Vap, Binh Thanh and Binh Chanh district.

The project to renovate this canal started in February 2023, with items such as building concrete embankments on both banks, dredging the canal bed, building 8-12 m wide roads along both sides, installing drainage, lighting, and tree systems, along with 19 drainage culverts, 12 boat docks, and 3 connecting bridges.

Ho Chi Minh City has planned to complete the project by April 30, 2025.

However, according to a recent report by the Ho Chi Minh City Urban Infrastructure Construction Investment Project Management Board (investor), construction progress has only reached 37.9% after nearly two years of implementation.

In 2024, the project was assigned a disbursement capital of VND 3,400 billion, but the investor is expected to be able to disburse only VND 1,028 billion, equivalent to 30.23% of the plan.

Currently, the project is facing difficulties such as lack of dumping site for soil and mud from the canal dredging process, 21 cases of re-encroachment of land, etc.

MINH QUÂN
TIN LIÊN QUAN

The project to renovate the longest canal in Ho Chi Minh City is messy, people are miserable

|

The Tham Luong - Ben Cat - Rach Nuoc Len canal renovation project, the longest canal in Ho Chi Minh City, is causing outrage because of prolonged and delayed construction.

Renovation of the longest canal in Ho Chi Minh City faces obstacles, risk of delay

|

The Tham Luong - Ben Cat - Rach Nuoc Len canal renovation project, the longest canal in Ho Chi Minh City, has only completed 37.9% of its volume after nearly two years of implementation.

Ho Chi Minh City requests review of Cambridge International certificates

|

Ho Chi Minh City People's Committee requires units to inspect and review officials who have declared the use of foreign language certificates named "Cambridge International".

SPT Company must pay nearly 500 million VND after tax inspection

|

Thanh Hoa Provincial Tax Department has requested SPT Architecture Joint Stock Company to pay nearly 500 million VND due to incorrect tax declaration.

Tens of thousands of people flock to watch the Ngo boat racing festival in Soc Trang

|

Mekong Delta - From November 14-15, 60 boat teams from provinces and cities in the Mekong Delta will compete in the Ngo Boat Race with fierce and exciting matches.

My Boss Expressed His Love Even Though He Knew I Was Getting Married (Part 1)

|

Hour 9 - The female employee is expressed her feelings by her manager when she is about to get married. What will this girl decide?

8pm News: Merging many wards in 6 central districts of Hanoi

|

News at 8pm on November 14: Hanoi merged many wards in 6 central districts; Arrested and took statements from singer Chi Dan, model An Tay...

Construction is in full swing at the two blocks of the Bac Lieu Three-Conical Hat Theater

|

Bac Lieu - The construction unit is working overtime to open the interior exhibition project of the provincial museum in December 2024.

The project to renovate the longest canal in Ho Chi Minh City is messy, people are miserable

MINH QUÂN |

The Tham Luong - Ben Cat - Rach Nuoc Len canal renovation project, the longest canal in Ho Chi Minh City, is causing outrage because of prolonged and delayed construction.

Renovation of the longest canal in Ho Chi Minh City faces obstacles, risk of delay

MINH QUÂN |

The Tham Luong - Ben Cat - Rach Nuoc Len canal renovation project, the longest canal in Ho Chi Minh City, has only completed 37.9% of its volume after nearly two years of implementation.

Tuyến kênh dài nhất TPHCM đã lộ hình hài sau hơn 1 năm khởi công cải tạo

Anh Tú |

TPHCM - Sau hơn một năm kể từ ngày khởi công, dự án cải tạo kênh Tham Lương – Bến Cát – rạch Nước Lên (đi qua địa bàn 7 quận, huyện của thành phố là Quận 12, Bình Tân, Tân Phú, Tân Bình, Gò Vấp, Bình Thạnh và huyện Bình Chánh) đã đạt hơn 37% khối lượng. Hiện tiến độ thi công đang được đẩy nhanh để hoàn thành vào dịp 30.4.2025.