Bac Ninh Provincial Inspectorate pointed out many shortcomings in the project implemented by Cat Loi Urban Development Investment Joint Stock Company.

Bac Ninh Provincial Inspectorate has just issued Notice No. 268/TB-TTT. NV9 Notice of Inspection Conclusion on the compliance with policies and laws on auction, investment, land, environment, construction, real estate business in the process of implementation for the project: Investment and construction of Housing Area in Chau Khe ward, Tu Son town (now Phu Khe ward, Bac Ninh province).

This is a project invested by Chau Khe Ward People's Committee (now Phu Khe Ward, Bac Ninh province); Cat Loi Urban Development Investment Joint Stock Company (Cat Loi Company) is the unit that won the auction for land use rights and construction investment.

Accordingly, the state allocates land with land use fees in the form of land use right auctions to invest in building residential areas. The total area of the land area is 66,484.3m2, of which the residential land area auctioned for land use rights is 23,194.3m2 (173 lots). Land use right winning bid price: 98,812,000 VND.

Notably, regarding the implementation of construction investment, the Inspectorate of Bac Ninh province pointed out:

The item of undergrounding the 35kV power line from pole 4 to pole 8 of the 35kV branch N.THCK1 road 372 E27. 3 passing through the project land area is not included in the construction content approved by the Chairman of Bac Ninh Provincial People's Committee. The construction, consulting and acceptance testing value of the undergrounding part of the 35kV power line is 3,167,578,834 VND.

The investor did not perform some tasks (Cost of preparing bidding documents, evaluating bid documents, cost of appraising contractor selection for project management consulting packages, design consulting, construction) with a total value of 1,2039,550,000 VND.

Construction contracts do not have contract negotiation minutes.

The investor did not perform the work of selecting construction insurance contractors, did not purchase construction insurance when implementing the project according to the provisions of Article 9 of the 2014 Construction Law. Construction insurance costs approved in the estimate are: 50,306,000 VND.

Regarding construction progress management: By the time of inspection, the project had expired its implementation period (2020-2021), the investor had not completed construction, had not submitted to competent authorities for inspection of the acceptance of completion of construction items and construction works, and had not handed over the works.

The investor, Phu Khe Ward People's Committee (formerly Chau Khe) has not seriously implemented the management of construction order and land management: 26 construction works violated construction order and some construction works were not in accordance with the detailed plan of the project.

Notably, Cat Loi Company prepared a dossier, requesting the Department of Natural Resources and Environment to notify about the eligibility for transferring land use rights when the entire technical infrastructure has not been completed.

ĐÌNH TRƯỜNG
RELATED NEWS

Thanh Hoa will inspect 22 social housing projects, resolutely recover apartments bought to the wrong people

|

Thanh Hoa - The province will inspect 22 social housing projects, resolutely recover apartments bought to the wrong people, used for the wrong purposes.

Inspections are not only aimed at handling violations but also at early detection of risks and preventing loopholes

|

Representatives of the Government Inspectorate have just exchanged views on the issue of institutional building and strengthening real estate market confidence.

Inspection of financial management and personnel at Hue Department of Construction

|

Hue City Inspectorate announces two inspection decisions of the Department of Construction and the Sub-Department of Construction Inspection on finance, public assets and personnel work.

Ho Chi Minh City proposes raising the ceiling income for social housing purchases to 60 million VND/month

|

Ho Chi Minh City - Households with three or more dependents may be applied a social housing purchase income threshold of up to 60 million VND/month.

From listening to action, Thanh Hoa Trade Union contributes to promoting double-digit growth

|

Thanh Hoa - From listening and caring to improving skills, Thanh Hoa Trade Union is unleashing the strength of union members, contributing to promoting double-digit growth.

5 victims died in restaurant fire in Ho Chi Minh City

|

On July 27, Cho Ray Hospital in Ho Chi Minh City said that 5 victims in the restaurant fire that occurred on July 11 died due to extremely severe burns.

"I am 95 years old, and my husband is still forever the most beautiful youth on the battlefield"

|

Although the war has receded, many families of martyrs are still diligently on their journey to find their loved ones - those who have spent their whole youth on the fierce battlefield.

Thanh Hoa will inspect 22 social housing projects, resolutely recover apartments bought to the wrong people

Trần Lâm |

Thanh Hoa - The province will inspect 22 social housing projects, resolutely recover apartments bought to the wrong people, used for the wrong purposes.

Inspections are not only aimed at handling violations but also at early detection of risks and preventing loopholes

TRÍ MINH |

Representatives of the Government Inspectorate have just exchanged views on the issue of institutional building and strengthening real estate market confidence.

Inspection of financial management and personnel at Hue Department of Construction

PHÚC ĐẠT |

Hue City Inspectorate announces two inspection decisions of the Department of Construction and the Sub-Department of Construction Inspection on finance, public assets and personnel work.