The nearly 500 billion VND connecting road project is still stuck with site clearance after 3 years of construction

Lam Thanh - Nguyễn Tùng |

Tuyen Quang - The project connects My Lam mineral stream to National Highway 2D, connecting to Tuyen Quang - Phu Tho expressway with the goal of expanding the urban area, promoting tourism development.

The road project from My Lam Mineral Spring Tourist Area to National Highway 2D, connecting to Tuyen Quang - Phu Tho Expressway, is 8.8km long, with a total investment of 487 billion VND. The project is divided into 2 packages, started in 2022 and is expected to be completed in 2025.

According to the reporter's records, some locations in the project have been basically completed, vehicles can circulate. Meanwhile, some areas are continuing to undergo construction.

Mot so vi tri gap kho khan trong qua trinh thi cong. Anh: Lam Thanh
Some locations encountered difficulties during the construction process. Photo: Lam Thanh

It is known that the land area recovered for the project is 37.63ha of 378 households. To date, 36.5 hectares of 360 households have been cleared, with compensation paid nearly VND91 billion, reaching 98.6%.

Currently, there are 5 households that have not received compensation; 7 households have received money but have not yet handed over the site; 11 households have not yet had a decision to reclaim land; 12 households subject to resettlement have not been allocated land.

In My Lam ward alone, the total area of land recovered to serve the project is up to 20.42 hectares of 206 households. Currently, 19.9 hectares have been reclaimed, reaching 97%. However, some households that have received resettlement have not relocated due to problems in procedures for granting land use right certificates.

These problems make it difficult to synchronously construct items.

Cac may moc, phuong tien duoc huy dong de trien khai du an. Anh: Lam Thanh
Machinery and vehicles are mobilized to implement the project. Photo: Lam Thanh

According to Mr. Le Thanh Cong - Commander of Package No. 08 (Hiep Phu Company Limited), the unit is in charge of the construction of the section from Km0 to Km1+900. From March 2024, the unit was handed over a part of the site but it was not complete, so it was impossible to mobilize machinery and human resources for simultaneous construction.

Currently, only about 50% of the contract value has been achieved. The unit's 1.9km long road is still stuck for about 500m, passing through the area of 8 households that have not yet handed over the site. The contractor hopes to soon remove obstacles and hand over clean land to speed up progress.

Mr. Ngo Viet Anh - Vice Chairman of My Lam Ward People's Committee - said that the locality is coordinating with relevant agencies to propagate, urgently complete the procedures for land allocation for resettlement and issue land use right certificates to households.

Mot so doan tuyen duong noi da co ban hoan thanh. Anh: Lam Thanh
Some sections of the connecting road have been basically completed. Photo: Lam Thanh

Households that have received compensation but have not yet moved due to procedures, the ward will support the completion of documents. In case of violation, there will be a plan to organize construction protection or comply with land recovery according to regulations.

According to Deputy Director of the Provincial Traffic Construction Investment Project Management Board Bui Cong Phuong, in response to problems in site clearance, the board has established working groups. At the same time, officers were sent directly to each household to discuss timely handling and removal measures, especially at "bottlenecks" affecting construction.

Lam Thanh - Nguyễn Tùng
RELATED NEWS

Prosecution of 2 more defendants in the case at the Bach Mai Hospital project, Viet Duc facility 2

|

Major General Nguyen Quoc Toan said that the Ministry of Public Security has prosecuted 2 additional defendants in the case that occurred at the second facility of Bach Mai and Viet Duc Hospitals.

Dien Bien speeds up the progress of road maintenance projects

|

Dien Bien - Department of Construction requires contractors to focus maximum resources to complete road maintenance projects in parallel with ensuring quality.

Dak Lak breaks through development with a series of projects attracting thousands of billions of VND in investment

|

Dak Lak is making a strong breakthrough with billion-dollar projects, attracting large FDI capital, becoming an attractive destination for investors.

Hanoi flooded through the lens of an Australian filmmaker

|

An Australian tourist recorded footage of the spirit of Hanoians when facing storms.

Nearly 400 earthquakes, more than 170 casualties after 6.9 earthquake in the Philippines

|

Hundreds of aftershocks shook after the 6.9 earthquake in the Philippines, causing heavy damage to people and property.

Order to close the bottom spillway of Tuyen Quang hydroelectric reservoir, 3 provinces and cities must ensure safety

|

The bottom spillway of Tuyen Quang hydroelectric reservoir was ordered to close at 11am this afternoon.

List of flooded spots in Hanoi on the morning of October 1

|

Hanoi - As of this morning, the inner city area still has more than 20 flooded spots causing traffic difficulties such as in Vo Chi Cong, Thang Long Avenue, Duong Dinh Nghe...

No tax-free shopping center of 35,000m2 in Da Nang

|

Da Nang - VV Mall Shopping Center ( Vo Nguyen Giap Street, Da Nang City) has recently closed, with few buyers.

Prosecution of 2 more defendants in the case at the Bach Mai Hospital project, Viet Duc facility 2

Vương Trần |

Major General Nguyen Quoc Toan said that the Ministry of Public Security has prosecuted 2 additional defendants in the case that occurred at the second facility of Bach Mai and Viet Duc Hospitals.

Dien Bien speeds up the progress of road maintenance projects

Quang Đạt |

Dien Bien - Department of Construction requires contractors to focus maximum resources to complete road maintenance projects in parallel with ensuring quality.

Dak Lak breaks through development with a series of projects attracting thousands of billions of VND in investment

MINH ANH |

Dak Lak is making a strong breakthrough with billion-dollar projects, attracting large FDI capital, becoming an attractive destination for investors.