Ring Road 4 parallel road project: Many bidding packages are about to be completed

SÓNG HỮU |

Hanoi - The bidding packages for the Ring Road 4 parallel road project are ensuring the set progress, including one bidding package that will be completed in March.

The Ring Road 4 project in the Capital region section passing through Hanoi is about 58km long, passing through 17 communes and wards.

To implement the Ring Road 4 project, Hanoi city must recover 800.15 hectares of land and relocate 9,039 graves.

Up to now, wards and communes have completed the construction of 13/13 resettlement areas, completed land acquisition, site clearance, moved graves, and moved underground and aboveground works to ensure progress.

a
Package No. 8 of the parallel road of Hanoi Ring Road 4 has been asphalted. Photo: Song Huu

Component project 2.1 - construction of the parallel road of Ring Road 4 has 4 bidding packages with 11 contractors participating in construction.

Talking to Lao Dong on February 9, Mr. Do Ngoc Sam - Commander of package No. 8, Truong Son Construction Corporation (Ministry of National Defense) said that the construction volume of package No. 8 has reached about 95% to date.

At the end of 2025, the contractor received the remaining land area from the local authorities. These locations are being constructed by the contractor for the crushed stone grade item.

The lighting system has been installed on the route. The asphalt pavement item is about to be completed. The intersection with National Highway 23B and the North-South railway overpass on the Hanoi - Lao Cai line will be asphalted after the Lunar New Year.

It is expected that the contractor will complete all items in March 2026" - Mr. Sam said.

a
Intersection of 100 Me Linh road and Ring Road 4. Photo: Song Huu
a
Construction area of Ring Road 4 and 100 Me Linh road intersection. Photo: Song Huu
a
The volume of package No. 8 has now reached about 95%. Photo: Song Huu

At package No. 9, constructed by Vietnam Import-Export and Construction Corporation - Vinaconex, the current progress is about 85%.

With a length of more than 20km, this is the largest bidding package for the parallel road of Ring Road 4 in the Capital region section passing through Hanoi.

Mr. Nguyen Hoang Hai - Commander of package No. 9 said that the package progress is still being ensured according to the set plan. The contractor is committed to completing the package in June 2026 according to the direction of Hanoi city.

In the next one or two days, workers will proceed to clean up the construction site, close entrances and exits to the project at intersections to ensure traffic safety during the Lunar New Year holiday. It is expected that around the 7th day of the Lunar New Year, engineers and workers will return to the construction site to work, completing the remaining items of the project" - Mr. Hai said.

a
Construction site of package No. 9 is undertaken by Vinaconex contractor. Photo: Song Huu
a
Machinery working at the project construction site. Photo: Song Huu
a
Many sections have been asphalted. Photo: Song Huu

Similarly, package No. 10 and package No. 11 are also being deployed simultaneously by contractors with many construction fronts, ensuring progress according to the plan.

For component project 3 - investing in the construction of the expressway according to the public-private partnership (PPP) method, investors are focusing on organizing the construction of key items, including Hong Ha, Me So, Hoai Thuong bridges and overpass sections on the route.

According to the Hanoi Transport Construction Investment Project Management Board, investors are focusing resources, striving to accelerate construction progress, complete the main route before the APEC 2027 Conference, and closely follow the direction of the Government and the Project Steering Committee.

SÓNG HỮU
RELATED NEWS

Hanoi cordons off corrugated iron, enforces land recovery for Hong Ha bridge - Ring Road 4 project

|

Hanoi - For cases of delay and non-compliance with site allocation for Ring Road 4 project, the government has issued a decision to enforce land recovery.

Hanoi enforces a series of households delaying the handover of Ring Road 4 land

|

Hanoi - A series of households were forced to recover land because they refused to hand over land to implement Ring Road 4.

Bridge on Ring Road 4 receives sufficient land, construction throughout the New Year

|

Hanoi - Leaving the New Year holiday, many engineers and workers stick to the construction site, accelerating the progress of Hong Ha bridge belonging to the Ring Road 4 project in the Capital region.

Deputy Prime Minister Nguyen Van Thang becomes Chairman of the Executive Council of the International Financial Center

|

Deputy Prime Minister Nguyen Van Thang was assigned to be the Chairman of the Executive Council of the International Financial Center in Vietnam.

From July 9-10, Hanoi Police will ban and temporarily suspend vehicles on many roads

|

Hanoi - City police temporarily ban and restrict vehicles on many roads to serve the "Peaceful Fatherland" Gala.

Dam breach in Guangxi, flood warning raised to the highest level

|

Torrential rain for many consecutive days caused a dam to break at a reservoir, forcing the Guangxi government, China, to immediately raise the emergency response level.

Launching a contest to learn about major resolutions of the Party, Fatherland Front and Trade Union

|

On the afternoon of July 6, the Party Committee of the Vietnam General Confederation of Labour organized the Launching Ceremony of the online contest "Understanding the Resolution of the 14th National Congress of the Party, Resolution of the 1st Congress of the Party Committee of the Vietnam Fatherland Front, Central Agencies, Resolution of the 14th Congress of the Vietnam Trade Union, term 2026-2031".

Hanoi cordons off corrugated iron, enforces land recovery for Hong Ha bridge - Ring Road 4 project

Anh Tuấn |

Hanoi - For cases of delay and non-compliance with site allocation for Ring Road 4 project, the government has issued a decision to enforce land recovery.

Hanoi enforces a series of households delaying the handover of Ring Road 4 land

Anh Tuấn |

Hanoi - A series of households were forced to recover land because they refused to hand over land to implement Ring Road 4.

Bridge on Ring Road 4 receives sufficient land, construction throughout the New Year

SÓNG HỮU |

Hanoi - Leaving the New Year holiday, many engineers and workers stick to the construction site, accelerating the progress of Hong Ha bridge belonging to the Ring Road 4 project in the Capital region.