The billion-dollar traffic project in Da Nang is at risk of being behind schedule

Nguyễn Hoàng |

Da Nang - Component project 1 to complete coastal road 129, with an investment of 1,100 billion VND, is facing the risk of not being able to finish in 2025.

Lack of fill, land clearance problems

Two major bottlenecks lack of roadbed and slow site clearance could cause the progress of the Coastal Road 129 completion project to be extended to 2026, although the project has been extended once until the end of 2025.

The project includes two component projects: (1) completing coastal road 129 ( Vo Chi Cong street); (2) the route connecting Vo Chi Cong street to Dong Que Son Industrial Park, connecting National Highway 14H and National Highway 1. The total investment is more than VND 2,056 billion, of which component project 1 accounts for VND 1,100 billion, component project 2 accounts for more than VND 956.7 billion.

Hien trang duong Vo Chi Cong, Da Nang doan qua cau Tam Tien. Anh: Quan Ho
Current status of Vo Chi Cong Street, Da Nang section across Tam Tien Bridge. Photo: Quan Ho

Component 1 of route DT619, starting from the National Highway 40B intersection (old Tam Ky City) to the DT620 intersection (old Nui Thanh District), connecting the road to Chu Lai Airport, with a total length of about 26.5km.

To date, localities have handed over 22.5km of land (reaching 84.9%). The value of the construction volume reached 540.9/914.109 billion VND (59.17%).

The biggest bottleneck at present is slow land acquisition and a long loading and unloading cycle. According to engineer Le Van Tin, Deputy Commander of Package 2 - there are still more than 3km of site that have not been handed over, mainly the section through Tam Anh and Nui Thanh communes. The sections for treating weak soil that have just been handed over since February 2025 have been forced to be reloaded, waiting for subsidence for up to 565 days (about 19 months).

The section from km14+000 through Tam Anh has not yet completed the site clearance, and has to be relocated for 595 days. "It is impossible to complete the contract by December 2025," said Mr. Tin.

Expected completion time to be postponed to 2026

Mr. Nguyen Van Thuong - Director of the Quang Nam Traffic Construction Investment Project Management Board - said that the goal is still to open to traffic by the end of 2025, but some items are definitely extended to 2026 due to two sections, a total of 2.6km, having to wait for 565 days to sink.

More worryingly, there are still 4km that have not been handed over: the 1.12km section through Tam Xuan is stuck with agricultural land, public land and one household is allowed to clear houses and land; the 2.17km section through Tam Anh is stuck with 169 plots (6 households are allowed to clear houses and land); the 0.76km section through Nui Thanh commune is stuck with 54 plots (26 households are allowed to clear houses and land). There are cases of white clearance that have not been considered for resettlement; there are still 28 5% of land plots that have not been processed.

Cac don vi day nhanh tien do thi cong trong du gap kho khan ve mat bang, nguyen lieu dat
Units speed up the project's construction progress, in difficult conditions regarding site clearance and filling materials. Photo: Nguyen Hoang

To remove obstacles, the investor recommended that the Da Nang City Land Fund Development Center direct the Branch of Area 11 to coordinate in providing land records, so that the People's Committees of communes can meet the conditions for compensation for 166 plots that have been discussed for origin. With 170 plots with specific and qualified land prices - of which 136 plots are listing plans - it is recommended to shorten the appraisal and approval time for payment; urgently establish and list plans for the remaining 34 plots. Localities where projects are being implemented actively mobilize people to agree and urgently hand over construction sites.

Duong ven bien Vo Chi Cong da hoan thien thong xe doan tu Hoi An vao Tam Ky,
The Vo Chi Cong coastal road has completed the opening of the section from Hoi An to Tam Ky, one of the routes with the most beautiful and spacious infrastructure in the old Quang Nam. Photo: Nguyen Hoang

Regarding the problem of shortage of materials and fill soil in Nui Thanh, which forces contractors to buy from Quang Ngai, the volume is limited, directly affecting progress. Currently, some mines in the area have completed the auction steps, the winning bidder has submitted documents to determine reserves and explore... The investor recommended that the City People's Committee soon complete procedures and grant exploitation licenses to meet the demand for fill, promote construction and disbursement.

Nguyễn Hoàng
RELATED NEWS

Da Nang youth bring Mid-Autumn Festival to the village, keeping the joy of children in the highlands

|

Da Nang - These days, Xo Dang children in remote villages are celebrating the Mid-Autumn Festival enthusiastically and fully for the first time, along with volunteer groups from the lowlands.

Update of Da Nang City land price list in 2025 after merger

|

Lao Dong Newspaper compiles the land price list for urban areas in Da Nang city after the merger in 2025, the highest being 340 million VND/m2.

2 areas in Ho Chi Minh City propose to establish low emission zones to limit gasoline and oil vehicles from 2026

|

Ho Chi Minh City is studying the establishment of a low-emission zone in the central area and Can Gio to limit the operation of gasoline and oil vehicles that do not meet emission standards from 2026.

Hundreds of thousands of people line up to buy tickets for the G-Dragon concert taking place at Vinhomes Ocean Park 3

|

On the first day of ticket sales, the G-DRAGON 2025 WORLD TOUR [Übermensch] concert attracted hundreds of thousands of people online waiting to buy tickets.

Principal apologizes to parents and students after the 25,000 VND meal that caused a stir

|

Quang Tri - When the image of a 25,000 VND meal at Ba Don Primary School No. 1 spread, the school's principal sent an apology letter to parents and students.

Fans queue for more than 3 hours to buy tickets to watch Vietnam play Nepal

|

Many fans lined up for more than 3 hours waiting to buy tickets to watch the Vietnam team face Nepal at Binh Duong Stadium (Thu Dau Mot Ward, Ho Chi Minh City).

People suffer to go to work, make their own boats to move in the sea after heavy rain

|

After heavy rain, many roads turned into rivers, making the journey to work difficult for people.

Plot to bomb US Embassy in Venezuela

|

Venezuela warns of the plot of extremist elements to bomb the US Embassy in Caracas.

Da Nang youth bring Mid-Autumn Festival to the village, keeping the joy of children in the highlands

Nguyễn Hoàng - Thiện Trang |

Da Nang - These days, Xo Dang children in remote villages are celebrating the Mid-Autumn Festival enthusiastically and fully for the first time, along with volunteer groups from the lowlands.

Đà Nẵng phê duyệt hơn 1.600 tỉ đồng đầu tư tuyến đường kết nối

Thu Giang |

Đà Nẵng - UBND TP ban hành Quyết định phê duyệt dự án tuyến đường kết nối đường Vành đai phía Tây đến cao tốc La Sơn - Túy Loan, mức đầu tư hơn 1.600 tỉ đồng.

Update of Da Nang City land price list in 2025 after merger

Thanh Bình |

Lao Dong Newspaper compiles the land price list for urban areas in Da Nang city after the merger in 2025, the highest being 340 million VND/m2.