The 470 billion VND oil depot project is behind schedule in Quang Tri

HƯNG THƠ |

Quang Tri - The Vietnam-Laos Petroleum Depot Project is 3 years behind schedule compared to the project implementation schedule in the first investment policy decision.

On January 6, the Quang Tri Provincial Economic Zone Management Board confirmed that it had requested the Quang Tri Provincial People's Committee to consider adjusting the progress of the Vietnam-Laos Petroleum Depot project.

The above project is invested by Vietnam-Laos Petroleum Investment Joint Stock Company, and was granted an investment policy decision by the People's Committee of Quang Tri province in March 2019. The project has a total investment capital of 470 billion VND, a land area of ​​16.9 hectares, and a total warehouse capacity of 200,000 m3.

Up to now, only the project's phase 1 leveling work of 4.4 hectares on shore has been completed; the breakwater construction is currently being organized, reaching 40% of the project volume; the embankment is being cast, reaching 50% of the project volume.

According to the proposed schedule, this project is 3 years behind schedule in completing and putting the first phase into operation compared to the project implementation schedule in the first investment policy decision (1.2021 to complete and put the first phase into operation) and 6 months behind schedule in the first investment policy adjustment approval decision (7.2024 to complete and put the first phase into operation).

The reasons for the project's delay are said to be due to problems that have prolonged site clearance; the impact of the COVID-19 pandemic; there is no road to transport materials and equipment to the project area; and the fire prevention and fighting approval procedure has lasted from November 2020 to November 2023 to be completed.

In addition, due to the consulting unit's explanation and completion of the fire prevention and fighting appraisal dossier not being guaranteed and not being timely; the Company's proposed investment policy (project implementation scope) was missing compared to the planning dossier, not ensuring the conditions for leasing land to build items such as embankments, oil import and export ports, so the project scope had to be adjusted (increasing the area from 16.93ha to 17.93ha); the investor was not really determined and drastic in speeding up the progress of the project implementation in phase 1.

Currently, the investor has a commitment to the project implementation progress with a detailed implementation plan for each construction item. In particular, the commitment is to complete and put phase 1 of the project into operation in July 2026. If the phase 1 construction items are not completed by the above time, no further progress adjustment will be requested but the investment project will be terminated.

"The biggest difficulties and obstacles have been resolved, and recently the investor has made efforts to implement the project. To facilitate the investor to implement the project and have a basis to continue construction, we have requested the Provincial People's Committee to consider adjusting the project implementation progress according to regulations" - said the leader of the Quang Tri Economic Zone Management Board.

HƯNG THƠ
TIN LIÊN QUAN

Many hydropower and wind power projects in Quang Tri are behind schedule

|

Quang Tri - The specialized agency proposed that the People's Committee of Quang Tri province require wind and hydropower projects that are behind schedule to deposit funds to ensure investment.

Stuck in forest land, series of hydropower plants in Kon Tum are behind schedule

|

Kon Tum - The power grid system is not secure and forest land is involved, making it impossible for 12 medium and small hydropower projects in Kon Tum to generate electricity.

Nghe An urges slow-progressing and wasteful projects

|

Nghe An - The province requires speeding up progress and putting slow-progressing cultural, health and educational projects into use soon to avoid waste.

Tickets for Thong Nhat train run out on April 30, train-loving holiday

|

Towards the 50th anniversary of the Liberation of the South and National Reunification Day, train trips to Ho Chi Minh City are popular during the 30.4-1.5. holiday.

Literature and art accompany the nation in the process of transformation

|

Over the past half century, Vietnamese literature and art have accompanied the nation in its transformation, creating a voice, strength and prediction for development.

People's Artist Ta Minh Tam, Phuong My Chi and more than 1,000 performing artists at the April 30 celebration

|

The special art program with the theme "Rang Dong Tuong Viet Nam" has the participation of more than 1,000 artists and actors such as Phuong My Chi, Ta Minh Tam...

Russia reminds the nuclear red lines, warns the West

|

Russia's revised nuclear doctrine has detailed the conditions under which the country can use nuclear weapons and which anyone can read.

Xuan Son may receive a large signing bonus from the contract with Nam Dinh team

|

Striker Xuan Son can receive about 36 billion VND in signings (excluding salary) at Nam Dinh club, based on a new contract with a term of 6 years.

Many hydropower and wind power projects in Quang Tri are behind schedule

HƯNG THƠ |

Quang Tri - The specialized agency proposed that the People's Committee of Quang Tri province require wind and hydropower projects that are behind schedule to deposit funds to ensure investment.

Stuck in forest land, series of hydropower plants in Kon Tum are behind schedule

THANH TUẤN |

Kon Tum - The power grid system is not secure and forest land is involved, making it impossible for 12 medium and small hydropower projects in Kon Tum to generate electricity.

Nghe An urges slow-progressing and wasteful projects

QUANG ĐẠI |

Nghe An - The province requires speeding up progress and putting slow-progressing cultural, health and educational projects into use soon to avoid waste.