The 470 billion VND oil depot project is behind schedule in Quang Tri

HƯNG THƠ |

Quang Tri - The Vietnam-Laos Petroleum Depot Project is 3 years behind schedule compared to the project implementation schedule in the first investment policy decision.

On January 6, the Quang Tri Provincial Economic Zone Management Board confirmed that it had requested the Quang Tri Provincial People's Committee to consider adjusting the progress of the Vietnam-Laos Petroleum Depot project.

The above project is invested by Vietnam-Laos Petroleum Investment Joint Stock Company, and was granted an investment policy decision by the People's Committee of Quang Tri province in March 2019. The project has a total investment capital of 470 billion VND, a land area of ​​16.9 hectares, and a total warehouse capacity of 200,000 m3.

Up to now, only the project's phase 1 leveling work of 4.4 hectares on shore has been completed; the breakwater construction is currently being organized, reaching 40% of the project volume; the embankment is being cast, reaching 50% of the project volume.

According to the proposed schedule, this project is 3 years behind schedule in completing and putting the first phase into operation compared to the project implementation schedule in the first investment policy decision (1.2021 to complete and put the first phase into operation) and 6 months behind schedule in the first investment policy adjustment approval decision (7.2024 to complete and put the first phase into operation).

The reasons for the project's delay are said to be due to problems that have prolonged site clearance; the impact of the COVID-19 pandemic; there is no road to transport materials and equipment to the project area; and the fire prevention and fighting approval procedure has lasted from November 2020 to November 2023 to be completed.

In addition, due to the consulting unit's explanation and completion of the fire prevention and fighting appraisal dossier not being guaranteed and not being timely; the Company's proposed investment policy (project implementation scope) was missing compared to the planning dossier, not ensuring the conditions for leasing land to build items such as embankments, oil import and export ports, so the project scope had to be adjusted (increasing the area from 16.93ha to 17.93ha); the investor was not really determined and drastic in speeding up the progress of the project implementation in phase 1.

Currently, the investor has a commitment to the project implementation progress with a detailed implementation plan for each construction item. In particular, the commitment is to complete and put phase 1 of the project into operation in July 2026. If the phase 1 construction items are not completed by the above time, no further progress adjustment will be requested but the investment project will be terminated.

"The biggest difficulties and obstacles have been resolved, and recently the investor has made efforts to implement the project. To facilitate the investor to implement the project and have a basis to continue construction, we have requested the Provincial People's Committee to consider adjusting the project implementation progress according to regulations" - said the leader of the Quang Tri Economic Zone Management Board.

HƯNG THƠ
TIN LIÊN QUAN

Many hydropower and wind power projects in Quang Tri are behind schedule

|

Quang Tri - The specialized agency proposed that the People's Committee of Quang Tri province require wind and hydropower projects that are behind schedule to deposit funds to ensure investment.

Stuck in forest land, series of hydropower plants in Kon Tum are behind schedule

|

Kon Tum - The power grid system is not secure and forest land is involved, making it impossible for 12 medium and small hydropower projects in Kon Tum to generate electricity.

Nghe An urges slow-progressing and wasteful projects

|

Nghe An - The province requires speeding up progress and putting slow-progressing cultural, health and educational projects into use soon to avoid waste.

Former swimmer Anh Vien is happy with her life after retirement

|

Former swimmer Nguyen Thi Anh Vien shared that she feels very happy with her current life as she continues to write her dream of swimming.

EU gives Ukraine billions of euros in frozen Russian assets

|

Using the interest from frozen Russian assets, the EU disbursed the first 3 billion euros to Ukraine from the G7 loan package.

Who is the actor who replaced People's Artist Cong Ly to play Bac Dau in Tao Quan?

|

In some Tao Quan seasons, the role of Bac Dau, once associated with People's Artist Cong Ly, was transferred.

Two hundred billion VND traffic projects change the face of Yen Bai

|

Yen Bai - The project connecting Nguyen Tat Thanh Street with Au Co Street and the IC 13 intersection project of Noi Bai - Lao Cai Expressway are about to be completed and are being awaited by the people.

China is about to build the Three Gorges Dam in space

|

China is working to build the Three Gorges Dam in space for solar power generation.

Many hydropower and wind power projects in Quang Tri are behind schedule

HƯNG THƠ |

Quang Tri - The specialized agency proposed that the People's Committee of Quang Tri province require wind and hydropower projects that are behind schedule to deposit funds to ensure investment.

Stuck in forest land, series of hydropower plants in Kon Tum are behind schedule

THANH TUẤN |

Kon Tum - The power grid system is not secure and forest land is involved, making it impossible for 12 medium and small hydropower projects in Kon Tum to generate electricity.

Nghe An urges slow-progressing and wasteful projects

QUANG ĐẠI |

Nghe An - The province requires speeding up progress and putting slow-progressing cultural, health and educational projects into use soon to avoid waste.