The project to expand the gateway to Ho Chi Minh City is stuck with 146 premises in Binh Duong

MINH QUÂN |

HCMC - The project to expand Hanoi Highway and National Highway 1 (from Tram 2 intersection to Tan Van) has been unfinished for many years due to 146 land issues in Binh Duong province.

The project to expand Hanoi Highway and National Highway 1 has a total length of 15.7 km, from Saigon Bridge to Tan Van intersection, and was started on April 2, 2010 under the BOT (build - operate - transfer) form.

The project is divided into 3 sections, with an expanded scale of 12-16 lanes: Section 1, from Saigon Bridge to Binh Thai intersection, is 6.2km long, 153m wide; Section 2, from Binh Thai to Tram 2 intersection, is 5.3km long, 113m wide; Section 3, from Tram 2 intersection to Tan Van, is 4.2km long, 113m wide.

According to the original plan, the project would be completed within 36 months from the handover of the site. However, up to now, sections 1 and 2 have been basically completed, while section 3 is still unfinished.

In Binh Duong province, the site clearance project is managed by the Ho Chi Minh City Traffic Construction Investment Project Management Board (Traffic Board).

The total number of affected households is 201, with an area of about 17 hectares. To date, 201 households have been inventoried, but only 55 households (about 5.5ha) have been compensated, the remaining 146 households (11.5ha) have not been resolved.

Du an qua ben xe Mien Dong moi van dang do do vuong mat bang phia tinh Binh Duong. Anh: Anh Tu
The project through the new Mien Dong bus station is still unfinished due to land clearance problems in Binh Duong province. Photo: Anh Tu

The Department of Natural Resources and Environment of Ho Chi Minh City said that on January 24, 2017, the People's Committee of Binh Duong province issued Decision No. 174/QD-UBND on approving the land compensation unit price for the remaining area of the project. The price of residential land is 20.19 million VND/m2, the price of agricultural land is 8.038 million VND/m2.

Regarding compensation costs for 146/201 remaining cases of phase 2, the Di An Town Land Fund Development Center issued document No. 445/TTPTQD dated October 15, 2019, estimated at about VND 3,079 billion, the expected compensation land price in 2020 for residential land is VND 42 million/m2, for agricultural land is VND 16.7 million/m2.

Meanwhile, the land price for the compensation plan to collect people's opinions for District 9 (now Thu Duc City, Ho Chi Minh City), Hanoi Highway is about 50 million VND/m2, for agricultural land with a coefficient of 14, equivalent to about 5.2 million VND/m2 (the unit price of agricultural land is about 10% of the unit price of residential land).

The Department of Natural Resources and Environment of Ho Chi Minh City said that there are main differences in agricultural land unit prices between the two localities.

According to the report of Binh Duong province, the land recovered for the project is mostly residential land (which can be converted to residential land), so the high unit price is appropriate compared to the residential land price to calculate compensation in the project (agricultural land price is about 25% of the residential land unit price).

The increase in land prices in Binh Duong has forced Ho Chi Minh City to balance to be able to clear the land and continue implementing the Hanoi Highway expansion project.

However, according to the Department of Natural Resources and Environment of Ho Chi Minh City, the determination of current land prices is based on market transaction information, so there is no mechanism to control land price increases but is regulated by the market.

Du an dang do, tao “nut that co chai” anh huong den di lai cua nguoi dan. Anh: Minh Quan
The project is unfinished, creating a "bottleneck" affecting people's travel. Photo: Minh Quan

In order to remove difficulties, the Ho Chi Minh City Department of Transport has recently proposed that the Ho Chi Minh City People's Committee assign the Ho Chi Minh City Traffic Department to proactively coordinate with relevant units to report to the Ho Chi Minh City People's Committee on difficulties and propose solutions to completely handle the issue of compensation and site clearance in Binh Duong.

At the same time, the Department of Natural Resources and Environment was assigned to preside over the work with CII Company - the project implementation unit, to review and propose solutions to the problem. The Department of Natural Resources and Environment needs to prepare working content between the leaders of the Ho Chi Minh City People's Committee and the Binh Duong Provincial People's Committee to completely resolve the compensation and site clearance work for the project.

MINH QUÂN
TIN LIÊN QUAN

Building a bridge at the billion-dollar intersection to relieve traffic jams in the East of Ho Chi Minh City

|

HCMC - In phase 3 of the My Thuy intersection project, an overpass will be built on Ring Road 2 (right branch) and Ky Ha 3 bridge (right branch) to relieve traffic jams in the East of HCMC.

The billion-dollar intersection in the East of Ho Chi Minh City is expected to be completed in 2026

|

HCMC - After 9 years of construction, the My Thuy intersection project - a project expected to "rescue" traffic congestion in the East of HCMC continues to start construction in phase 3.

The Eastern Artery Road of Ho Chi Minh City has not been expanded for 15 years

|

HCMC - After 15 years of implementation, the project to expand Hanoi Highway and National Highway 1 - the eastern gateway route of HCMC is still unfinished due to land clearance problems for 176 households.

Foreign companies queue back to Russia

|

Multi-national companies lined up to re-enter the Russian market amid the ongoing negotiations on a ceasefire in Ukraine.

A series of dams in Dak Nong have run out of water during the dry season

|

Dak Nong - Up to this point, there are about 13 lakes and dams in the province that have run out of water; about 30 other lakes and dams have less than 30% of their capacity.

Thousands of cadres and teachers in disadvantaged communes are owed allowances

|

Quang Tri - Thousands of commune-level cadres, civil servants and educational institutions in Cam Lo district have not received full regional allowances.

The famous actor of the movie The Voice of the crow in the bushes of thorns passed away

|

Actor Richard Chamberlain, famous for his role as Cha Ralph in the drama "The Voice of the crow in the dust of thorns" passed away at the age of 90.

The story of the multi-heritage - Savior couple of Hai Phong villagers

|

Hai Phong - For local people, the two banyan trees in Don Rieng Temple (Duong Kinh, Hai Phong) are like a "savior", helping villagers overcome the big storm in 1955.

Building a bridge at the billion-dollar intersection to relieve traffic jams in the East of Ho Chi Minh City

Minh Tâm - Anh Tú |

HCMC - In phase 3 of the My Thuy intersection project, an overpass will be built on Ring Road 2 (right branch) and Ky Ha 3 bridge (right branch) to relieve traffic jams in the East of HCMC.

The billion-dollar intersection in the East of Ho Chi Minh City is expected to be completed in 2026

Tâm Tú |

HCMC - After 9 years of construction, the My Thuy intersection project - a project expected to "rescue" traffic congestion in the East of HCMC continues to start construction in phase 3.

The Eastern Artery Road of Ho Chi Minh City has not been expanded for 15 years

MINH QUÂN |

HCMC - After 15 years of implementation, the project to expand Hanoi Highway and National Highway 1 - the eastern gateway route of HCMC is still unfinished due to land clearance problems for 176 households.