The Eastern Artery Road of Ho Chi Minh City has not been expanded for 15 years

MINH QUÂN |

HCMC - After 15 years of implementation, the project to expand Hanoi Highway and National Highway 1 - the eastern gateway route of HCMC is still unfinished due to land clearance problems for 176 households.

The project to expand Hanoi Highway and National Highway 1 has a total length of 15.7 km, from Saigon Bridge to Tan Van intersection, and was started on April 2, 2010 under the BOT (build - operate - transfer) form.

The project is divided into 3 sections, with an expanded scale of 12-16 lanes: Section 1, from Saigon Bridge to Binh Thai intersection, is 6.2km long, 153m wide; Section 2, from Binh Thai to Tram 2 intersection, is 5.3km long, 113m wide; Section 3, from Tram 2 intersection to Tan Van, is 4.2km long, 113m wide.

According to the original plan, the project would be completed within 36 months from the handover of the site. However, up to now, sections 1 and 2 have been basically completed, while section 3 is still unfinished.

Quoc lo 1 (tu ben xe Mien Dong moi den nut giao Tan Van) chua mo rong xong, tao nut that co chai. Anh: Anh Tu
National Highway 1 (from the new Mien Dong bus station to Tan Van intersection) has not been expanded, creating a bottleneck. Photo: Anh Tu

The Ho Chi Minh City Department of Transport said that section 3 from the Tram 2 intersection to Tan Van has reached more than 91% of the workload, but many locations cannot be constructed due to not yet cleared.

In Thu Duc City, the right parallel road is still stuck with 28 households in Tan Phu ward (about 4,150m2) and 1 household in Phuoc Long A ward (800m2).

Ham chui nut giao Tram 2 tren Xa lo Ha Noi (TPHCM) dang do vi vuong 28 mat bang. Anh: Minh Quan
The underpass at the Tram 2 intersection on Hanoi Highway (HCMC) is unfinished due to 28 land clearance problems. Photo: Minh Quan

Meanwhile, the left parallel road is still stuck with a household with an area of about 260m2 at the branch to An Suong intersection.

In Binh Duong province, the site clearance project is managed by the Ho Chi Minh City Traffic Construction Investment Project Management Board (Traffic Board).

The total number of affected households is 201, with an area of about 17 hectares. To date, 201 households have been inventoried, but only 55 households (about 5.5ha) have been compensated, the remaining 146 households (11.5ha) have not been resolved.

The main reason is the difference in compensation prices between Ho Chi Minh City and Binh Duong, causing the project's progress to stagnate.

Du an con vuong mat bang
The section through the new Mien Dong bus station is still stuck with the land of 146 households in Binh Duong province. Photo: Anh Tu
Du an dang do, tao “nut that co chai” anh huong den di lai cua nguoi dan. Anh: Minh Quan
The project is unfinished, creating a "bottleneck" affecting people's travel. Photo: Minh Quan

In order to remove difficulties, the Ho Chi Minh City Department of Transport has just proposed that the Ho Chi Minh City People's Committee direct the Department of Finance to promptly complete the project adjustment assessment to submit to the Ho Chi Minh City People's Committee as a basis for implementing the next steps.

Thu Duc City People's Committee speeds up the progress of resolving remaining problems, handing over vacant premises to investors.

The Ho Chi Minh City Traffic Department proactively coordinates with relevant units to report to the Ho Chi Minh City People's Committee on difficulties and propose solutions to completely handle the issue of compensation and site clearance in Binh Duong.

The Department of Natural Resources and Environment will preside over working with CII Company - the project implementation unit, to review and propose solutions to resolve the problem. At the same time, the department needs to prepare working content between the leaders of the Ho Chi Minh City People's Committee and the Binh Duong Provincial People's Committee to completely resolve the compensation and site clearance work for the project.

The BOT project to expand Hanoi Highway and National Highway 1 was approved by the Ho Chi Minh City People's Committee in 2009 with a total investment of VND 2,516 billion. By 2016, adjusted investment costs increased to more than VND 4,900 billion.

Since April 2021, Hanoi Highway BOT has officially collected tolls, with an expected period of 17 years and 9 months.

This is a vital route at the eastern gateway of Ho Chi Minh City, not only directly connecting with Binh Duong and Dong Nai but also located parallel to Metro Line No. 1 (Ben Thanh - Suoi Tien).

MINH QUÂN
TIN LIÊN QUAN

The VND3,600 billion intersection in Ho Chi Minh City is stalled due to 186 land congestion

|

HCMC - The My Thuy intersection project with a total capital of more than VND3,600 billion continues to be stalled because Thu Duc City has not yet handed over 186 sites, greatly affecting the construction progress.

8 years have passed since the construction of the underpass at the eastern gateway of Ho Chi Minh City was completed

|

HCMC - Construction began in 2016 on the underpass at Station 2 intersection on Hanoi Highway, from HCMC to Dong Nai, but has yet to be completed due to land acquisition issues.

HCMC completes and starts construction of a series of large projects in 2025

|

Ho Chi Minh City completes An Phu intersection, Tran Quoc Hoan - Cong Hoa connecting road, Tham Luong canal and starts construction of Saigon River pedestrian bridge, Ring Road 2, Nguyen Khoi bridge...

Ho Chi Minh City and Hanoi have the highest divorce rates in the country

|

According to statistics, the whole country has about 2,225,000 divorces/devorces, of which Ho Chi Minh City and Hanoi account for the highest rate.

VTV Binh Dien Long An won the opening match of Hoa Lu Cup

|

On the afternoon of March 4, VTV Binh Dien Long An won 3-1 against Long Son Thanh Hoa Cement in the opening match of the Hoa Lu Cup 2025 volleyball tournament.

Traffic in Thai Nguyen is invested in to help connect better

|

Thai Nguyen - The road connecting Phu Binh district and Pho Yen city with a total investment of 736 billion VND is about to be completed, helping traffic connect better.

In 2025, serving at least 1/3 of the sentence will be considered for amnesty

|

According to the Deputy Minister of Public Security, to be considered for amnesty in 2025, a prison sentence must be served at least 1/3 of the time in cases of limited prison sentences.

Germany, EU and Russia respond to Nord Stream 2 reopening news

|

Germany, the European Union (EU) and Russia have all responded to the news that the Nord Stream 2 pipeline is likely to reopen.

The VND3,600 billion intersection in Ho Chi Minh City is stalled due to 186 land congestion

MINH QUÂN |

HCMC - The My Thuy intersection project with a total capital of more than VND3,600 billion continues to be stalled because Thu Duc City has not yet handed over 186 sites, greatly affecting the construction progress.

8 years have passed since the construction of the underpass at the eastern gateway of Ho Chi Minh City was completed

MINH QUÂN |

HCMC - Construction began in 2016 on the underpass at Station 2 intersection on Hanoi Highway, from HCMC to Dong Nai, but has yet to be completed due to land acquisition issues.

Chủ đầu tư BOT Xa lộ Hà Nội nói về việc đóng đường dưới cầu Rạch Chiếc

MINH QUÂN |

TPHCMChủ đầu tư BOT Xa lộ Hà Nội cho biết, việc đóng đường dưới cầu Rạch Chiếc là để trả lại mặt bằng theo quy hoạch chứ không nhằm mục đích tận thu.