The 10,000 billion VND tidal prevention project is about to be re-constructed, Ho Chi Minh City expects to reduce flooding

MINH QUÂN |

HCMC - After 5 years of stagnation, the nearly VND10,000 billion flood prevention super project is about to be restarted, expected to be completed soon to contribute to reducing flooding in the city.

The project to solve flooding caused by tides in the Ho Chi Minh City area taking into account climate change factors (phase 1) started in 2016 under the BT (build - transfer) form, with a total investment of nearly 10,000 billion VND.

The goal is to control flooding caused by high tides for an area of about 570 km2, with about 6.5 million people on the right bank of the Saigon River and the center of Ho Chi Minh City.

Duong Tran Xuan Soan la mot trong tong 7 tuyen duong bi ngap do trieu cuong chua duoc giai quyet. Anh: Minh Quan
Tran Xuan Soan Street is one of a total of 7 roads flooded due to high tides that have not been resolved. Photo: Minh Quan

As of the temporary suspension in November 2020, the project has reached more than 90% of the construction volume. However, problems with land fund payment, capital allocation and completion of legal procedures forced the project to temporarily suspend construction.

According to Trung Nam Construction Investment Joint Stock Company - the project investor, the prolonged stagnation has caused arising costs to increase sharply, in which the loan interest alone is up to more than 1.7 billion VND per day. If calculated according to the expected completion schedule by the end of 2025, the total investment of the project has increased to more than VND 14,000 billion.

A representative of Trung Nam Company affirmed that when all current problems are resolved, the investor can restart construction immediately upon completing the mobilization of materials and human resources, with a time limit for completing the entire project within 9 months.

Recently, the Government issued Resolution 212/NQ-CP on removing difficulties and obstacles for the project.

According to the Resolution, the Ho Chi Minh City People's Committee is allowed to adjust the project's Feasibility Study Report and implement payment options using land funds to remove capital obstacles.

Ho Chi Minh City will use three land plots to pay investors, including: Land plot of Lot C8A - Area A - New Urban Area of Nam Thanh City (large 5,500 m2, old District 7); land plot 762 Binh Quoi (large 4,298 m2, old Binh Thanh District); land plot 232 Do Xuan Hop (large over 17,500 m2, old Thu Duc City).

In case the value of the land fund is lower than the value of the project (after eliminating unreasonable costs), the difference will be paid with public investment capital managed by Ho Chi Minh City.

In addition, the Government also assigned the State Audit to conduct a project audit to serve as a basis for settling construction investment capital, ensuring the harmony of interests between the State and investors, avoiding waste, and putting the project into operation soon.

Cong ngan trieu Muong Chuoi sau thoi gian dai khong thi cong. Anh: Anh Tu
Muong Chuoi tidal sluice after a long period of no construction. Photo: Anh Tu

To prepare for the reconstruction, Ho Chi Minh City has recently added VND1,800 billion in public investment capital in 2025 to the tidal barrier project.

At the same time, Ho Chi Minh City has directed departments and branches to urgently complete legal procedures related to payment land funds.

The Ho Chi Minh City Department of Finance is assigned to preside over and coordinate with relevant units to study and propose investment policies for land plots, and quickly implement the adjustment of contracts with investors. In particular, selecting a consulting unit to review the dossier to adjust the feasibility study report, advise the entire project working group, negotiate and sign the BT contract appendix, as well as specific payment options.

The Ho Chi Minh City Urban Infrastructure Construction Investment Project Management Board is assigned to check the value of the completed volume, as a basis for submitting a recommendation for the audit of the completed value.

Regarding operation after completion, the Ho Chi Minh City People's Committee assigned the Department of Construction to preside over and coordinate with the Department of Agriculture and Environment and related units to develop a handover plan, determine the unit receiving the operation and technical standards for the construction system.

MINH QUÂN
TIN LIÊN QUAN

The Government issues a resolution to remove obstacles for the 10,000 billion VND flood prevention project in Ho Chi Minh City

|

HCMC - The nearly VND10,000 billion flood prevention project and the Ring Road 2 section with a capital of more than VND2,700 billion have just been resolved by the Government to remove difficulties and obstacles.

More than 18,000 illegal slaughterhouses increase the risk of African swine fever outbreak

|

The Deputy Minister of Agriculture and Rural Development emphasized the need to resolutely handle slaughterhouses that do not ensure food hygiene and safety - one of the causes of the spread of African swine fever.

Declaring a natural disaster emergency at the Sa Pa BOT station area

|

Lao Cai - The Provincial People's Committee has just announced a natural disaster emergency at the landslide site of the Sa Pa BOT toll station due to the impact of heavy rains.

More than 2,600 cases of chickenpox fever in China, WHO issues global warning

|

The Chinese city of Fujian is entering a heating period in the fight to prevent the epidemic caused by the chikungunya virus transmitted through Aedes mosquitoes.

People in mountainous communes of Nghe An struggle with mud after floods

|

Nghe An - Present in Huu Kiem and Muong Xen communes, Lao Dong Newspaper reporters recorded the urgent atmosphere of the people to overcome the consequences of floods.

Unusual report of rice tray with foreign object giong do during lunch

|

Lao Cai - According to the report of the provincial Department of Health, the foreign object suspected to be a worm may be in the guava fruit, not in the rotated meat as reflected by the workers.

Ban Ve Hydropower Plant records a particularly large flood peak, cutting 74% of flood flow downstream

|

Nghe An - Ban Ve Hydropower Plant recorded a particularly large flood due to the impact of storm No. 3 with a peak flow of up to 12,800 m3/s.

Two dike lines are seriously sunken and cracked, affecting flood resistance, Hanoi urgently directs

|

Hanoi - The right dike of Cau and the right dike of Hong has seen increasingly widening subsidence and cracks, which are assessed as serious.

The Government issues a resolution to remove obstacles for the 10,000 billion VND flood prevention project in Ho Chi Minh City

MINH QUÂN |

HCMC - The nearly VND10,000 billion flood prevention project and the Ring Road 2 section with a capital of more than VND2,700 billion have just been resolved by the Government to remove difficulties and obstacles.

Người dân TPHCM khốn khổ vì ngập, dự án chống ngập 10.000 tỉ đồng bước sang năm thứ 5

MINH QUÂN |

TPHCM - Sau trận mưa lớn đầu mùa, nhiều tuyến đường ở TPHCM ngập nặng, trong khi dự án chống ngập 10.000 tỉ đồng bước sang năm thứ 5 "đắp chiếu".

Dự án ngăn triều nằm im, lãi vay phát sinh 1,7 tỉ đồng mỗi ngày

MINH QUÂN |

Là một trong những dự án bị Ủy viên Bộ Chính trị, Thủ tướng Chính phủ Phạm Minh Chính điểm tên, dự án chống ngập do triều cường gần 10.000 tỉ đồng tại TPHCM dù đạt 93% khối lượng, nhưng lại "đắp chiếu" nhiều năm, khiến lãi vay phát sinh hằng ngày hơn 1,7 tỉ đồng.