The nearly 200 billion VND square project in Hue enters the final sprint phase

ĐẠT LUÂN |

HUE - The contractor is focusing manpower and equipment to bring the Thua Thien Hue Cultural and Sports Square Project to completion early after a delay.

Expecting early completion of the urban highlight project

On the afternoon of June 8, reporters of Lao Dong Newspaper recorded at the Thua Thien Hue Cultural and Sports Square project (Vi Da ward, Hue City), many items have been basically completed, while the gymnasium area still maintains an atmosphere of urgent construction.

At the construction site, workers focused on completing tasks such as building, plastering walls, installing roofing systems, shelters and mechanical and electrical systems. This is an important item under Package No. 11 on renovating the gymnasium.

Previously, An Bao Construction and Trading Joint Stock Company - the unit participating in the construction of the package - had a document requesting the investor to consider extending the project implementation time due to some objective difficulties arising and adjusting the design during the implementation process.

Những hạng mục mới đã hoàn thiện giúp người dân có không gian mới để vui chơi, thể dục thể thao. Ảnh: Phúc Đạt
The new items that have been completed help people have a new space to play and exercise. Photo: Nguyen Luan

According to the contractor, the bidding package is implemented in a period of 400 days, from January 6, 2025 to February 10, 2026. The construction process has changes in technical solutions and design, affecting the overall progress of the project.

Up to now, although not fully completed according to the extended plan, the rough construction of the gymnasium has been basically completed and is entering the final stage of completing the final items.

Hopefully the project will be completed soon and put into service for the people. We are very comfortable walking here every time, it will be even better when the gymnasium is completed, the scenery will be much more beautiful" - Mr. Quoc Viet (a resident of Hue City) shared.

Accelerate the final items

Talking to a reporter of Lao Dong Newspaper, a representative of the Hue City Urban Development and Construction Investment Project Management Board (the project investor) said that the consulting packages of the project have been completed. For the technical infrastructure item under Package No. 10, the project was inaugurated in September 2025 and is currently completing acceptance and handover procedures.

Package No. 11, implemented by the joint venture of An Bao Construction and Trading Joint Stock Company - Vinaconex 25 Joint Stock Company, is worth more than 83.2 billion VND. The investor said that in the past time, they have regularly coordinated with relevant units to remove difficulties and urge contractors to accelerate progress.

Nhà thầu tập trung công nhân, máy móc thi công hạng mục nhà thi đấu. Ảnh: Phúc Đạt
Contractor gathers workers and machinery to construct the competition hall item. Photo: Nguyen Luan

We continue to strengthen supervision, requesting contractors to focus manpower and equipment to complete the project soon, and at the same time ensure quality according to the set requirements" - representative of the Project Management Board said.

When completed, the square and gymnasium will create more large-scale cultural and sports space for city residents.

The Thua Thien Hue Culture and Sports Square project has a total investment of 196 billion VND, with an area of about 7.06ha. The project is expected to contribute to renovating the Ba Trieu Gymnasium area, completing the system of public cultural and sports facilities, and creating a landscape highlight for the eastern center of Hue City.

ĐẠT LUÂN
RELATED NEWS

Viet Tri Ward invests in a series of urban upgrade projects

|

Phu Tho - In the first months of 2026, Viet Tri ward has implemented bidding and construction of many projects, with investments of tens of billions of VND per project.

Payment of compensation for 110kV power line renovation project in Hai Phong

|

Hai Phong - In the afternoon of June 8, 13 households in Hop Tien commune were paid compensation and support for land recovery to implement the 110KV Pha Lai - Dong Nien power line renovation project.

Dong Nai urgently approves compensation to start construction of 5 transport projects

|

Dong Nai - 5 projects started at the end of June include: Ho Chi Minh City Ring Road 4 project, Nguyen Huu Canh road project (Huong Lo 2) and DT road projects 769, 773, 770B.

Wealth of the 5 richest people in Southeast Asia, Vietnamese billionaires lead

|

In the list of the richest people in Southeast Asia, billionaire Pham Nhat Vuong continues to rank No. 1, with assets of up to 30.5 billion USD.

Nuclear weapons return to the center of global geopolitical competition

|

Countries possessing nuclear weapons are taking more warheads out of storage and installing them on launch systems.

A pair of super-luxury cars with an electricization trend attracts the attention of car lovers in Ho Chi Minh City

|

The Lamborghini Urus SE and Rolls-Royce Spectre duo with the trend of electrification have just appeared on the streets of Ho Chi Minh City, attracting the attention of car lovers.

House fire in a deep alley in Ho Chi Minh City suspected of being caused by electrical short circuit

|

Ho Chi Minh City - A house in a deep alley on Le Van Luong street, Tan Hung ward suddenly caught fire, with flames billowing. The initial cause of the fire is suspected to be an electrical short circuit.

10-day weather forecast from June 9th to June 18th nationwide

|

The National Center for Hydro-Meteorological Forecasting forecasts the weather for the next 10 days (from the night of June 8th to June 18th) in regions across the country.

Viet Tri Ward invests in a series of urban upgrade projects

Tô Công |

Phu Tho - In the first months of 2026, Viet Tri ward has implemented bidding and construction of many projects, with investments of tens of billions of VND per project.

Payment of compensation for 110kV power line renovation project in Hai Phong

Hoàng Khôi |

Hai Phong - In the afternoon of June 8, 13 households in Hop Tien commune were paid compensation and support for land recovery to implement the 110KV Pha Lai - Dong Nien power line renovation project.

Dong Nai urgently approves compensation to start construction of 5 transport projects

HÀ ANH CHIẾN |

Dong Nai - 5 projects started at the end of June include: Ho Chi Minh City Ring Road 4 project, Nguyen Huu Canh road project (Huong Lo 2) and DT road projects 769, 773, 770B.