Traffic in Thai Nguyen is invested in to help connect better

Nguyễn Hoàn |

Thai Nguyen - The road connecting Phu Binh district and Pho Yen city with a total investment of 736 billion VND is about to be completed, helping traffic connect better.

The Provincial Road Project (DT) 261 - DT.266 connecting Phu Binh District and Pho Yen City has a total investment of 736 billion VND, invested by the Thai Nguyen Provincial Traffic Construction Investment Project Management Board and approved by the Provincial People's Committee in 2023.

The project has a total length of 2km and a width of 47m. Of which, the section through Phu Binh district is 1.5km long, the rest is in Pho Yen city. The starting point of the project intersects with DT.261 at Km47+350.54, the end point intersects with DT.266 in Diem Thuy commune (Phu Binh).

According to the reporter of Lao Dong Newspaper in early March 2025, after more than 1 year of implementation, the project has been basically completed. Most of the entire road surface is paved with asphalt, making it easy for people and vehicles to travel.

To hand over the project in March 2025, the investor is currently speeding up and urgently implementing the construction of sidewalk items and some other auxiliary items.

As of the first quarter of 2025, the construction progress has reached: the roadbed reached 92.81% of the volume; the road foundation reached 93.3%; the asphalt concrete pavement reached 59.26%; the Kenh bridge project reached 87.51%. Other items (such as drainage system; traffic safety; technical mines, trees, sidewalks, etc.) reached 72.42%.

Toan canh tuyen duong 736 ti dong noi huyen Phu Binh va TP Pho Yen (Thai Nguyen). Anh: Nguyen Hoan.
Overview of the 736 billion VND traffic route connecting Phu Binh district and Pho Yen city (Thai Nguyen). Photo: Nguyen Hoan.

Having a house near the above project, Ms. Nguyen Thi Tham (Phu Binh) said that before the project was implemented, people's travel was very difficult, people and vehicles had to travel a long and time-consuming detour.

"When we learned that there was a road construction project, the people in the area agreed and supported us. Currently, transportation is much more convenient than before, we hope this project will be completed soon to serve the people", Ms. Tham added.

Information from the People's Committee of Diem Thuy commune (Phu Binh), to implement the project through the commune, the area that needs to be cleared is over 4.4 hectares, with 83 households affected.

When completed, the route will create a complete traffic network, connecting industrial parks in the area with the old Hanoi - Thai Nguyen expressway and National Highway 3, contributing to promoting trade and attracting investment.

Some recorded images:

1
After more than 1 year of construction, the road is gradually emerging. Photo: Nguyen Hoan.
2
Currently, the entire route is paved with asphalt, making it easy for vehicles to travel. Photo: Nguyen Hoan.
4
Workers are implementing the construction of sidewalk items. Photo: Nguyen Hoan.
Hshs
Warning signs have been installed to ensure safety for people and vehicles. Photo: Nguyen Hoan.
Nguyễn Hoàn
RELATED NEWS

Upgrading and renovating a series of traffic routes in Thai Nguyen

|

Thai Nguyen - More than 70 billion VND has been invested by Pho Yen City in a series of transportation projects, making travel and trade more convenient.

The support level of 1.6 billion/km cannot "solidify" the traffic route

|

Quang Ngai voters have just proposed that the support level of 1.6 billion/km will not be enough to solidify the roads.

Gas stations in Ho Chi Minh City are ready to sell E10 gasoline

|

From May 15, gas stations in Ho Chi Minh City began switching from RON 95-V gasoline to E10 gasoline.

Buses and electric taxis in Hanoi increase rapidly

|

Clean buses running on green energy have exceeded 42%, electric taxis have reached more than 60% in just the first 4 months of 2026; many people expect the green transition process to take place faster to improve the air quality of the Capital.

After 1 month of subscriber verification, users are surprised to still receive warnings from the network operator

|

After 1 month of deploying SIM authentication, users continue to receive messages from network operators requesting confirmation of phone numbers still in their names.

Instructions on switching from old gasoline cars to electric cars at Green Transit Day 2026

|

On Green Transformation Day 2026, people can bring old gasoline cars to participate in the "gasoline to electricity exchange" program and directly experience new electric vehicle lines.

Draft Report of the Executive Committee of the Vietnam General Confederation of Labor (XIII term) at the XIV Congress of the Vietnam Trade Union, term 2026 - 2031

|

Building a comprehensively strong Vietnam Trade Union; focusing on representing, caring for, and protecting union members and workers; promoting the pioneering role, spirit of innovation and creativity, contributing to realizing the aspiration to build a rich, prosperous, civilized, and happy country.

Upgrading and renovating a series of traffic routes in Thai Nguyen

Nguyễn Hoàn |

Thai Nguyen - More than 70 billion VND has been invested by Pho Yen City in a series of transportation projects, making travel and trade more convenient.

The support level of 1.6 billion/km cannot "solidify" the traffic route

Hiếu Anh |

Quang Ngai voters have just proposed that the support level of 1.6 billion/km will not be enough to solidify the roads.

Kiểm tra việc thi công thủy điện làm sạt lở đường giao thông

NGUYỄN QUÂN |

UBND tỉnh Lâm Đồng yêu cầu đơn vị chức năng kiểm tra, chỉ đạo giải quyết việc thi công công trình thủy điện Cam Ly gây sạt lở đường giao thông.