The connecting road worth over VND4,200 billion in Thai Nguyen is about to reach the finish line for traffic

Nguyễn Hoàn |

Thai Nguyen - The inter-provincial connecting road is being accelerated, expected to be technically opened to traffic on August 19 after more than three years of construction.

As one of the province's key projects with the goal of inter-regional connectivity, the Bac Giang - Thai Nguyen - Vinh Phuc connecting route is expected to create a traffic axis, promoting economic and social development.

The project started construction in May 2022 with a total length of more than 42.5km, a total investment of more than VND 4,200 billion, invested by the Thai Nguyen Provincial Traffic and Agricultural Construction Investment Project Management Board.

gehe
After more than 3 years of implementation, the Bac Giang - Thai Nguyen - Vinh Phuc connecting road project has been basically completed. Photo: Nguyen Hoan.

According to Lao Dong Newspaper reporters in mid-August 2025, after more than 3 years of implementation, the shape of the road has been revealed.

At the end of the route connecting to Phu Tho province (formerly Vinh Phuc province), workers are handling the slope and locations at risk of landslides.

At the same time, a drainage system and slope reinforcement are being deployed to ensure safety.

ydhdj
The road surface is paved with asphalt, railings and warning signs have been installed. Photo: Nguyen Hoan.

Informing reporters, the Thai Nguyen Provincial Project Management Board for Investment and Construction of Traffic and Agricultural Works said that there are currently dozens of vehicles and machines on the entire route under continuous construction.

The construction teams have basically completed the asphalt concrete pavement, installed guardrails, signs, and lighting systems. The site clearance work has reached 99.94%, with only 26 households remaining behind.

The progress of main items such as: roadbed is nearly 100%, foundation level of type II crushed stone is 97.01%, type I is 96.3%, asphalt concrete road surface is 96.3%.

Three large bridges have completed 95.03%, the basic items of culverts, underpasses, and retaining walls are completed.

hdhs
The Chairman of the Thai Nguyen Provincial People's Committee (currently pointing out) inspected the end point of the project connecting to Phu Tho province (formerly Vinh Phuc province). Photo: Dang Vu.

Previously, Mr. Pham Hoang Son - Chairman of Thai Nguyen Provincial People's Committee said that this is a strategic project that helps shorten travel time, reduce traffic pressure, and open new development space for the locality.

The provincial leader requested investors to mobilize maximum human resources and equipment, coordinate with departments and branches to remove obstacles, ensure progress and quality. The entire route is expected to be technically open to traffic on August 19, 2025.

When put into operation, the route will become an important link in the inter-regional transport network, opening up opportunities to attract investment, develop trade, services and industry, contributing to changing the economic landscape of the region.

Some recorded images:

1
The project's end point area is rushing to complete the infrastructure and final items before the technical opening date. Photo: Nguyen Hoan.
Mat duong toan tuyen 4 lan xe thuoc dia phan tinh Thai Nguyen da tham nhua xong. Anh: Nguyen Hoan.
The road surface of the entire 4-lane route in Thai Nguyen province has been paved with asphalt. Photo: Nguyen Hoan.
3
The slope areas are reinforced to ensure safety. Photo: Nguyen Hoan.
4
A series of hard bridges across the river is basically completed. Photo: Dang Vu.
Nguyễn Hoàn
RELATED NEWS

A series of key overpasses on the billion-dong connecting road

|

Thai Nguyen - The Thai Nguyen - Bac Giang - Vinh Phuc connecting road has a total investment of VND3,800 billion, and has gradually been completed after a long period of construction.

The shape of a river-crossing bridge on the regional connecting road

|

Thai Nguyen - The Cong River overpass on the Thai Nguyen - Bac Giang - Vinh Phuc connecting route is speeding up the progress, constructing the installation of girders.

Thai court sets date for sentencing Ms. Paetongtarn over phone call with Mr. Hun Sen

|

The verdict on Ms. Paetongtarn Shinawatra in the leak of a phone call with Mr. Hun Sen will be announced on August 29.

Appointing Mr. Bui Quang Huy to hold the position of Secretary of the Central Party Committee of the Youth Union for the 2025 - 2030 term

|

On the afternoon of August 13, in Hanoi, the 1st Congress of the Central Party Committee of the Ho Chi Minh Communist Youth Union, term 2025 - 2030, held a solemn session.

Medical examination has surrounded the hospital gate, the obsession has no end

|

HCMC Exposure to whooping cough is a reality that makes patients frustrated, the health sector has a headache finding a definitive solution.

The case of house construction waiting for compensation in Thai Nguyen, Ward Chairman asks to take responsibility

|

Thai Nguyen - Chairman of Pho Yen Ward would like to take responsibility before the Provincial People's Committee if there are any construction violations that are not promptly prevented and handled.

28 enterprises will be honored as "Outstanding Enterprises for Workers"

|

The "Outstanding Enterprise for Workers" Award is scheduled to take place at 7:30 p.m. on August 15.

A series of key overpasses on the billion-dong connecting road

Lam Thanh |

Thai Nguyen - The Thai Nguyen - Bac Giang - Vinh Phuc connecting road has a total investment of VND3,800 billion, and has gradually been completed after a long period of construction.

The shape of a river-crossing bridge on the regional connecting road

Lam Thanh |

Thai Nguyen - The Cong River overpass on the Thai Nguyen - Bac Giang - Vinh Phuc connecting route is speeding up the progress, constructing the installation of girders.

Những mét nhựa đầu tiên trên tuyến đường liên kết nghìn tỉ ở Thái Nguyên

Việt Bắc |

Sau tròn 2 năm khởi công, những km đầu tiên của tuyến đường liên kết Thái Nguyên - Bắc Giang - Vĩnh Phúc đã được thảm nhựa tiến tới hoàn thành toàn bộ dự án.