The project to renovate and upgrade the inter-commune road DH47 section passing through Cam Khe and Van Ban communes was approved according to Decision No. 990/QD-UBND dated November 14, 2025 of Cam Khe Commune People's Committee.
This project belongs to Group C, with a total investment of 38 billion VND invested by Cam Khe Commune People's Committee.
According to the reporter's investigation, Cam Khe Commune People's Committee recently issued a notice inviting bids for Package No. 05 - Construction of the project.
Package No. 05 was widely bid through the network, costing more than 33 billion VND from provincial budget support, commune budget and mobilizing other legal capital sources.
In the coming time, after having the contractor selection results approved by the investor, the construction contractor will deploy the bidding package with the scope of work as follows:
The total length of the route is about 3.1km designed according to the standard of level IV mountain roads (including 2 sections: section 1 is 2.7km long and section 2 is 0.4 km long), the starting point of the route is provincial road 313 (Km4+450), heading along old DH47 road connecting Cam Khe and Van Ban communes, going to the entire area of Cam Khe commune.
For section 1 (passing through the old Xuong Thinh commune, 2,666.87m long), the road surface width is 5.5m, the asphalt concrete surface is 7cm thick; the width of the drainage ditch is 0.25m on each side; the sidewalk width is 1.52m on each side, including the sidewalk and nape (the drainage system is only arranged synchronously with the sidewalk on section 1).
For section 2 (through Cap Dan commune connecting to old Tung Khe commune, 414.16m long), road surface width 5.5m, asphalt concrete surface 7cm thick.
Regarding the intersection at the beginning and end of the route, at the beginning of section 1, the location of the intersection with provincial road 313 is recovered and cleared of ground, expanded to ensure the expansion of the entrance and exit intersection of the road. At the end of section 1, the beginning of section 2 and the end of section 2 are designed to connect synchronously with the road section that has been completed before.
Along with that, the bidding package will construct turnarounds, service roads, turnarounds to restore people's houses; lighting system; paint marking, placement of signs...
Package implementation time: 300 days.
Talking to Lao Dong Newspaper reporters, Mr. Nguyen Anh Tuan - Vice Chairman of Cam Khe Commune People's Committee said that the project is invested with the aim of overcoming the degradation of the foundation and roads, upgrading the drainage system, avoiding flooding, installing synchronous lighting, ensuring traffic safety, convenient for people's travel and aesthetics in the area.
After the project is put into operation, a large number of workers in the area will easily travel on the road, thereby connecting the inter-regional road branch to go straight to Cam Khe industrial park" - Mr. Tuan shared.