The first elevated road in Ho Chi Minh City continues to postpone the opening date

MINH QUÂN |

Ho Chi Minh City - The elevated road belonging to the Ring Road 3 project, the eastern section, 14.7km long, 4 lanes, continues to postpone the opening date to June 30, instead of April 30.

On April 21, representatives of the Ho Chi Minh City Traffic Construction Investment Project Management Board (Traffic Board) said that the construction progress of the elevated road section of Ring Road 3 of Ho Chi Minh City (from Ho Chi Minh City - Long Thanh - Dau Giay expressway to Tan Van intersection) did not meet expectations. According to the design, this section is 14.7km long, with a scale of 4 lanes.

Currently, the Ho Chi Minh City Traffic Board has reported on the plan to adjust the progress, expected to be completed by the end of June 2026.

Đoạn Vành đai 3 trên cao nối ra nút giao Tân Vạn vẫn còn những nhịp cầu chưa gác dầm.  Ảnh: Minh Quân
The elevated Ring Road 3 section connecting to Tan Van intersection still has bridge spans without girders. Photo: Minh Quan

Records at the construction site show that many items are still unfinished. The uphill and downhill area at the section adjacent to Tan Van intersection is not completed, and girder installation has not been completed.

Đường trên cao Vành đai 3 vẫn còn đứt đoạn.  Ảnh: Minh Quân
Ring Road 3 elevated road is still broken. Photo: Minh Quan

Asphalt concrete paving from Vinhomes Grand Park urban area to Tan Van intersection is being stalled.

Similarly, the intersection item between Ring Road 3 and the Ho Chi Minh City - Long Thanh - Dau Giay expressway is also not complete.

Vành đai 3 qua khu đô thị Vinhomes Grand Park đã thảm bê tông nhựa.  Ảnh: Minh Quân
Ring Road 3 through Vinhomes Grand Park urban area has been paved with asphalt concrete. Photo: Minh Quan

This is the second time that this elevated Ring Road 3 section has missed the traffic opening deadline. Previously, the Ho Chi Minh City Traffic Board had committed to put it into operation on December 19, 2025, but by this time the project has only reached the technical traffic opening level. After that, the completion milestone was further adjusted to April 30, 2026, but still could not be achieved.

Vành đai 3 uốn lượn trên cao qua khu Đông TPHCM.  Ảnh: Minh Quân
Ring Road 3 winding up high through the East of Ho Chi Minh City. Photo: Minh Quan

Not only the East section, but also the West section of Ring Road 3 HCMC (through Cu Chi, Hoc Mon, Binh Chanh districts before) about 32.6km long, including 5 bidding packages from XL6 to XL10, is also behind schedule and is likely not to be cleared in time for June 30, 2026. The reason is the shortage of raw materials.

Người dân phải chờ thêm 2 tháng nữa mới được lưu thông qua Vành đai 3 phía Đông.  Ảnh: Minh Quân
People have to wait another 2 months to be able to travel through Ring Road 3 East. Photo: Minh Quan

Faced with this situation, the Ho Chi Minh City People's Committee has issued drastic directions to accelerate the progress of the entire project. The Traffic Management Board is requested to urgently approve the technical design dossiers of smart traffic system (ITS) items, non-stop electronic toll collection (ETC), as well as vehicle load control works in April 2026 to deploy synchronously throughout the route.

At the same time, relevant units must review and re-establish detailed progress for each bidding package; clarify the construction situation, difficulties, obstacles and propose solutions. The new progress must be confirmed by the investor, contractor and supervision consultant, committed to implementation, and reported to the City People's Committee and the Department of Construction for monitoring.

The Ho Chi Minh City People's Committee also requested the investor to proactively and thoroughly handle obstacles affecting the progress. In case it is not guaranteed to be completed before June 30, 2026 according to Resolution 105/NQ-CP and the City's direction, it is necessary to specifically report the completed volume, the remaining part, causes and remedial plans.

Vành đai 3 TPHCM phía Đông lùi mốc thông xe đến ngày 30.6.  Ảnh: Minh Quân
Ring Road 3 of Ho Chi Minh City in the East is postponed from the opening date to June 30. Photo: Minh Quan

In addition, construction management work must be strengthened and personnel must be sufficiently qualified; requiring contractors to promote resource mobilization, expand construction teams, organize "3 shifts, 4 teams" and proactively gather materials.

The Ho Chi Minh City Transport Board is assigned to be fully responsible to the City Party Committee and the City People's Committee for the progress, quality and contents related to the Ring Road 3 component project through the area.

MINH QUÂN
RELATED NEWS

Tan Van intersection, the largest on Ring Road 3 in Ho Chi Minh City, is about to open to traffic, reducing congestion in the East

|

Ho Chi Minh City - Tan Van intersection, the largest of the Ho Chi Minh City Ring Road 3 project with a total capital of more than 1,800 billion VND, is being accelerated and is expected to open to traffic on June 30.

Technical traffic opening of nearly 15 km of Ring Road 3 overpass through the eastern urban area of Ho Chi Minh City

|

HCMC - The nearly 15 km long section of the Ho Chi Minh City Ring Road 3 overpass was technically opened to traffic on December 19, after more than two years of construction.

The Traffic Department states the reason for the delay in the opening of the first elevated road in Ho Chi Minh City

|

HCMC - The 14.7 km long eastern elevated road section of Ho Chi Minh City Ring Road 3 will only be technically open to traffic on December 19, 2025, instead of officially opening as planned.

Cold air is about to cause thunderstorms, warning of dangerous weather in 7 provinces and cities

|

The meteorological agency warns of the risk of extreme rain due to inter-season cold air, especially in some northern mountainous provinces or the west of Thanh Hoa and Nghe An.

Cuba negotiates with the US on lifting oil and gas embargo

|

Cuba confirmed that it had negotiated with US officials, focusing on ending Washington's oil embargo.

Quy Nhon beach reveals strange object, suspected to be wartime tank parts

|

Gia Lai - A large metal object suddenly revealed at Quy Nhon beach when the tide receded, suspected to be a buried wartime tank part.

Experts talk about the operating efficiency of E10 gasoline

|

E10 gasoline contains 10% ethanol with oxygen content, which helps the burning process in the engine to be more complete and cleaner.

Government Inspectorate names a series of urban area and housing projects with violations in Hanoi

|

The Government Inspectorate pointed out many shortcomings and violations after inspecting urban area and housing projects in Hanoi.

Tan Van intersection, the largest on Ring Road 3 in Ho Chi Minh City, is about to open to traffic, reducing congestion in the East

MINH QUÂN |

Ho Chi Minh City - Tan Van intersection, the largest of the Ho Chi Minh City Ring Road 3 project with a total capital of more than 1,800 billion VND, is being accelerated and is expected to open to traffic on June 30.

Technical traffic opening of nearly 15 km of Ring Road 3 overpass through the eastern urban area of Ho Chi Minh City

Tâm Tú |

HCMC - The nearly 15 km long section of the Ho Chi Minh City Ring Road 3 overpass was technically opened to traffic on December 19, after more than two years of construction.

The Traffic Department states the reason for the delay in the opening of the first elevated road in Ho Chi Minh City

MINH QUÂN |

HCMC - The 14.7 km long eastern elevated road section of Ho Chi Minh City Ring Road 3 will only be technically open to traffic on December 19, 2025, instead of officially opening as planned.