Public investment disbursement in Quang Tri is slow, risk of missing progress

CÔNG SÁNG |

Quang Tri - Up to now, public investment disbursement in Quang Tri has only reached 45.54% of the plan assigned by the Prime Minister, lower than the national average.

Many projects have very low disbursement rates

On December 16, according to the latest update from the State Treasury of Region XII, as of November 30, 2025, the disbursement rate of public investment capital in 2025 for projects managed by localities in Quang Tri reached a low level.

The new disbursement reached 42.96% of the total local capital plan and reached 45.54% of the capital plan (KHV) assigned by the Prime Minister, lower than the national average.

According to the analysis of the State Treasury of Region XII, the main reason is that many projects are in the construction phase and do not have completed volume for acceptance and payment. In addition, some projects are allocated large capital plans but the disbursement rate is very low, reducing the overall rate of the whole province.

Notably, a series of key transport and infrastructure projects have disbursement levels only at a "moderate" level. The National Highway 15D project from My Thuy Port to Cam Lo - La Son Expressway has only reached 1.09%. The coastal road section through Cua Tung and Cua Viet bridges disbursed 3.17%. The route connecting Quang Tri Airport with National Highway 1 has only reached more than 5%.

Many other projects such as the road at both ends of the Song Hieu cable-stayed bridge (phase 1), developing tourism infrastructure to support comprehensive growth in the GMS area phase 2, Tran Nguyen Han street (phase 2) all have a disbursement rate of less than 12%. Component project 1 of Coastal Road has reached 41%.

On the other hand, the disbursement of public investment capital at the commune level has changed more positively. The total commune-level budget revenue in 2025 is VND 941,329 million, including extended capital and capital in 2025.

By November 30, 2025, the disbursed capital reached 73.7% of the capital plan. Of which, the extended disbursement capital reached 71.2%, and the capital in 2025 reached 73.7%.

However, there is still nearly 119 billion VND that has not been integrated into the Tabmis system, of which more than 72.8 billion VND does not have land funds and more than 46.1 billion VND does not have construction codes. These are technical "bottlenecks" that make it impossible to disburse at the same time.

Speed up the progress for the remaining days

Faced with this situation, Chairman of the People's Committee of Quang Tri province Le Hong Vinh said that for the public investment capital of the commune-level budget and other capital sources invested by the commune, the province requires communes, wards and special zones to urgently review, proactively urge contractors, speed up construction progress and complete payment documents, and disburse all assigned capital plans.

In case of failure to disburse all, communes, wards and special zones must take full responsibility.

The People's Committee of Quang Tri province will also organize a review and include the disbursement results in the emulation and reward criteria at the end of 2025. Units that cannot disburse, have their estimates canceled, lose capital or do not complete the project according to the approved schedule will be held responsible.

Along with that, the province requires relevant departments, branches and units to implement an assignment mechanism, with clear and specific coordination on authority and responsibility. The support for investors in acceptance, handover, putting the project into use as well as payment and disbursement procedures must be carried out synchronously, avoiding the situation of "playing football" with responsibility.

The State Treasury of Region XII and transaction offices in the province are assigned to strengthen guidance, support, and create favorable conditions for investors in the process of completing payment procedures, especially for the long-term planned capital.

The Chairman of the People's Committee of Quang Tri province affirmed that the remaining disbursement time is not much, requiring provincial departments, branches, sectors, People's Committees of communes, wards, special zones, investors and project management boards to focus highly and urgently implement.

CÔNG SÁNG
RELATED NEWS

Disbursement of public investment capital has only reached 39.4%, Vinh Long resolutely speeds up progress

|

Vinh Long - By November 14, the province had only disbursed public investment capital reaching 39.4% of the plan, the province determined to handle weakness and speed up progress.

Hanoi speeds up public investment disbursement

|

Hanoi is promoting many solutions to speed up the disbursement of public investment capital, creating an important driving force to achieve the economic growth target of 8%.

Lang Son adjusts to reduce public investment capital by more than 197 billion VND in 3 major projects

|

Lang Son - The Provincial People's Committee has just adjusted down more than 197 billion VND in public investment capital in 2025 in 3 major projects, including transportation, digital transformation and sports complexes.

Nguyen Thi Oanh equalizes a record of 15 gold medals in SEA Games athletics

|

The victory in the 3,000m final overcoming obstacles helped Nguyen Thi Oanh equal the record of 15 gold medals in the SEA Games athletics.

Police exposed the tricks of drivers to avoid AI cameras

|

Hanoi - Many drivers use all kinds of methods to cover and blur their license plates to bypass the AI camera.

Accelerating site clearance, Ring Road 1 gradually emerges

|

Hanoi - The site clearance of Ring Road 1 from Hoang Cau to Voi Phuc is in the acceleration phase, with continuous machinery and openings.

The Standing Vice President of the Vietnam General Confederation of Labor suggested 4 issues at the Vinh Long Provincial Trade Union Congress

|

Vinh Long - Ms. Thai Thu Xuong - Permanent Vice President of the Vietnam General Confederation of Labor suggested a number of issues at the Provincial Trade Union Congress.

After 7 years of sluggish progress, the Cho Mai - Tan My road project in Hue has just completed the asphalt paving

|

HUE - The Cho Mai - Tan My road project with a total investment of nearly 200 billion VND, over 4km long, has just completed asphalt paving after many years of slow construction.

Disbursement of public investment capital has only reached 39.4%, Vinh Long resolutely speeds up progress

AN NHIÊN |

Vinh Long - By November 14, the province had only disbursed public investment capital reaching 39.4% of the plan, the province determined to handle weakness and speed up progress.

Hanoi speeds up public investment disbursement

Minh Hạnh |

Hanoi is promoting many solutions to speed up the disbursement of public investment capital, creating an important driving force to achieve the economic growth target of 8%.

Lang Son adjusts to reduce public investment capital by more than 197 billion VND in 3 major projects

Khánh Linh |

Lang Son - The Provincial People's Committee has just adjusted down more than 197 billion VND in public investment capital in 2025 in 3 major projects, including transportation, digital transformation and sports complexes.