According to the report of the Department of Finance, in 2025, the total public investment capital plan of Quang Ngai province assigned by the Prime Minister is VND 7,866 billion, of which the central budget is VND 2,776 billion and the local budget is VND 5,091 billion.
In the initial phase of merging provinces and organizing local governments at two levels, under the strong direction of the Provincial People's Committee, investors have made efforts to implement projects, but the disbursement progress is still facing difficulties. The main reason is that some projects have to be suspended to review and re-determine demand; adjust the scale and scope of investment; change investors or adjust medium-term public investment capital plans, 2025 plans...

According to the leader of the Land Fund Development Center, some land clearance projects have not met requirements due to slow construction of resettlement areas; slow determination of land prices as a basis for approving compensation plans. These problems and difficulties have now been basically resolved, the Provincial Land Fund Development Center is speeding up the site clearance progress.
According to Mr. Nguyen Hoang Giang - Chairman of the People's Committee of Quang Ngai province, the provincial leaders have requested departments, branches and localities to focus on promoting compensation, site clearance, and urging construction progress; localities actively propagate and mobilize people to create consensus among the people on the implementation of projects in the area...
The Chairman of the People's Committee of Quang Ngai province also agreed to stipulate the time frame for reporting the disbursement of public investment capital in the whole province on the 2nd of each month to promptly grasp and direct.
The leader of the People's Committee of Quang Ngai province also requested the State Treasury of the XV region to study and refer to the effective practices of other localities, creating favorable conditions for investors to complete payment procedures, and increase the disbursement rate of the province. At the same time, the State Treasury is requested to provide detailed disbursement data for each project month to serve the synthesis and reporting work, serving the direction and operation of the Provincial People's Committee.