Freeing the power grid from the North-South expressway

TRẦN TUẤN |

Ha Tinh - One of the two last grid-connected points of the North-South Expressway Project through Ha Tinh, in Tan Lam Huong commune, was cleared on January 5.

On January 5, according to a reporter from Lao Dong Newspaper, the 220kV power grid crossing the North-South expressway project, Ham Nghi - Vung Ang section in Tan Lam Huong commune (Ha Tinh city) is being urgently pulled up to 2 new pole positions by dozens of technical staff and workers of Quoc Anh Construction Investment Company (Hanoi) to ensure safety for the expressway construction contractor.

A technical officer of Tu Lap Construction Company Limited - the contractor constructing the 3.9km expressway currently stuck in the 220kV power grid in Tan Lam Huong commune - said that Quoc Anh Construction Investment Company has announced that the wire pulling to the pole will be completed on January 5.

100m cao toc qua xa Tan Lam Huong nay lau nay vuong luoi dien 220kV chua thi cong mong nen, tham duong duoc. Anh: Tran Tuan.
100m of the highway through Tan Lam Huong commune was obstructed by the 220kV power grid, causing the construction of the foundation and pavement to be delayed. Photo: Tran Tuan.
Nhung day dien cuoi cung sap duoc keo cang len cot. Anh: Tran Tuan. Anh: Tran Tuan.
The last wire is about to be stretched onto the pole. Photo: Tran Tuan.

"This section of the power grid is 100m long. From tomorrow, we will focus on human resources and machinery to pour the roadbed and lay asphalt to make the line continuous," this person said.

The technical officer of Tu Lap Construction Company Limited also added that the 3.9km of highway that the unit undertook to construct has been basically completed, with only 100m remaining stuck with the power grid. If the past time had not been stuck, the unit would have completed the entire construction package of its contract.

As planned, Tu Lap Construction Company Limited will focus on completing the entire 3.9km expressway project before Lunar New Year 2025.

3,9km cao toc ma Cong ty Tu Lap thi cong co ban da hoan thanh, hien chi con 100m doan vuong luoi , tu ngay 6.1 se duoc tap trung thi cong de lien tuyen. Anh: Tran Tuan.
The 3.9km expressway that Tu Lap Company is constructing has basically been completed, currently there is only 100m of the grid-bound section left, from January 6th, construction will be focused on to connect the route. Photo: Tran Tuan.

On January 5, Mr. Doan Ngoc Huong - Chairman of Thanh Binh Thinh Commune People's Committee (Duc Tho District) - said that the North - South Eastern Expressway project phase 2021 - 2025 is currently stuck at a 220kV power grid location through this locality.

According to the plan, on January 10, when the electricity industry cuts off power, the contractor will start pulling wires to two new pole locations, striving to complete before January 16 to hand over the site for highway construction.

The North-South Eastern Expressway project in the 2021-2025 period through Ha Tinh province, which has been blocked by many power distribution grids (voltage level 110 kV or lower), has now been cleared, ensuring the ground for contractors to construct the expressway.

Luoi dien 220kV qua xa Tan Lam Huong lau nay vuong can tro thi cong cao toc, tu ngay 5.1 da hoan thanh giai phong. Anh: Tran Tuan.
The 220kV power grid through Tan Lam Huong commune, which had long been obstructing the construction of the expressway, was cleared on January 5. Photo: Tran Tuan.

The power transmission grid in Ha Tinh province has 10 intersections with the North-South Expressway, including 4 500 kV lines and 6 220 kV lines in the districts of Ky Anh, Cam Xuyen, Thach Ha, Duc Tho, and Ky Anh town. To date, there is only 1 remaining problem in Thanh Binh Thinh commune, Duc Tho district.

To date, there is only one remaining bottleneck in Thanh Binh Thinh commune, Duc Tho district. The People's Committee of Ha Tinh province has repeatedly urged the urgent completion of the power grid clearance to hand over the site to the highway construction contractor.

TRẦN TUẤN
TIN LIÊN QUAN

A section of the North-South Expressway will be expanded from 17m to over 32m

|

The Ministry of Transport said that the Cao Bo - Mai Son expressway will be operational from 2023. This section of the expressway will be widened from 17m to more than 32m.

Busy construction of North-South expressway in Ha Tinh

|

Ha Tinh - December 31 is the last day of the 2024 calendar year. At the construction site of the North-South expressway through Ha Tinh province, workers are still busy speeding up construction progress.

17ha of forest conversion for North-South expressway project

|

Ha Tinh - During the construction of the North-South Expressway project, an additional 17 hectares of forest were converted, so Ha Tinh authorities are completing the procedures for the conversion.

Visit the home of extremely venomous snakes on Phu Quoc Island

|

Kien Giang - Dong Tam 2 Snake Farm is a place to preserve medicinal herbs and the gene source of two rare venomous snake species, the cobra and king cobra of Phu Quoc.

Shocking truth about the collision of 2 US planes that killed 67 people

|

The US Federal Aviation Administration (FAA) announced the preliminary results of the investigation into the collision of a US plane and a military helicopter on January 29 near Washington D.C.

EU goes easy on Russian gas in new sanctions package

|

The EU did not impose a comprehensive ban on Russian gas imports in the 16th package of sanctions.

Leather shoe factory fire on the second night of Tet in Ho Chi Minh City

|

HCMC - A leather shoe factory in Hoc Mon district suddenly caught fire on the night of the second day of the Lunar New Year (January 30), destroying many properties.

A section of the North-South Expressway will be expanded from 17m to over 32m

Xuyên Đông |

The Ministry of Transport said that the Cao Bo - Mai Son expressway will be operational from 2023. This section of the expressway will be widened from 17m to more than 32m.

Busy construction of North-South expressway in Ha Tinh

TRẦN TUẤN |

Ha Tinh - December 31 is the last day of the 2024 calendar year. At the construction site of the North-South expressway through Ha Tinh province, workers are still busy speeding up construction progress.

17ha of forest conversion for North-South expressway project

TRẦN TUẤN |

Ha Tinh - During the construction of the North-South Expressway project, an additional 17 hectares of forest were converted, so Ha Tinh authorities are completing the procedures for the conversion.