On the morning of September 13, the weather in Ha Tinh was clear. Contractors focused on machinery and construction personnel to speed up progress on the North-South Expressway Project packages for the 2021-2025 phase through Ha Tinh province.
At the Ham Nghi - Vung Ang section through Tan Lam Huong commune, Thach Ha district, constructed by Tu Lap Construction Company Limited, the road roller is focusing on rolling after spreading the C19 asphalt layer, while in some other sections, the final asphalt layer, C16 asphalt layer, has been completed.
A technical officer of Tu Lap Construction Company Ltd. present at the construction site said that the contract package of this Company is 4km long, up to now, the construction of C19 asphalt concrete layer has reached 50%, and C16 asphalt concrete layer (final road surface layer) has reached 45%.
Some workers are laying lines to erect a hard median strip on the road, others are sowing grass seeds on the roadside embankment.
Also at the Ham Nghi - Vung Ang section in Cam Thach commune (Cam Xuyen), adjacent to the section constructed by Tu Lap Construction Company Limited, Xuan Truong Construction Company is constructing the roadbed in the section that was previously obstructed by the high-voltage power grid.
Road rollers and trucks are working at this point to connect the roadbed.
Mr. Nguyen Khac Trung - Director of the North - South Expressway Project Management Board, Ham Nghi - Vung Ang section - informed that up to this point, the total construction volume on the Ham Nghi - Vung Ang route has reached about 56%.
Of which, the roadbed has been basically completed, the road foundation has reached about 60%, and the road surface has reached about 45%.
"Currently, contractors are focusing on synchronously constructing underpasses and access roads to ensure technical and aesthetic requirements, speeding up the synchronous progress of the Project," said Mr. Trung.
Mr. Hoang Chien Thang - Executive Director of the Bai Vot - Ham Nghi expressway project (Thang Long Project Management Board) - said that up to this point, the total construction volume of contractors on the Bai Vot - Ham Nghi section has reached about 59% of the volume.
Some images of highway construction in Ha Tinh on the morning of September 13: