Removing the bottleneck of the Noi Bai - Lao Cai expressway service road

Duy Dũng |

Functional forces are actively removing site bottlenecks on service roads and intersections so that the Noi Bai - Lao Cai expressway expansion project can be completed on schedule.

Removing each site bottleneck

At the construction site of the Yen Bai - Lao Cai expansion project, the construction atmosphere is urgent.

The investor - Vietnam Expressway Corporation (VEC) and contractors are mobilizing manpower, machinery, and organizing construction in the spirit of "3 shifts, 4 teams", striving to complete the project in 2026.

However, the implementation process still faces many difficulties due to some locations still facing additional site clearance at intersections and people's service roads.

Dự án mở rộng cao tốc Nội Bài - Lào Cai có tổng mức đầu tư gần 7.700 tỉ đồng. Ảnh: Hùng Cường
The Noi Bai - Lao Cai expressway expansion project has a total investment of nearly 7,700 billion VND. Photo: Hung Cuong

According to VEC's report, at IC15 intersection (Km165+690), package XL1-NBLC is still facing site clearance issues for 2 households in branch C.

The project also needs to recover additional 2,793m2 of land to build the E branch service road connecting to provincial road 163, 242m long, 5m wide base.

In Chau Que commune, the additional people's service road on the left side of the expressway, section Km171+600 - Km172+240, 751m long, is being prepared by the contractor with machinery to pile soil K95, K90 and pour cement concrete C25.

Before the urgent requirement for progress, VEC has issued an urgent document requesting the People's Committee of Lao Cai province and the authorities of Dong Cuong and Chau Que communes to focus on definitively resolving obstacles and handing over land before September 15, 2026.

Public and transparent dialogue

In Chau Que commune, to create ground for the 751m long service road, in recent days, local officials have directly gone to villages and hamlets to meet and exchange with each household.

Tuyến đường gom dân sinh tại xã Châu Quế có chiều dài 751m.
The people's service road in Chau Que commune is 751m long. Photo: Hung Cuong

Mr. Nguyen Dinh Dang - Head of the Economic Department of Chau Que commune - said that after being propagated and mobilized by the government, Mr. Chu Van Tien's family agreed to hand over the affected land area for the construction unit to implement the project.

The process of determining the boundary of recovery is carried out publicly, combined with meetings in the village to explain specifically the scope of recovery, land use purpose and long-term benefits of the project.

Các cơ quan chuyên môn xã Châu Quế tuyên truyền, trao đổi với hộ dân bị ảnh hưởng.
Specialized agencies propagate and exchange information with affected households. Photo: Hung Cuong

In Dong Cuong commune, where land needs to be recovered to build the road to restore branch E, serving IC15 intersection, local authorities also organized surveys, measurements and worked directly with households.

Mr. Nguyen Xuan Duong - Head of the Economic Department of Dong Cuong commune - said that as soon as there was a plan, local officials directly measured and reviewed each land area.

According to Mr. Duong, the biggest difficulty is that the road affects the area currently cultivated with crops of 7 households.

Therefore, the locality chooses a direct, public, and transparent working plan to both ensure the progress of the project and ensure the legitimate rights of the people.

People agree for the common good

Mr. Chu Van Tien's family, in Khe Phao village, Chau Que commune, has about 200m2 of rice and banana land affected by the people's service road.

Người dân nhường đất để cao tốc sớm về đích
People voluntarily give up land for the project to continue construction. Photo: Hung Cuong

After being propagated, mobilized and specifically explained by the government about the scope of recovery, Mr. Tien agreed to hand over the land to serve construction.

In Toan An village, Dong Cuong commune, Ms. Do Thi Loan's family also agreed to hand over the land area within the project scope.

Ms. Loan shared that her family agreed to donate land to serve the expressway expansion project, and hoped that the road would be completed soon so that people could travel and transport goods more conveniently.

Chính quyền xã Đông Cuông tuyên truyền, vận động các hộ dân có đất nằm trong diện thu hồi.
Dong Cuong commune authorities propagate and mobilize households with land in the recovered area. Photo: Hung Cuong

Not only resolving an administrative procedure, direct meetings between officials and people have contributed to creating consensus from the grassroots level.

When people clearly understand the goals and benefits of the project and their legitimate rights are guaranteed, the remaining land areas are gradually removed.

Vietnam Expressway Development Investment Corporation emphasized that each meter of site handed over at the right time not only helps the contractor expand the construction area but also contributes to keeping the pace for the entire construction site of the Noi Bai - Lao Cai expressway expansion project.

Duy Dũng
RELATED NEWS

Completing the road connecting 2 expressways Noi Bai - Lao Cai and Tuyen Quang - Phu Tho

|

Phu Tho - The road connecting the Noi Bai - Lao Cai expressway with the Tuyen Quang - Phu Tho expressway, more than 2.7km long, has been completed.

Noi Bai - Lao Cai expressway expansion site accelerates before the rainy and flood season

|

At the Noi Bai - Lao Cai expressway expansion site, hundreds of engineers and workers are working day and night to race before the rainy and flood season.

Intense heat, the tunnel through the mountains of the Noi Bai - Lao Cai expressway still has red lights

|

In the harsh summer heat, workers are still clinging to the construction site, speeding up the progress of the mountain tunnel belonging to the Noi Bai - Lao Cai expressway expansion project.

Fined 7 million VND for alcohol concentration, a man hugs traffic police officer to ask for sympathy because he missed out

|

Ho Chi Minh City - During the September 2nd holiday, many cases of alcohol concentration violations were handled. Among them, a man was fined 7 million VND, hugged a traffic police officer pleading because he was "excited".

Regulations on transferring documents and papers when renaming Quang Ninh city

|

The National Assembly Standing Committee has issued a Resolution on the establishment of Quang Ninh city.

Explosion of stimulus programs on the occasion of Quang Ninh becoming a city

|

Quang Ninh - Welcoming Quang Ninh City and holidays, many businesses and units are implementing many stimulus programs and preferential price packages for products and services.

Cong Phuong's team changed its name before their first season in the V.League

|

Cong Phuong's team will have a new name, Dong Nai City Football Team, from the 2026-2027 season, after completing relevant procedures.

National Day in the memories of soldiers in the past

|

From the battlefield to the silent tasks on big holidays, veterans have gone through a part of history with youth, sweat and sacrifice. More than half a century has passed, that memory is still intact, so that every National Day holiday returns, they feel proud to live in a peaceful country.

Completing the road connecting 2 expressways Noi Bai - Lao Cai and Tuyen Quang - Phu Tho

Tô Công |

Phu Tho - The road connecting the Noi Bai - Lao Cai expressway with the Tuyen Quang - Phu Tho expressway, more than 2.7km long, has been completed.

Noi Bai - Lao Cai expressway expansion site accelerates before the rainy and flood season

Bảo Nguyên |

At the Noi Bai - Lao Cai expressway expansion site, hundreds of engineers and workers are working day and night to race before the rainy and flood season.

Intense heat, the tunnel through the mountains of the Noi Bai - Lao Cai expressway still has red lights

Nguyên Phong |

In the harsh summer heat, workers are still clinging to the construction site, speeding up the progress of the mountain tunnel belonging to the Noi Bai - Lao Cai expressway expansion project.