Removing obstacles to materials for key national transport projects

HÀ ANH CHIẾN |

In Dong Nai province, a conference was held to agree on solutions to ensure construction materials for the construction of key national transport projects in the area.

Implementing the Prime Minister's direction at the meeting on February 1, 2025, the Dong Nai Provincial People's Committee was requested to preside over and coordinate with the Ministry of Natural Resources and Environment and the Ministry of Public Security to resolve difficulties in materials - February 7, the Ministry of Natural Resources and Environment to coordinate with the Dong Nai Provincial People's Committee and relevant ministries and branches to organize the "Reunification of solutions to ensure construction materials for the construction of key national transport projects in Dong Nai province".

At the conference, Mr. Le Anh Tuan - Deputy Minister of Transport said that the Southern region is implementing 15 key traffic projects with demand for stone materials for these 15 projects of about 21.5 million m3. Up to now, 4.6 million m3 have been brought to the construction site, the remaining volume that needs to be mobilized is 16.9 million m3.

The component project 1 Bien Hoa - Vung Tau Expressway, currently the total demand for the road material is 5.2 million m3, until now, the new construction site is 0.55 million m3, need to be continued. The custom of mobilizing 4.7 million m3 to level the road.

Mr. Vo Tan Duc - Chairman of Dong Nai Provincial People's Committee also said that in addition to Long Thanh airport, there are 6 key projects in the area including: Bien Hoa - Vung Tau Expressway, Ben Luc - Long Thanh Expressway, Dau Giay - Tan Phu Expressway, Tan Phu - Bao Loc Expressway, Ho Chi Minh City Ring Road 3, Ho Chi Minh City Ring Road 4 is under construction.

Through review, only construction stones can meet the needs of the province, while construction sand, sand and sand, embankment has not met the needs.

At the meeting, a representative of the construction unit said that access to construction material mines supplied to the Long Thanh airport construction project was also very difficult and proposed that the Ministry of Natural Resources and Environment and the Dong Nai Provincial People's Committee study to increase the capacity of construction material mines to meet the demand.

The representative of the construction unit also said that it is necessary to immediately establish a coordinating team on construction materials for key projects, especially the Long Thanh airport project, Bien Hoa - Vung Tau expressway, Ho Chi Minh City Ring Road 3, which are urgent and key national projects...

Bo truong Bo Tai nguyen va Moi truong Do Duc Duy phat bieu tai hoi nghi. Anh: HAC
Minister of Natural Resources and Environment Do Duc Duy spoke at the conference. Photo: HAC

Concluding the conference, Minister of Natural Resources and Environment Do Duc Duy said that it is necessary to immediately solve the problem of supply and demand for construction materials for key national transport projects in Dong Nai to quickly remove difficulties, speed up the progress of project implementation...

HÀ ANH CHIẾN
TIN LIÊN QUAN

Prime Minister wishes a Happy New Year to workers at the Ho Chi Minh City Ring Road 3 project

|

Dong Nai - Prime Minister Pham Minh Chinh visited and wished a happy new year to engineers and workers working at Nhon Trach Bridge, part of the 1A Ring Road 3 component project in Ho Chi Minh City.

Prime Minister gives lucky money to workers constructing Long Thanh airport

|

Dong Nai – Prime Minister Pham Minh Chinh wished a happy new year, gave gifts and lucky money to officials, engineers and workers who are working during Tet at Long Thanh airport.

Car suddenly reverses, Throwing a woman walking in a hospital in Hanoi

|

Hanoi - The pickup truck suddenly reversed and drove a woman walking in the grounds of Ha Dong General Hospital.

Mountainous commune in Nghe An owes 530 million VND for food and stationery

|

Nghe An - Many individuals submitted petitions to collect a debt of more than 530 million VND from Chau Tien Commune People's Committee (Nghe An), mainly arising before 2021.

Israel kills senior commander of the Coast Guard in Tehran

|

Israel said it killed the wartime chief of staff of Iran's Islamic Revolutionary Guard Corps in an airstrike in the capital Tehran.

The 200 billion VND villa and assets of Meritorious Artist Vu Luan - adopted child of Vu Linh

|

Meritorious Artist Vu Luan - adopted child of Vu Linh lives in a 200 billion VND villa with his Miss wife. He also owns many assets in common with his wife after marriage.

Exam scores, benchmarks for grade 10 in 2025 of provinces and cities

|

The list of provinces and cities announcing the 10th grade entrance exam scores for the 2025-2026 school year is updated quickly and accurately by Lao Dong.

F88 floated amid skepticism about bad debt and high loan costs

|

Listing is a big step forward for F88, but this enterprise still faces pressure from bad debt, high loan costs and expectations of transparency from the capital market.

Prime Minister wishes a Happy New Year to workers at the Ho Chi Minh City Ring Road 3 project

HÀ ANH CHIẾN |

Dong Nai - Prime Minister Pham Minh Chinh visited and wished a happy new year to engineers and workers working at Nhon Trach Bridge, part of the 1A Ring Road 3 component project in Ho Chi Minh City.

Prime Minister gives lucky money to workers constructing Long Thanh airport

HÀ ANH CHIẾN - NHƯ QUỲNH |

Dong Nai – Prime Minister Pham Minh Chinh wished a happy new year, gave gifts and lucky money to officials, engineers and workers who are working during Tet at Long Thanh airport.

Nhà thầu cao tốc Phan Thiết - Dầu Giây lo lắng tiến độ vì thiếu vật liệu

HÀ ANH CHIẾN |

Đồng Nai - Dự án cao tốc Phan Thiết - Dầu Giây được Bộ Giao thông vận tải giao tiến độ đưa vào vận hành khai thác trước ngày 30.4.2023. Tuy nhiên, đến nay dự án đang đứng trước nguy cơ trượt tiến độ do thiếu nguồn đất đắp thi công các hạng mục đường gom dân sinh... Các nhà thầu cũng rất lo lắng khi chưa được gia hạn các mỏ đất để tiếp tục thi công.