Removing obstacles to materials for key national transport projects

HÀ ANH CHIẾN |

In Dong Nai province, a conference was held to agree on solutions to ensure construction materials for the construction of key national transport projects in the area.

Implementing the Prime Minister's direction at the meeting on February 1, 2025, the Dong Nai Provincial People's Committee was requested to preside over and coordinate with the Ministry of Natural Resources and Environment and the Ministry of Public Security to resolve difficulties in materials - February 7, the Ministry of Natural Resources and Environment to coordinate with the Dong Nai Provincial People's Committee and relevant ministries and branches to organize the "Reunification of solutions to ensure construction materials for the construction of key national transport projects in Dong Nai province".

At the conference, Mr. Le Anh Tuan - Deputy Minister of Transport said that the Southern region is implementing 15 key traffic projects with demand for stone materials for these 15 projects of about 21.5 million m3. Up to now, 4.6 million m3 have been brought to the construction site, the remaining volume that needs to be mobilized is 16.9 million m3.

The component project 1 Bien Hoa - Vung Tau Expressway, currently the total demand for the road material is 5.2 million m3, until now, the new construction site is 0.55 million m3, need to be continued. The custom of mobilizing 4.7 million m3 to level the road.

Mr. Vo Tan Duc - Chairman of Dong Nai Provincial People's Committee also said that in addition to Long Thanh airport, there are 6 key projects in the area including: Bien Hoa - Vung Tau Expressway, Ben Luc - Long Thanh Expressway, Dau Giay - Tan Phu Expressway, Tan Phu - Bao Loc Expressway, Ho Chi Minh City Ring Road 3, Ho Chi Minh City Ring Road 4 is under construction.

Through review, only construction stones can meet the needs of the province, while construction sand, sand and sand, embankment has not met the needs.

At the meeting, a representative of the construction unit said that access to construction material mines supplied to the Long Thanh airport construction project was also very difficult and proposed that the Ministry of Natural Resources and Environment and the Dong Nai Provincial People's Committee study to increase the capacity of construction material mines to meet the demand.

The representative of the construction unit also said that it is necessary to immediately establish a coordinating team on construction materials for key projects, especially the Long Thanh airport project, Bien Hoa - Vung Tau expressway, Ho Chi Minh City Ring Road 3, which are urgent and key national projects...

Bo truong Bo Tai nguyen va Moi truong Do Duc Duy phat bieu tai hoi nghi. Anh: HAC
Minister of Natural Resources and Environment Do Duc Duy spoke at the conference. Photo: HAC

Concluding the conference, Minister of Natural Resources and Environment Do Duc Duy said that it is necessary to immediately solve the problem of supply and demand for construction materials for key national transport projects in Dong Nai to quickly remove difficulties, speed up the progress of project implementation...

HÀ ANH CHIẾN
TIN LIÊN QUAN

Prime Minister wishes a Happy New Year to workers at the Ho Chi Minh City Ring Road 3 project

|

Dong Nai - Prime Minister Pham Minh Chinh visited and wished a happy new year to engineers and workers working at Nhon Trach Bridge, part of the 1A Ring Road 3 component project in Ho Chi Minh City.

Prime Minister gives lucky money to workers constructing Long Thanh airport

|

Dong Nai – Prime Minister Pham Minh Chinh wished a happy new year, gave gifts and lucky money to officials, engineers and workers who are working during Tet at Long Thanh airport.

The cash flow of real estate businesses has not improved

|

HCMC - The operating cash flow of real estate businesses continues to decline while debt increases sharply.

List of self-employed companies of large securities companies

|

The self-made list of stock giants in 2024 reflects the adjustment in investment strategies, aiming to optimize profits and control risks.

Champions League 1/8 draw results: Liverpool vs PSG

|

Results of the draw for matches in the round of 16, quarter-finals and semi-finals of the Champions League 2024-2025.

HCMC tightens protection of State secrets when streamlining the apparatus

|

HCMC - When cadres and party members quit their jobs, change jobs or retire, they must hand over all confidential documents and commit not to disclose information.

Disciplinary Warning for former Chairman of Ha Nam Provincial People's Committee

|

The Prime Minister disciplined Mr. Nguyen Xuan Dong, former Chairman of the People's Committee of Ha Nam province, with a Warning for violations and shortcomings.

Hanoi FC beat Hoang Anh Gia Lai thanks to playing with one more player

|

Hanoi FC defeated Hoang Anh Gia Lai 3-0 in round 14 of V.League 2024-2025, taking place on the afternoon of February 21.

Prime Minister wishes a Happy New Year to workers at the Ho Chi Minh City Ring Road 3 project

HÀ ANH CHIẾN |

Dong Nai - Prime Minister Pham Minh Chinh visited and wished a happy new year to engineers and workers working at Nhon Trach Bridge, part of the 1A Ring Road 3 component project in Ho Chi Minh City.

Prime Minister gives lucky money to workers constructing Long Thanh airport

HÀ ANH CHIẾN - NHƯ QUỲNH |

Dong Nai – Prime Minister Pham Minh Chinh wished a happy new year, gave gifts and lucky money to officials, engineers and workers who are working during Tet at Long Thanh airport.

Nhà thầu cao tốc Phan Thiết - Dầu Giây lo lắng tiến độ vì thiếu vật liệu

HÀ ANH CHIẾN |

Đồng Nai - Dự án cao tốc Phan Thiết - Dầu Giây được Bộ Giao thông vận tải giao tiến độ đưa vào vận hành khai thác trước ngày 30.4.2023. Tuy nhiên, đến nay dự án đang đứng trước nguy cơ trượt tiến độ do thiếu nguồn đất đắp thi công các hạng mục đường gom dân sinh... Các nhà thầu cũng rất lo lắng khi chưa được gia hạn các mỏ đất để tiếp tục thi công.