Hanoi to open a 50m wide road connecting Cau Giay to Nguyen Trai

SÓNG HỮU |

Hanoi - 4 sections of Ring Road 2.5 when completed will connect Cau Giay road with Nguyen Trai, reducing traffic pressure for Ring Road 2, Ring Road 3.

Ring Road 2.5 section from Cau Giay street to Nguyen Trai street is divided into 6 sections, with a total length of more than 5km, cross-section from 40-50m.

To date, 2 sections have been completed and put into use, including the section from Duong Dinh Nghe street to Vu Pham Ham (about 1.47km long) and the section from Tran Duy Hung - Nguy Nhu Kon Tum about 1km long.

a
Hanoi Ring Road 2.5, Duong Dinh Nghe - Vu Pham Ham section, nearly 1.5km long, has been completed and put into use many years ago. Photo: Song Huu
a
This section has a cross-section of 40-50m. Photo: Song Huu

For the remaining 4 sections, the city has directed Cau Giay, Yen Hoa, and Thanh Xuan wards to deploy land acquisition and site clearance to complete construction in 2026.

Among these, there is a section from Cau Giay street to Dich Vong New Urban Area, 420m long, deployed many years ago but stalled due to site clearance problems.

a
Ring Road 2.5, Cau Giay to Dich Vong New Urban Area section, 420m long, has been implemented for many years but has not been completed due to site clearance issues. Photo: Song Huu

Although Cau Giay Ward People's Committee has propagated, mobilized, and dialogued, to date, many households have received compensation money but have not relocated or handed over land; some other households have not agreed to receive money due to problems with land unit prices as well as supplementary resettlement policies.

Cau Giay Ward People's Committee said that it will coordinate with relevant units to inspect and consider stopping the supply of electricity, water, telecommunications and television information, and corrugated iron fences in the site clearance area.

In case of non-compliance with site handover, Cau Giay Ward People's Committee will assign relevant units to prepare dossiers and organize land recovery coercion according to regulations, to be completed in the first quarter of 2026.

a
Ring Road 2.5 intersection with Pham Van Bach street, afternoon of January 7, 2026. Photo: Song Huu

The remaining 3 sections include the section from Dich Vong New Urban Area - Duong Dinh Nghe (Cau Giay ward); Vu Pham Ham - Tran Duy Hung (Yen Hoa ward); Nguy Nhu Kon Tum - Nguyen Trai (Thanh Xuan ward) with a total length of about 2.26km.

The city spent about 8,402 billion VND to implement 3 sections of the above route, of which construction costs are 488 billion VND, and the rest is site clearance.

Cau Giay, Yen Hoa, Thanh Xuan wards are assigned to be investors of compensation and support component projects, technical infrastructure works; construction investment component projects invested by the Hanoi Traffic Works Investment Management Board.

a
Ring Road 2.5 section of Dich Vong - Duong Dinh Nghe New Urban Area, about 710m long, will be built in the near future. Photo: Song Huu

According to Politburo Member, Hanoi Party Secretary Nguyen Duy Ngoc, Ring Road 2.5 plays an important role in the Hanoi Capital's transportation system, contributing to diverting traffic flow and reducing pressure on main roads such as Ring Road 2 and Ring Road 3.

This road not only promotes socio-economic development but is also a key solution to solve traffic congestion bottlenecks. However, this project has been prolonged for many years and has not been completed.

Secretary of the Hanoi City Party Committee requested the Party Committee of the City People's Committee to direct the City People's Committee, departments, branches, Traffic Construction Investment Project Management Board; Party committees and authorities of communes and wards to clearly define political responsibilities to complete site clearance and complete the entire project in 2026.

SÓNG HỮU
RELATED NEWS

Many households do not comply with the direction on the Ring Road 2.5 project

|

Hanoi - Many households have not terminated or stopped leasing or lending houses and land within the Ring Road 2.5 project area as directed by Cau Giay ward.

Hanoi is about to enforce land recovery to build Ring Road 2.5, expanding a vital road

|

Hanoi - Households that intentionally do not hand over land for the Ring Road 2.5 construction project, expanding National Highway 6 will be subject to land recovery coercion according to regulations.

Hanoi cuts off electricity and water, coerces land recovery to build Ring Road 2.5

|

Hanoi - Cau Giay Ward will implement tough measures against households that intentionally do not hand over land for the Ring Road 2.5 project.

Ministry of Public Security informs about ensuring security and order to serve the 14th Party Congress

|

On the morning of January 10, the Ministry of Public Security will organize a launching ceremony and drills of security and order assurance plans to serve the 14th Party Congress.

Stock market adjusts after strong rally

|

Strong selling pressure suddenly appeared, causing the stock market not to maintain an impressive streak of gains.

Central Mass Mobilization Associations continue to streamline their apparatus

|

Mass organizations continue to implement the arrangement of organizational structure at the central level in the direction of streamlining and operating effectively.

2 people died in a 7-story house fire in Hanoi

|

Hanoi - On January 8, a house fire occurred on Le Loi street (Ha Dong ward), killing 2 people and injuring 1 person.

Cambodia dissolves bank of fraud boss Chen Zhi

|

After fraud boss Chen Zhi was arrested, Cambodia ordered the dissolution of Prince Bank of this subject.

Many households do not comply with the direction on the Ring Road 2.5 project

SÓNG HỮU |

Hanoi - Many households have not terminated or stopped leasing or lending houses and land within the Ring Road 2.5 project area as directed by Cau Giay ward.

Hanoi is about to enforce land recovery to build Ring Road 2.5, expanding a vital road

SÓNG HỮU |

Hanoi - Households that intentionally do not hand over land for the Ring Road 2.5 construction project, expanding National Highway 6 will be subject to land recovery coercion according to regulations.

Hanoi cuts off electricity and water, coerces land recovery to build Ring Road 2.5

SÓNG HỮU |

Hanoi - Cau Giay Ward will implement tough measures against households that intentionally do not hand over land for the Ring Road 2.5 project.