Hanoi reclaims land to widen road to 40-50m, capital of nearly VND3,380 billion

SÓNG HỮU |

Hanoi - The investor is speeding up the site clearance progress to implement the project to expand Road 70, 4.95km long, with a total capital of nearly VND 3,380 billion.

The project to build Provincial Road 70 was approved by the Hanoi People's Committee in March 2024. The project has a total investment of more than VND 3,377 billion, with the People's Committee of Tay Mo Ward as the investor.

The expanded section is about 4.95km long, section 1 from Trinh Van Bo Street to Nga Bridge is 3.25km long, with a cross-section of 50m; section 2 from Thang Long Avenue to Ngo Thi Nham Street is about 1.7km long, with a cross-section of 40m.

The total area of recovered land for the project is 229,319 sixm2, of which Xuan Phuong ward is about 140,885.3m2 (accounting for 61.4%); Son Dong commune is 19,554.7m2 (accounting for 8.6%); Tay Mo ward is 68,879.6m2 (accounting for 30%).

d
Site clearance is the biggest obstacle for the Hanoi Road 70 project. Photo: Song Huu

According to the representative of the Tay Mo Ward Infrastructure - Investment Project Management Board (representative of the investor), the project is implementing 3 construction packages and 1 survey consulting package, developing construction drawings for moving floating underground works.

The current difficulties and problems of the project are mainly related to compensation, support, and resettlement for site clearance.

Currently, the Board is carrying out the work of assigning land, not having a plan to arrange resettlement land fund, not yet relocating floating underground technical infrastructure works, leading to impacts on the progress of package No. 29 (construction of works and ensuring traffic safety from Trinh Van Bo Street to the railway overpass) and part of package No. 30 (construction of works and ensuring traffic safety from the railway overpass to Nga Bridge).

s
A section of Road 70 has been expanded. Photo: Song Huu
s
A concrete block blocks the road, endangering vehicles participating in traffic. Photo: Huu Chanh

There are other problems affecting the project's progress such as temporary tents, means of property, and violating items on the road surface and sidewalks that have been constructed by the Investment Project to build part of Road 70 (from Nga Bridge to the end of the International Education Village project) and the road around the International Education Village in Xuan Phuong Ward, which have not yet been relocated.

In the coming time, the People's Committee of Tay Mo Ward will work with the People's Committees of Xuan Phuong and Son Dong Wards to review and determine the resettlement needs and land funds for resettlement under the project, thereby serving as a basis for synthesizing reports to the City People's Committee and departments and branches according to regulations.

d
Road 70 is narrow and often congested. Photo: Song Huu

Vice Chairman of Tay Mo Ward People's Committee Nguyen Tien Hung emphasized that site clearance work will be implemented publicly and transparently. All policies and prices will be clearly listed. The ward government will apply all mechanisms and policies according to the provisions of law to ensure the best and most beneficial rights for the people.

At the same time, the locality will closely coordinate with units to prepare the best resettlement plans, ensuring synchronous infrastructure, so that people can soon stabilize their lives.

Regarding the proposal for compensation for resettlement by land, Mr. Nguyen Tien Hung said that the ward will consider comprehensively to ensure maximum benefits for households subject to site clearance that are eligible for resettlement by land.

"The Ward People's Committee will maintain a regular, direct dialogue mechanism. We will handle each specific case, not avoid it, in the spirit of openness and the rule of law. All problems of the people will be answered and resolved thoroughly" - Mr. Nguyen Tien Hung said.

The People's Committee of Tay Mo Ward is committed to implementing on schedule and urgently removing all obstacles to ensure the project will be completed within the next 3 years.

SÓNG HỮU
RELATED NEWS

Putting into use 800m of the arterial road expansion project in Hanoi in 2025

|

Hanoi - The 800m project to upgrade and expand National Highway 32 through Quang Oai commune is expected to be completed in 2025, helping people travel smoothly.

Contrasting extreme at key transport projects in the South of Hanoi

|

Hanoi - While the Ring Road 2.5 and Kim Dong underpass projects are accelerating, the Tam Trinh and Linh Nam road expansion projects are still sluggish due to land clearance problems.

People hope to receive adequate compensation when Hanoi reclaims land to build Tu Lien bridge

|

Hanoi reclaims land to build Tu Lien bridge, people hope to have a satisfactory compensation, support and resettlement policy, ensuring their rights according to regulations.

Personnel transfer and appointment in Phu Tho, Hue, Quang Tri, Dong Nai

|

Hue, Quang Tri, Phu Tho, Dong Nai... are localities that have just implemented decisions to transfer, appoint, and appoint personnel last week.

Nghe An traffic police break down doors to rescue 11 people in a house fire

|

Nghe An - In the early morning of January 11, the working group of Dien Chau Traffic Police Station promptly discovered and broke down the door to rescue 11 people trapped in a house fire in Hoang Mai ward.

Da Nang people celebrate Tet in the warm home of Quang Trung Campaign

|

Da Nang - The wooden house of Mr. Nguyen Dinh (Thuong Duc commune) swept away by floods has been replaced by a solid shelter during the Quang Trung Campaign.

Forecast of low pressure combined with extremely strong cold air coming soon

|

Extremely strong cold air is forecast to be coming down, in the context of 2 consecutive low pressures expected to appear near the East Sea.

The truth about Venezuela hiding 60 billion USD of Bitcoin

|

Rumors that Venezuela may hold up to 60 billion USD of Bitcoin are spreading, but experts believe that this number is still a big question mark.

Putting into use 800m of the arterial road expansion project in Hanoi in 2025

HỮU CHÁNH - ĐẶNG TIẾN |

Hanoi - The 800m project to upgrade and expand National Highway 32 through Quang Oai commune is expected to be completed in 2025, helping people travel smoothly.

Contrasting extreme at key transport projects in the South of Hanoi

SÓNG HỮU |

Hanoi - While the Ring Road 2.5 and Kim Dong underpass projects are accelerating, the Tam Trinh and Linh Nam road expansion projects are still sluggish due to land clearance problems.

People hope to receive adequate compensation when Hanoi reclaims land to build Tu Lien bridge

SÓNG HỮU |

Hanoi reclaims land to build Tu Lien bridge, people hope to have a satisfactory compensation, support and resettlement policy, ensuring their rights according to regulations.